Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Replace forced air furnace. Date: November 13, 2001 Contractor: Welzig Heating And Air Client: Of City | Applicant: Welzig Heating & Air | Permit type: Mechanical | Permit status: Cmp | Completion date: April 25, 2002 | Current use: Multifamily dwe | |||||
SCORE 100 Remove existing shingles and replace with landmark dimensional shingles. Date: August 21, 2003 Contractor: M B Roofing Inc Client: Mary Harvey | Applicant: M B Roofing, Inc. | Permit type: Roofing | Permit status: Cmp | Completion date: September 2, 2003 | Current use: Multifamily dwe | |||||
SCORE 98 Water heater replacement Date: April 18, 2007 Contractor: Boulder Housing Partners Applicant: Boulder Housing Partners | Permit type: Mechanical | Permit status: Cmp | Completion date: June 19, 2007 | Current use: Multifamily dwe | |||||
SCORE 95 Mechanical permit to replace unit heater unit #3 Date: July 17, 2007 Contractor: Welzig Mechanical Client: Of City | Applicant: Welzig Mechanical | Permit type: Mechanical | Permit status: Cmp | Completion date: December 8, 2008 | Current use: Multifamily dwe | |||||
SCORE 98 Replace hot water heater in unit #1 Date: February 19, 2008 Contractor: Boulder Housing Partners Applicant: Boulder Housing Partners | Permit type: Mechanical | Permit status: Cmp | Completion date: July 1, 2008 | Current use: Multifamily dwe | |||||
SCORE 95 Installation of cedar privacy fence along front and northern side yard of condo building. Fence to vary from 4 to 6-feet in height, 2 feet total length. Date: October 10, 2008 Contractor: Monroe Fence Co Client: Arthur 3520.0 | Applicant: Monroe Fence Co | Permit type: Fence | Permit status: Cmp | Completion date: August 30, 2013 | Current use: Multifamily dwe | |||||
SCORE 100 Replace faulted primary cable. Excavate from pole to property Date: February 17, 2010 Contractor: Xcel Energy Client: Inc Sherrelwood | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Raise telephone ped - qwest address 2712 kalmia Date: March 16, 2010 Contractor: Qwest Comm Centurylink Client: Inc Sherrelwood | Applicant: Qwest Comm/centurylink | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 82 Replacement forced air furnace in closet, 80k btu. Date: September 14, 2010 Contractor: U. S. Engineering Company Client: Of City | Applicant: U. S. Engineering Company | Permit type: Mechanical | Permit status: Cmp | Completion date: November 2, 2010 | Current use: Multifamily dwe | |||||
SCORE 99 Total tear-off & reroof of sfd, 26 squares of asphalt shingles on a pitch represented as 6 12. Shingles to comply with astm d225 or d3462 and d3161 class f. Overlay not allowed - see section r907. 3 (specifically item 4) of 2006 irc. Mid-roof inspection required if pitch less than 4 12. Date: July 22, 2013 Contractor: Nixon Roofing Client: Inc Sherrelwood | Applicant: Nixon Roofing | Permit type: Roofing | Permit status: Cmp | Completion date: January 7, 2014 | Current use: Townhomes, exis | |||||
SCORE 99 Total tear-off & reroof of sfd, 28 squares of asphalt shingles on a pitch represented as 6 12. Shingles to comply with astm d225 or d3462 and d3161 class f. Overlay not allowed - see section r907. 3 (specifically item 4) of 2006 irc. Mid-roof inspection required if pitch less than 4 12. Date: July 22, 2013 Contractor: Nixon Roofing Client: Inc Sherrelwood | Applicant: Nixon Roofing | Permit type: Roofing | Permit status: Cmp | Completion date: January 7, 2014 | Current use: Townhomes, exis | |||||
SCORE 100 Replace cable via bore. 3 bore pits, 14 bore holes. Majority of work within easements at 2701 iris. Date: January 13, 2015 Contractor: Xcel Energy Client: Inc Sherrelwood | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 99 Remove existing shinlges and re-roof multi-family building with dimensional shingles. 26 squares, roof pitch represented by contractor to be 5:12. Date: February 9, 2015 Contractor: Nixon Roofing Client: Inc Sherrelwood | Applicant: Nixon Roofing | Permit type: Roofing | Permit status: Cmp | Completion date: February 23, 2015 | Current use: Multifamily dwe | |||||
SCORE 99 Total tear off and reroof with 26. 66 squares of owens corning oakridge shingles on roof pitch represented as 5 12. Date: March 30, 2015 Contractor: Nixon Roofing Client: Inc Sherrelwood | Applicant: Nixon Roofing | Permit type: Roofing | Permit status: Cmp | Completion date: April 2, 2015 | Current use: Multifamily dwe | |||||
SCORE 95 Building 35 (4 units). Remodel (4 sq. Ft. Per unit). Scope of work includes associated meps to include ventilating equipment. Proposed community center (building 3525) under separate permit and any sitework, signage, walls, and fire sprinkling work under separate permit if necessary. See lur2015-00023 approval. Client: Of City | Applicant: Palace Construction Co Inc | Permit type: Building, electrical | Permit status: Act | Current use: Multifamily dwe | |||||
SCORE 100 Building 35 (6 units). Remodel (4 sq. Ft. Per unit). Scope of work includes associated meps to include ventilating equipment. Proposed community center (building 3525) under separate permit and any sitework, signage, walls, and fire sprinkling work under separate permit if necessary. See lur2015-00023 approval. Client: Of City | Applicant: Of City | Permit type: Building, electrical | Permit status: Act | Current use: Multifamily dwe | |||||
SCORE 99 Total tear-off & reroof of sfd, 26 squares of asphalt shingles on a pitch represented as 6 12. Shingles to comply with astm d225 or d3462 and d3161 class f. Overlay not allowed - see section r907. 3 (specifically item 4) of 2006 irc. Mid-roof inspection required if pitch less than 4 12. Client: Inc Sherrelwood | Permit type: Roofing | Permit status: Cmp | Completion date: January 7, 2014 | Current use: Townhomes, existing | Permit id: Pmt2013-03395 | |||||
SCORE 99 Total tear-off & reroof of sfd, 28 squares of asphalt shingles on a pitch represented as 6 12. Shingles to comply with astm d225 or d3462 and d3161 class f. Overlay not allowed - see section r907. 3 (specifically item 4) of 2006 irc. Mid-roof inspection required if pitch less than 4 12. Client: Inc Sherrelwood | Permit type: Roofing | Permit status: Cmp | Completion date: January 7, 2014 | Current use: Townhomes, existing | Permit id: Pmt2013-03396 | |||||
SCORE 95 Replace forced air furnace. Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: April 25, 2002 | Current use: Multifamily dwellings, existing | Permit id: Pmt2001-05007 | |||||
Replace cable via bore. 3 bore pits, 14 bore holes. Majority of work within easements at 2701 iris. Date: January 26, 2015 Client: Inc Sherrelwood | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2014-04720 | |||||
Replace faulted primary cable. Excavate from pole to property Date: February 17, 2010 Client: Inc Sherrelwood | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-00543 | |||||
Raise telephone ped - qwest address 2712 kalmia Date: March 16, 2010 Client: Inc Sherrelwood | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-00905 | |||||
SCORE 82 Replacement forced air furnace in closet, 80k btu. Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: November 2, 2010 | Current use: Multifamily dwellings, existing | Permit id: Pmt2010-03949 | |||||
SCORE 98 Replace hot water heater in unit #1 Permit type: Mechanical | Permit status: Cmp | Completion date: July 1, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-00557 | |||||
SCORE 98 Water heater replacement Permit type: Mechanical | Permit status: Cmp | Completion date: June 19, 2007 | Current use: Multifamily dwellings, existing | Permit id: Pmt2007-01407 | |||||
SCORE 99 Remove existing shinlges and re-roof multi-family building with dimensional shingles. 26 squares, roof pitch represented by contractor to be 5:12. Client: Inc Sherrelwood | Permit type: Roofing | Permit status: Cmp | Completion date: February 23, 2015 | Current use: Multifamily dwellings, existing | Permit id: Pmt2015-00418 | |||||
SCORE 99 Total tear off and reroof with 26. 66 squares of owens corning oakridge shingles on roof pitch represented as 5 12. Client: Inc Sherrelwood | Permit type: Roofing | Permit status: Cmp | Completion date: April 2, 2015 | Current use: Multifamily dwellings, existing | Permit id: Pmt2015-01113 | |||||
SCORE 95 Building 35 (4 units). Remodel (4 sq. Ft. Per unit). Scope of work includes associated meps to include ventilating equipment. Proposed community center (building 3525) under separate permit and any sitework, signage, walls, and fire sprinkling work under separate permit if necessary. See lur2015-00023 approval. Client: Of City | Permit type: Building, electrical, mechanical, plumbing | Permit status: Iss | Current use: Multifamily dwellings, remodel | Permit id: Pmt2015-03603 | |||||
SCORE 95 Building 35 (6 units). Remodel (4 sq. Ft. Per unit). Scope of work includes associated meps to include ventilating equipment. Proposed community center (building 3525) under separate permit and any sitework, signage, walls, and fire sprinkling work under separate permit if necessary. See lur2015-00023 approval. Client: Of City | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: December 6, 2016 | Current use: Multifamily dwellings, remodel | Permit id: Pmt2015-03605 | |||||
SCORE 95 Building 3510. Installation of front and rear porches and individual storage sheds for all 6 units in a multi-family building, new siding and windows throughout. Client: Of City | Permit type: Building | Permit status: Cmp | Completion date: December 6, 2016 | Current use: Multifamily dwellings, existing, shed, n | Permit id: Pmt2015-03777 | |||||
SCORE 95 Building 3500. Installation of front and rear porches and individual storage sheds for 4 all units in a multi-family building and installation of 8 additional storage sheds on eastern elevation of building, new siding and windows throughout. Client: Of City | Permit type: Building | Permit status: Cmp | Completion date: December 5, 2016 | Current use: Multifamily dwellings, existing, shed, n | Permit id: Pmt2015-03781 | |||||
SCORE 72 Install storm sewer inlet in easement & tie into existing storm main Date: February 15, 2017 Contractor: Anaya Concrete Corp Client: Communitie Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2017-00500 | |||||
SCORE 100 Remove existing shingles and replace with landmark dimensional shingles. Client: Mary Harvey | Permit type: Roofing | Permit status: Cmp | Completion date: September 2, 2003 | Current use: Multifamily dwellings, existing | Permit id: Pmt2003-03555 | |||||
SCORE 95 Mechanical permit to replace unit heater unit #3 Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: December 8, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2007-02969 | |||||
SCORE 95 Installation of cedar privacy fence along front and northern side yard of condo building. Fence to vary from 4 to 6-feet in height, 2 feet total length. Client: Arthur | Permit type: Fence | Permit status: Cmp | Completion date: August 30, 2013 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-04517 |