SCORE 86 75 State St Boston Ma 02109 Remove pendent sprinkler heads.; replace with upright sprinkler heads to accomodate removal of ceiling. Date: November 14, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk100057 | Parcel: 0303860000 | |||||
SCORE 86 39 Brighton Av Allston Ma 02134 Relocate approximately (13) wet sprinkler heads to accommodate new construction renovation weekends only 1st floor Date: September 28, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk44286 | |||||
SCORE 86 115 Stuart St Boston Ma 02116 Relocate approximately (40) wet sprinkler heads to accommodate new construction renovation 1st floor Date: February 25, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk64188 | |||||
SCORE 86 5 Huntington Av Mission Hill Ma 02115 Install new sprinkler system 2nd floor only building has no fire sprinkler system Date: August 9, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk36752 | Parcel: 0402024000 | |||||
SCORE 86 City Sq Charlestown Ma 02129 Relocate approx wet sprinklers to accodomate new construction. Work to be done per nfpa stands one floor zone at a time. Date: September 27, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk97425 | Parcel: 0203711000 | |||||
SCORE 86 Franklin St Boston Ma 02110 Relocate approx. (10) wet sprinkler heads to accommodate new construction &; renovation. Work to be done one floor zone at a time. Work to be done per nfpa stands. 7 cmr. Date: July 10, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk129590 | |||||
SCORE 86 255 State St Boston Ma 02109 Relocate 48 wet sprinklers onthe 3rd fl relocate 29 wet sprinklers on the 7th fl relocate 16 wet sprinklers on the 2nd fl to accodomate new construction Date: August 17, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk90656 | Parcel: 0303821000 | |||||
SCORE 86 53 State St Boston Ma 02109 Relocate approximately (36) wet sprinkler heads to accommodate new construction renovation work performed off hours 12th floor Date: October 6, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk44969 | |||||
SCORE 86 1 Federal St Boston Ma 02110 Relocate approximately (25) wet sprinklers to accommodate new construction renovation 6th floor work to be done one floor zone at a time per nfpa 13 stands. Date: August 4, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk35762 | Parcel: 0304406000 | |||||
SCORE 86 101 Federal St Boston Ma 02110 Relocate approx. (28) wet sprinkler heads to accommodate new construction &; renovation. Work to be done one floor zone at a time. Work to be done per nfpa stands. 7 cmr. Date: April 17, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk129593 | Parcel: 0304199000 | |||||
SCORE 86 115 Stuart St Boston Ma 02116 Relocate modify add (54) wet sprinklers to accommodate new construction renovation on 1st floor. Work to be done per nfpa stands. One floor zone at a time. Date: January 30, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk114397 | |||||
SCORE 86 48 Brighton Av Allston Ma 02134 Replace sprinkler line feeding common areas previously removed by others basement Date: January 3, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk57144 | Parcel: 2100760000 | |||||
SCORE 86 175 Berkeley St Boston Ma 02116 Relocate approx. (6) wet sprinkler heads on the 4th floor to accommodate new construction renovation. Work to be done per nfpa stands. Work to be done one floor zone at a time. Date: July 12, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk84775 | |||||
SCORE 86 225 Franklin St Boston Ma 02110 Relocate approx 26 wet sprinkler heads to accomodate new constructionrenovation per nfpa 13 stand. 7 cmr.; work to be done one floor zone at a time. Date: March 8, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk66390 | Parcel: 0304134000 | |||||
SCORE 86 529 Main St Charlestown Ma 02129 Relocate approximately (13) wet sprinkler to accommodate new construction renovation 1st floor work to be done one floor zone at a time per nfpa 13 stands. Date: August 4, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk35767 | Parcel: 0201829000 | |||||
SCORE 86 53 State St Boston Ma 02109 Relocate approx. (26) wet sprinklers on 4th floor to accommodate new construction renovation. Work to be done one floor zone at a time. Work to be done per nfpa stands. 7 cmr. Date: April 17, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit status: Na | Permit id: Sprk129605 | |||||
SCORE 86 75 State St Boston Ma Remove pendent sprinkler heads.; replace with upright sprinkler heads to accomodate removal of ceiling. Date: November 14, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: World Financial Properties | Permit type: Bfd sprinkler system | Permit id: Sprk100057 | Parcel: 0303860000 | |||||
SCORE 86 5 Huntington Av Mission Hill Ma Install new sprinkler system 2nd floor only building has no fire sprinkler system Date: August 9, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: Wentworth Institute | Permit type: Bfd sprinkler system | Permit id: Sprk36752 | Parcel: 0402024000 | |||||
SCORE 86 City Sq Charlestown Ma Relocate approx wet sprinklers to accodomate new construction. Work to be done per nfpa stands one floor zone at a time. Date: September 27, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: City Sq Trust | Permit type: Bfd sprinkler system | Permit id: Sprk97425 | Parcel: 0203711000 | |||||
SCORE 86 Franklin St Boston Ma Relocate approx. (10) wet sprinkler heads to accommodate new construction &; renovation. Work to be done one floor zone at a time. Work to be done per nfpa stands. 7 cmr. Date: July 10, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk129590 | |||||
SCORE 86 255 State St Boston Ma Relocate 48 wet sprinklers onthe 3rd fl relocate 29 wet sprinklers on the 7th fl relocate 16 wet sprinklers on the 2nd fl to accodomate new construction Date: August 17, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: Pembroke R E | Permit type: Bfd sprinkler system | Permit id: Sprk90656 | Parcel: 0303821000 | |||||
SCORE 86 101 Federal St Boston Ma Relocate approx. (28) wet sprinkler heads to accommodate new construction &; renovation. Work to be done one floor zone at a time. Work to be done per nfpa stands. 7 cmr. Date: April 17, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: Transwestern Federal Llc | Permit type: Bfd sprinkler system | Permit id: Sprk129593 | Parcel: 0304199000 | |||||
SCORE 86 48 Brighton Av Allston Ma Replace sprinkler line feeding common areas previously removed by others basement Date: January 3, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk57144 | Parcel: 2100760000 | |||||
SCORE 86 39 Brighton Av Allston Ma Relocate approximately (13) wet sprinkler heads to accommodate new construction/ renovation weekends only 1st floor Date: September 28, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk44286 | |||||
SCORE 86 115 Stuart St Boston Ma Relocate approximately (40) wet sprinkler heads to accommodate new construction/ renovation 1st floor Date: February 25, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk64188 | |||||
SCORE 86 53 State St Boston Ma Relocate approximately (36) wet sprinkler heads to accommodate new construction/ renovation work performed off hours 12th floor Date: October 6, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk44969 | |||||
SCORE 86 529 Main St Charlestown Ma Relocate approximately (13) wet sprinkler to accommodate new construction/ renovation 1st floor work to be done one floor zone at a time per nfpa 13 stands. Date: August 4, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: The Flatley Co | Permit type: Bfd sprinkler system | Permit id: Sprk35767 | Parcel: 0201829000 | |||||
SCORE 86 115 Stuart St Boston Ma Relocate modify add (54) wet sprinklers to accommodate new construction / renovation on 1st floor. Work to be done per nfpa stands. One floor zone at a time. Date: January 30, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk114397 | |||||
SCORE 86 175 Berkeley St Boston Ma Relocate approx. (6) wet sprinkler heads on the 4th floor to accommodate new construction / renovation. Work to be done per nfpa stands. Work to be done one floor zone at a time. Date: July 12, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk84775 | |||||
SCORE 86 53 State St Boston Ma Relocate approx. (26) wet sprinklers on 4th floor to accommodate new construction / renovation. Work to be done one floor zone at a time. Work to be done per nfpa stands. 7 cmr. Date: April 17, 2012 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Permit type: Bfd sprinkler system | Permit id: Sprk129605 | |||||
SCORE 86 1 Federal St Boston Ma Relocate approximately (25) wet sprinklers to accommodate new construction/ renovation 6th floor work to be done one floor zone at a time per nfpa 13 stands. Date: August 4, 2010 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: The Landmark Condo Assn | Permit type: Bfd sprinkler system | Permit id: Sprk35762 | Parcel: 0304406000 | |||||
SCORE 86 225 Franklin St Boston Ma Relocate approx 26 wet sprinkler heads to accomodate new construction/renovation per nfpa 13 stand. 7 cmr.; work to be done one floor zone at a time. Date: March 8, 2011 Contractor: Barry C. Rose Barry Rose Fire Protection Llc Client: Two25 Franklin Owner Llc | Permit type: Bfd sprinkler system | Permit id: Sprk66390 | Parcel: 0304134000 |