SCORE 92 Temporary power pole Date: November 26, 2003 Contractor: Caltech Construction Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: May 24, 2004 | Permit id: 311260033 | |||||
SCORE 94 New pool and spa, standard plan#26077 Engineer: Dawn Pasol | Applicant: Wang Paul | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: November 29, 2004 | Permit id: 405120006 | |||||
SCORE 95 Install (n) roof-mounted solar photovoltaic system, 6. 3 kw, 21 panels, 1 inverter. Applicant: Kuo Stanley | Permit status: Finaled | Completion date: September 5, 2014 | Expiration date: July 29, 2015 | Permit id: 1406090066 | |||||
SCORE 95 Install roof mounted pv system 6. 3kw Date: July 29, 2014 Contractor: Pacific Stonegate Inc Applicant: Pacific Stonegate, Inc. Dba Solar Vast | Permit status: Finaled | Completion date: September 5, 2014 | Expiration date: July 29, 2015 | Permit id: 1407290029 | |||||
SCORE 100 Replace wall furnace Date: January 19, 2000 Contractor: B And W Furnace Service Applicant: B And W Furnace | Permit status: Finaled | Completion date: January 21, 2000 | Expiration date: July 17, 2000 | Permit id: 1190020 | |||||
SCORE 92 Plumbing for new sfr. Date: December 12, 2003 Contractor: Caltech Construction Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: June 9, 2004 | Permit id: 312120033 | |||||
SCORE 92 Connect new sft to public sewer. Date: December 12, 2003 Contractor: Caltech Construction Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: June 9, 2004 | Permit id: 312120010 | |||||
SCORE 92 New 1 story sfr. - 41 sq. Ft., att. Gar. - 6 s. F. Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: December 6, 2004 | Permit id: 310090024 | |||||
SCORE 92 Demo existing house 13 s. F. Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: January 13, 2004 | Expiration date: November 20, 2004 | Permit id: 311260032 | |||||
SCORE 92 Electrical for new sfr. Date: December 12, 2003 Contractor: Caltech Construction Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: June 9, 2004 | Permit id: 312120028 | |||||
SCORE 92 New 1 story sfr. - 41 sq. Ft., att. Gar. - 6 s. F. Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: December 6, 2004 | Permit id: 310090024 | |||||
SCORE 92 Demo existing house 13 s. F. Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: January 13, 2004 | Expiration date: November 20, 2004 | Permit id: 311260032 | |||||
SCORE 96 Install (n) roof-mounted solar photovoltaic system, 6. 3 kw, 21 panels, 1 inverter. Applicant: Kuo Stanley | Permit status: Finaled | Completion date: September 5, 2014 | Expiration date: July 29, 2015 | Permit id: 1406090066 | |||||
SCORE 92 Temporary power pole Date: November 26, 2003 Contractor: Caltech Construction, Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: May 24, 2004 | Permit id: 311260033 | |||||
SCORE 96 Install roof mounted pv system 6. 3kw Date: July 29, 2014 Contractor: Pacific Stonegate, Inc Applicant: Pacific Stonegate, Inc. Dba Solar Vast | Permit status: Finaled | Completion date: September 5, 2014 | Expiration date: July 29, 2015 | Permit id: 1407290029 | |||||
SCORE 92 Plumbing for new sfr. Date: December 12, 2003 Contractor: Caltech Construction, Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: June 9, 2004 | Permit id: 312120033 | |||||
SCORE 92 Connect new sft to public sewer. Date: December 12, 2003 Contractor: Caltech Construction, Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: June 9, 2004 | Permit id: 312120010 | |||||
SCORE 92 Electrical for new sfr. Date: December 12, 2003 Contractor: Caltech Construction, Inc Engineer: Samir Guirguis | Applicant: Guirguis Samir | Permit status: Finaled | Completion date: June 27, 2004 | Expiration date: June 9, 2004 | Permit id: 312120028 |