Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning use permit Date: February 12, 2008 Client: Nathex Trust | Permit status: Completed | Permit id: 129339 | |||||
Electrical permit Date: October 19, 2007 Client: Nathex Trust | Permit status: Completed | Permit id: 105265 | |||||
Alteration permit Date: August 19, 2009 Client: Nathex Trust | Permit status: Completed | Permit id: 228615 | |||||
Alteration permit Date: February 26, 2008 Client: Nathex Trust | Permit status: Expired | Permit id: 131865 | |||||
Alteration permit Date: October 21, 2014 Client: Nathex Trust | Permit status: Completed | Permit id: 533100 | |||||
Electrical permit Date: October 5, 2009 Client: Nathex Trust | Permit status: Completed | Permit id: 240746 | |||||
Administrative permit Date: April 13, 2012 Client: Nathex Trust | Permit status: Completed | Permit id: 398348 | |||||
Administrative permit Date: July 13, 2010 Client: Nathex Trust | Permit status: Completed | Permit id: 290585 | |||||
Electrical permit Date: June 30, 2011 Client: Nathex Trust | Permit status: Completed | Permit id: 347865 | |||||
Mechanical permit Date: April 4, 2012 Client: Sermarini Andrew J | Permit status: Revoked | Permit id: 385649 | |||||
Zoning use permit Date: August 11, 2009 Client: Nathex Trust | Permit status: Completed | Permit id: 221414 | |||||
Electrical permit Date: April 9, 2012 Client: Nathex Trust | Permit status: Completed | Permit id: 392438 | |||||
SCORE 56 Replace 20kw natural gas generator indoor with diesel kw generator outdoors on concrete pad. (east dist) Date: October 19, 2007 Contractor: Joseph Appleyard Iii Client: Nathex Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: January 23, 2008 | Permit id: 105265 | |||||
SCORE 100 Install 1 amp sub-panel for future house use as per 2005 nec (east district) addition permit required for branch circuit Date: October 5, 2009 Contractor: James Wilkins Client: Nathex Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: August 10, 2010 | Permit id: 240746 | |||||
SCORE 93 Power up temporary chillers - 4 volt now running on generator - customer has 208 volt available as per 2008 nec (east dist) permit expires days after date of issuance Date: June 30, 2011 Contractor: Cape Turnkey Corporation Client: Nathex Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: September 27, 2011 | Permit id: 347865 | |||||
SCORE 100 Amend permit number 385649 for correct address Date: April 13, 2012 Contractor: Precision Mech Client: Nathex Trust | Permit type: Administrative permit | Permit status: Completed | Completion date: August 23, 2012 | Permit id: 398348 | |||||
SCORE 56 Rewire burned out chiller units as per 2008 nec(apt complex)(east dist) Date: April 9, 2012 Contractor: David Secrest Client: Nathex Trust | Permit type: Electrical permit | Permit status: Completed | Completion date: July 26, 2012 | Permit id: 392438 | |||||
SCORE 56 For resolution of dept. Of l&i case# 426781 for the installation of an exterior exit stairway of wood frame construction w. Cast-in-place concrete footing & non-combustible railing to replace previous exterior exit stairway serving existing three (3) story above grade plane, w. Basement & rooftop structures, mixed-use multi-family building. Date: October 21, 2014 Contractor: Robert H Smith Jr Client: Nathex Trust | Permit type: Alteration permit | Permit status: Completed | Completion date: January 7, 2015 | Permit id: 533100 | |||||
SCORE 100 Remove and install 2 chillers as per plan. Date: April 4, 2012 Contractor: Precision Mech Client: Sermarini Andrew J | Permit type: Mechanical permit | Permit status: Revoked | Completion date: April 30, 2012 | Permit id: 385649 |