Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: April 11, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 334858 | |||||
Electrical permit Date: December 2, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 368963 | |||||
Suppression permit Date: February 15, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 320092 | |||||
Plumbing permit Date: October 26, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 305025 | |||||
New construction permit Date: July 1, 2010 Client: Phila Housing Authority | Client Company: Zia Rahman | Permit status: Completed | Permit id: 288711 | |||||
Zoning/use permit Date: February 16, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 257964 | |||||
Administrative permit Date: November 21, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 352164 | |||||
Administrative permit Date: May 16, 2013 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 471838 | |||||
Suppression permit Date: November 2, 2010 Client: Phila Housing Authority | Client Company: Zia Rahman | Permit status: Completed | Permit id: 306226 | |||||
Mechanical permit Date: November 23, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 370369 | |||||
Electrical permit Date: April 8, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 271450 | |||||
Zoning permit Date: June 29, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 265649 | |||||
Zoning permit Date: July 13, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 328490 | |||||
Demolition permit Date: February 16, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 257966 | |||||
Zoning/use permit Date: November 17, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 373956 | |||||
Permit for relocation of lot lines to create two lots from two lots for the complete demolition of all structures on the lot, lot a,(7200) for the erection of a one story structure (maximum height nte 21 feet) for use as a community building with computer rooms, community room, accessory office space, kitchen for preparing and serving of food, storage space with two(2) off street parking spaces, lot b (7208) for the erection of a two story semi-detached structure(maximum height nte 22. 4 feet) ada compliant residential duplex dwellings with two off street parking spaces each with an ornamental metal fencing. Date: May 10, 2011 Client: Philadelphia Housing Auth | Applicant: Kafi Lindsay, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: June 21, 2011 | Permit id: 15096 | |||||
Permit for the relocation of lot lines to create sixty (60) lots from fifty-three(53) deeded lots in one brt account number, for the demolition of all structures on the lot, for the erection of fifty (50) three story attached structures (lots 1 thru 3, lots 7 thru 18, lots 22 thru 36. Lots 38 thru 45, lots 47 thru 52, lots 54 thru 59,) each with one (1) interior off-street parking space, for the erection of nine (9) three (3) story ada compliant residential duplex dwellings. On lots 4, 21, 37, 46, 53 and 60, two (2) semi-detached structures (lots 19, 20), one detached structure (lot 60), each with two (2) interior off-street parking spaces with ada ramps. Buildings to include second floor roof overhangs. For the erection of a two (2) story structure for use as a community building with computer rooms, community room and accessory office, kitchen for preparing and serving of food, storage space with three off street parking spaces, including one handicapped accessible space (lot 5). Date: April 8, 2010 Client: Philadelphia Housing Auth | Applicant: Allison J. Levy, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: May 24, 2010 | Permit id: 11436 | |||||
Electrical permit Date: October 25, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 364915 | |||||
Zoning use permit Date: February 16, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 257964 | |||||
Mechanical permit Date: February 17, 2011 Client: Phila Housing Authority | Client Company: Zia Rahman | Permit status: Completed | Permit id: 318374 | |||||
Administrative permit Date: May 16, 2013 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 471838 | |||||
Administrative permit Date: November 21, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 352164 | |||||
Plumbing permit Date: April 11, 2011 Client: Phila Housing Authority | Client Company: Zia Rahman | Permit status: Completed | Permit id: 334866 | |||||
Demolition permit Date: February 16, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 257966 | |||||
Plumbing permit Date: January 19, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 257801 | |||||
New construction permit Date: July 1, 2010 Client: Phila Housing Authority | Client Company: Zia Rahman | Permit status: Completed | Permit id: 288711 | |||||
Zoning permit Date: July 13, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 328490 | |||||
Zoning permit Date: June 29, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 265649 | |||||
Electrical permit Date: April 8, 2010 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 271450 | |||||
Suppression permit Date: February 15, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 320092 | |||||
Suppression permit Date: November 2, 2010 Client: Phila Housing Authority | Client Company: Zia Rahman | Permit status: Completed | Permit id: 306226 | |||||
Zoning use permit Date: November 17, 2011 Client: Philadelphia Housing Auth | Permit status: Completed | Permit id: 373956 | |||||
Permit for relocation of lot lines to create two lots from two lots for the complete demolition of all structures on the lot, lot a,(7200) for the erection of a one story structure (maximum height nte 21 feet) for use as a community building with computer rooms, community room, accessory office space, kitchen for preparing and serving of food, storage space with two(2) off street parking spaces, lot b (7208) for the erection of a two story semi-detached structure(maximum height nte 22. 4 feet) ada compliant residential duplex dwellings with two off street parking spaces each with an ornamental metal fencing. Date: May 10, 2011 Client: Philadelphia Housing Auth | Applicant: Kafi Lindsay, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: June 21, 2011 | Permit id: 15096 | |||||
Permit for the relocation of lot lines to create sixty (60) lots from fifty-three(53) deeded lots in one brt account number, for the demolition of all structures on the lot, for the erection of fifty (50) three story attached structures (lots 1 thru 3, lots 7 thru 18, lots 22 thru 36. Lots 38 thru 45, lots 47 thru 52, lots 54 thru 59,) each with one (1) interior off-street parking space, for the erection of nine (9) three (3) story ada compliant residential duplex dwellings. On lots 4, 21, 37, 46, 53 and 60, two (2) semi-detached structures (lots 19, 20), one detached structure (lot 60), each with two (2) interior off-street parking spaces with ada ramps. Buildings to include second floor roof overhangs. For the erection of a two (2) story structure for use as a community building with computer rooms, community room and accessory office, kitchen for preparing and serving of food, storage space with three off street parking spaces, including one handicapped accessible space (lot 5). Date: April 8, 2010 Client: Philadelphia Housing Auth | Applicant: Allison J. Levy, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: May 24, 2010 | Permit id: 11436 | |||||
Amend permit # 352164 to include lawful occupancy as part of the community building. Date: May 16, 2013 Client: Philadelphia Housing Auth | Permit type: Administrative permit | Permit status: Completed | Completion date: June 14, 2013 | Permit id: 471838 | |||||
Lot a for the erection of one story structure, Date: November 17, 2011 Client: Philadelphia Housing Auth | Permit type: Zoning/use permit | Permit status: Completed | Completion date: November 17, 2011 | Permit id: 373956 | |||||
SCORE 100 Installation of new hvac system to include ductwork and water cooled heat pump units as per plans. 33 registars diffusers Date: November 23, 2011 Contractor: Accord Mechanical And Mgmt Svs Client: Philadelphia Housing Auth | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 7, 2012 | Permit id: 370369 | |||||
SCORE 100 New 3 amp service for temporary contstruction office trailer and construction site. Services is 120 2 single phase as per 2008 nec (west district) Date: April 8, 2010 Contractor: Anmar Electrical Contractor In Client: Philadelphia Housing Auth | Permit type: Electrical permit | Permit status: Completed | Completion date: July 6, 2010 | Permit id: 271450 | |||||
Construction of a community bldg as part of a new construction project as per plans. Date: July 2, 2010 Client: Philadelphia Housing Auth | Permit type: New construction permit | Permit status: Completed | Completion date: January 24, 2012 | Permit id: 270829 | |||||
(north of prop. Saybrook) relocation of lot lines to create (20) proposed lots from (20) existing lots. For the demo of all existing structures and new constrution of new structures for use as dwellings. (south of prop. Saybrook) relocation of lot lines to create (40) proposed lots from (33) existing lots. For the demo of all existing structures and new construction of new structures for use as dwellings. Date: June 29, 2010 Client: Philadelphia Housing Auth | Permit type: Zoning permit | Permit status: Completed | Completion date: June 29, 2010 | Permit id: 265649 | |||||
SCORE 93 Complete demolition no demolition prior to Date: February 16, 2010 Contractor: Meco Demolition Inc Client: Philadelphia Housing Auth | Permit type: Demolition permit | Permit status: Completed | Completion date: June 3, 2010 | Permit id: 257966 | |||||
SCORE 93 Complete demolition of all structures to create vacant lot. Date: February 16, 2010 Contractor: Meco Demolition Inc Client: Philadelphia Housing Auth | Permit type: Zoning/use permit | Permit status: Completed | Completion date: November 5, 2010 | Permit id: 257964 | |||||
SCORE 100 Sealing of existing laterals and water as follows: 23-6" laterals, 2-10" laterals, 1-18" lateral and 1-6" domestic water line Date: January 19, 2010 Contractor: Meco Constructors Inc Client: Philadelphia Housing Auth | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 23, 2010 | Permit id: 257801 | |||||
Erection of community building with three off street parking spaces. Date: June 29, 2010 Client: Philadelphia Housing Auth | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 29, 2010 | Permit id: 288452 | |||||
SCORE 89 New construction,18 fixtures with piping for pha rental office Date: October 26, 2010 Contractor: Lpi Mechanical Llc Client: Philadelphia Housing Auth | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 7, 2012 | Permit id: 305025 | |||||
SCORE 100 Installation of complete fire sprinkler system for community bldg as per plans and calcs. Date: February 15, 2011 Contractor: Angkor Contracting Services Client: Philadelphia Housing Auth | Permit type: Suppression permit | Permit status: Completed | Completion date: February 7, 2012 | Permit id: 320092 | |||||
For the relocation of lot lines to create two lots from two lots lot a for the erection of one story structure, lot b for erection of two semidetached structures with two off street spaces. Date: July 13, 2011 Client: Philadelphia Housing Auth | Permit type: Zoning permit | Permit status: Completed | Completion date: July 13, 2011 | Permit id: 328490 | |||||
Amending permit # 270829 to reflect reconfigured building as per plans. Date: November 21, 2011 Client: Philadelphia Housing Auth | Permit type: Administrative permit | Permit status: Completed | Completion date: February 7, 2012 | Permit id: 352164 | |||||
SCORE 100 To install new lateral from sewer to curb Date: April 11, 2011 Contractor: Harry Stuhl Iii Client: Philadelphia Housing Auth | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 7, 2011 | Permit id: 334858 | |||||
SCORE 100 Wire entire center bldg, includes fire alarm, tele communication sercurity, lighting and devices as per 2008 nec,nfpa-72 communitie center Date: October 25, 2011 Contractor: Larry C Mccrae Inc Client: Philadelphia Housing Auth | Permit type: Electrical permit | Permit status: Completed | Completion date: February 1, 2012 | Permit id: 364915 | |||||
SCORE 100 Install 2 5. 3kw systems for community bldg. As per 2008 nec (west dist) Date: December 2, 2011 Contractor: Larry C Mccrae Inc Client: Philadelphia Housing Auth | Permit type: Electrical permit | Permit status: Completed | Completion date: February 1, 2012 | Permit id: 368963 | |||||
SCORE 100 To install new lateral 6" from sewer to curb Date: April 11, 2011 Contractor: Harry Stuhl Iii Permit type: Plumbing permit | Permit status: Completed | Completion date: April 20, 2011 | Permit id: 334866 | |||||
SCORE 100 Install all wiring throughout single family dwelling and rear security pole light as per 2008 (west dist) Date: June 10, 2011 Contractor: Larry C Mccrae Inc Permit type: Electrical permit | Permit status: Completed | Completion date: August 10, 2013 | Permit id: 346512 | |||||
Construction of new single family dwelling. See a p 268465 for plans Date: July 1, 2010 Permit type: New construction permit | Permit status: Completed | Completion date: November 2, 2011 | Permit id: 288711 | |||||
SCORE 100 Installation of fire sprinkler system Date: November 2, 2010 Contractor: Angkor Contracting Services Permit type: Suppression permit | Permit status: Completed | Completion date: November 4, 2011 | Permit id: 306226 | |||||
Erection of three story attached structure- one off street parking space Date: June 29, 2010 Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 29, 2010 | Permit id: 288339 | |||||
SCORE 100 Permit to install one 2 ton water cooled heat pump with related ductwork, within single family dwelling. No penetration of any fire rated assemblies allowed under this permit. Date: February 17, 2011 Contractor: Accord Mechanical And Mgmt Svs Permit type: Mechanical permit | Permit status: Completed | Completion date: November 4, 2011 | Permit id: 318374 | |||||
SCORE 89 New construction,14 fixtures with piping for 2 family dwelling Date: October 26, 2010 Contractor: Lpi Mechanical Llc Permit type: Plumbing permit | Permit status: Completed | Completion date: November 4, 2011 | Permit id: 304988 | |||||
SCORE 100 Installation of a 1. 88kw pv system as per 2008 nec (west district) Date: September 15, 2011 Contractor: Larry C Mccrae Inc Client: Phila Housing Authority | Client Company: Michael Johns | Permit type: Electrical permit | Permit status: Completed | Completion date: December 24, 2012 | Permit id: 362461 |