SCORE 93 Remove and replace sidewalk and curbcut. Date: April 21, 2006 Contractor: Jb Construction Inc Client: Benjamin Moss, Moss | Applicant: Jb Construction, Inc. | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Set new 3 4" meter pit Date: March 4, 2005 Contractor: Cap Xcavating Construction Llc Client: Benjamin Moss, Moss | Applicant: Cap Xcavating Construction Llc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 93 Set dumpster on hawthorn avenue. Date: November 17, 2004 Contractor: Jb Construction Inc Client: Benjamin Moss, Moss | Applicant: Jb Construction, Inc. | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 82 Total structure demolition of the existing single-family residence. Date: August 16, 2004 Contractor: Benjamin Moss Client: Benjamin Moss, Moss | Applicant: Benjamin Moss | Permit type: Demolition | Permit status: Cmp | Completion date: March 3, 2008 | Current use: Single family d | |||||
SCORE 95 Construction of a new single-family detached residence with five bedrooms and three bathrooms. New detached garage via separate permit. Client: Benjamin Moss, Moss | Applicant: Moss Builders Inc | Permit type: Building, electrical | Permit status: Cmp | Current use: Single family d | |||||
SCORE 95 Construction of a new detached garage (648 s. F.) in association with a new single-family residence (see pmt2004-03200). Client: Benjamin Moss, Moss | Applicant: Moss Builders Inc | Permit type: Building, electrical | Permit status: N&v | Current use: Single family d | |||||
SCORE 82 Temporary construction power. Date: August 16, 2004 Contractor: Benjamin Moss Client: Benjamin Moss, Moss | Applicant: Benjamin Moss | Permit type: Electrical | Permit status: Cmp | Completion date: September 1, 2004 | Current use: Single family d | |||||
SCORE 56 Basement finish existing roughin bath. 1000sf Client: Andrew Larson,Amy Larson | Applicant: Complete Design & Build, Llc | Permit type: Building, electrical | Permit status: Cmp | Completion date: May 9, 2007 | Current use: Single family d | |||||
SCORE 99 Installation of radiant heat system and heat pump. Date: January 30, 2007 Contractor: Four Seasons Heating Inc Client: Andrew Larson,Amy Larson | Applicant: Four Seasons Heating Inc | Permit type: Electrical, mechanic | Permit status: Cmp | Completion date: April 25, 2007 | Current use: Single family d | |||||
Total structure demolition of the existing single-family residence. Date: August 16, 2004 Client: Benjamin Moss | Permit type: Demolition | Permit status: Cmp | Completion date: March 3, 2008 | Current use: Single family detached dwelling, existin | Permit id: Pmt2004-03218 | |||||
SCORE 100 Temporary construction power. Date: August 16, 2004 Contractor: Lightscape Electric, Llc Client: Benjamin Moss | Permit type: Electrical | Permit status: Cmp | Completion date: September 1, 2004 | Current use: Single family detached dwelling, existin | Permit id: Pmt2004-03219 | |||||
SCORE 93 Set dumpster on hawthorn avenue. Date: November 17, 2004 Contractor: Jb Construction, Inc Client: Benjamin Moss | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2004-04452 | |||||
SCORE 93 Remove and replace sidewalk and curbcut. Date: April 21, 2006 Contractor: Jb Construction, Inc Client: Benjamin Moss | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-01425 | |||||
SCORE 95 Construction of a new single-family detached residence with five bedrooms and three bathrooms. New detached garage via separate permit. Client: Benjamin Moss | Permit type: Building, electrical, mechanical, plumbing, water, wastewater | Permit status: Cmp | Current use: Single family detached dwelling, new | Permit id: Pmt2004-03200 | |||||
SCORE 95 Construction of a new detached garage (648 s. F.) in association with a new single-family residence (see pmt2004-03200). Client: Benjamin Moss | Permit type: Building, electrical | Permit status: N&v | Current use: Single family detached dwelling, existin | Permit id: Pmt2004-03201 | |||||
SCORE 99 Set dumpster on hawthorn avenue. Date: November 17, 2004 Contractor: Jb Construction Client: Benjamin Moss | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2004-04452 | |||||
SCORE 95 Set new 3 4inch meter pit Date: March 4, 2005 Contractor: Cap Excavating, Inc Client: Benjamin Moss | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2005-00770 | |||||
SCORE 99 Remove and replace sidewalk and curbcut. Date: April 21, 2006 Contractor: Jb Construction Client: Benjamin Moss | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-01425 | |||||
SCORE 56 Basement finish existing roughin bath. 1000sf Client: Andrew Larson | Permit type: Building, electrical, mechanical, plumbing, water | Permit status: Cmp | Completion date: May 9, 2007 | Current use: Single family detached dwelling, remodel | Permit id: Pmt2006-05353 | |||||
SCORE 99 Installation of radiant heat system and heat pump. Client: Andrew Larson | Permit type: Electrical, mechanical | Permit status: Cmp | Completion date: April 25, 2007 | Current use: Single family detached dwelling, existin | Permit id: Pmt2007-00298 |