Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 82 Hvaccommercial installation of cooling system Date: October 14, 2013 Contractor: E. Escher Inc Permit type: Hvac | Permit status: Issued | Permit id: Bm-201302973 | |||||
SCORE 58 Add and relocate sprinkler heads to local and state code. Date: October 11, 2013 Contractor: Nix Permit type: Fire sprinkler | Permit status: Issued | Permit id: Bp-201303501 | |||||
SCORE 96 Medical research lab- bldg f- basement interior alteration to create a new 1 sq ft equipment lab room within an existing basement level of research building. New partition walls, door, ceiling, hvac and electrical. Date: September 17, 2013 Contractor: Dpr Construction A General Partnership Permit type: Alteration | Permit status: Issued | Permit id: Bb-201305234 | |||||
SCORE 84 Server rm 342 clean agent system - new Date: July 26, 2013 Contractor: Century Fire Protection Inc Permit type: Low voltage | Permit status: Issued | Permit id: Be-201305955 | |||||
SCORE 86 Event date: 5 17 13-yancey power providing stage power (1) 60kw, (2) 100kw generators (generators will be grounded) Date: May 17, 2013 Contractor: Harris Diversified Llc Permit type: Electrical | Permit status: Issued | Permit id: Be-201303874 | |||||
SCORE 73 Electrical proteomics labs 2nd floor Date: February 20, 2013 Contractor: Georgia Specialty Constructors Inc Permit type: Electrical | Permit status: Issued | Permit id: Be-201301390 | |||||
SCORE 86 Electrical Date: February 20, 2013 Contractor: Onepath Systems Llc Permit type: Low voltage | Permit status: Issued | Permit id: Be-201301383 | |||||
SCORE 82 Revision of existing area- tl melton revision to permit bb-201204197 space Date: January 28, 2013 Contractor: E. Escher Inc Permit type: Plumbing | Permit status: Issued | Permit id: Bp-201300312 | |||||
SCORE 68 Gas line reair at the central plant aka 2 lee street Date: December 24, 2012 Contractor: Capital City Mechanical Services Permit type: Hvac | Permit status: Issued | Permit id: Bm-201203563 | |||||
SCORE 82 New sprinkler system to lower existing building-library Date: December 5, 2012 Contractor: Vsc Fire And Security Inc. Norcross Permit type: Fire sprinkler | Permit status: Issued | Permit id: Bp-201204068 | |||||
SCORE 82 Plumbing first floor renovation Date: November 9, 2012 Contractor: E. Escher Inc Permit type: Plumbing | Permit status: Issued | Permit id: Bp-201203786 | |||||
SCORE 62 Electrical work-low voltage heating ventilation air conditioning low voltage controls wiring Date: November 7, 2012 Contractor: Tls Eletrical Inc Permit type: Low voltage | Permit status: Issued | Permit id: Be-201208986 | |||||
SCORE 73 7 westview dr sw--morehouse meb library 1st floor--renovating existing space Date: October 8, 2012 Contractor: Georgia Specialty Constructors Inc Permit type: Electrical | Permit status: Issued | Permit id: Be-201208129 | |||||
SCORE 100 Install new sprinkler system in second floor of existing building Date: September 13, 2012 Contractor: Vsc Fire And Security Inc Permit type: Fire sprinkler | Permit status: Issued | Permit id: Bp-201203151 | |||||
SCORE 82 7 westview dr morehouse school of medicine - 2nd floor gas line addition for emergency generator Date: August 29, 2012 Contractor: E. Escher Inc Permit type: Hvac | Permit status: Issued | Permit id: Bm-201202426 | |||||
SCORE 95 Renovate existing library Date: August 23, 2012 Contractor: Turner Construction Company Permit type: Alteration | Permit status: No co required | Permit id: Bb-201204197 | |||||
Remove 1 tree Date: August 2, 2012 Permit type: Landscape | Permit status: Revisions required | Permit id: Ba-201203771 | |||||
SCORE 95 Replace and install back-up power generator seperate permit required for installation of fuel storage tanks... Issued by fire prevention division. Date: July 16, 2012 Contractor: Turner Construction Company Permit type: Alteration | Permit status: Issued | Permit id: Bb-201203441 | |||||
SCORE 95 Install screened rooftop mechanical units. Date: May 25, 2012 Contractor: Turner Construction Company Permit type: Alteration | Permit status: Issued | Permit id: Bb-201202577 | |||||
Low voltage, fire alarm Date: May 24, 2012 Permit type: Low voltage | Permit status: Issued | Permit id: Be-201204224 | |||||
SCORE 82 Hvac work-2nd floor hvac renovation. Equipment will be installed in mechanical room on the roof. Date: May 21, 2012 Contractor: E. Escher Inc Permit type: Hvac | Permit status: Issued | Permit id: Bm-201201400 | |||||
SCORE 82 2nd floor plumbing renovation Date: May 9, 2012 Contractor: E. Escher Inc Permit type: Plumbing | Permit status: Issued | Permit id: Bp-201201659 | |||||
SCORE 95 Renovate 2nd floor of existing medical education bldg with finishes Date: April 13, 2012 Contractor: Turner Construction Company Permit type: Alteration | Permit status: No co required | Permit id: Bb-201201789 | |||||
Dead dying hazardous Date: April 12, 2012 Permit status: Issued | Permit id: Ba-201201715 | |||||
SCORE 86 Modify sprints existing wireless installation as follows: install (9) new antennas to existing tower mounts, install (2) new equipment cabinets on existing conc. Slab, install 3 hybrid cables to tower, install related euipment to tower and slab. Remove old equipment after 6 months testing of new equipment Date: December 15, 2011 Contractor: Neocom Permit type: Miscellaneous | Permit status: Issued | Permit id: Bb-201105805 |