Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Fire alarm modifications Date: November 7, 2011 Contractor: Hunt Electric Permit type: Low voltage | Permit status: Pass | Completion date: March 5, 2012 | Current use: Commercial | Permit id: Bld2011-07171 | |||||
SCORE 61 New commercial building Date: March 27, 2015 Contractor: National Filter Media Bldg #3michael Mchugh Permit status: Closed | Current use: Commercial | Permit id: Bld2014-07413 | |||||
Power to panel Date: February 11, 2015 Permit type: Electrical | Permit status: Pass | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2015-00960 | |||||
Rough/finish Date: November 24, 2014 Permit type: Electrical | Permit status: Pass | Completion date: March 27, 2015 | Current use: Commercial | Permit id: Bld2014-08650 | |||||
SCORE 77 1 2ton ac and furnace 1 100cfm ef 3 evap coolers 8 radiant heaters Date: January 30, 2015 Contractor: Total Air Handling Incnational Filter Media Permit type: Mechanical | Permit status: Closed | Completion date: March 19, 2015 | Current use: Commercial | Permit id: Bld2015-00647 | |||||
Please pay balance due plumbing in new building. Add gas line Date: November 17, 2014 Permit type: Plumbing | Permit status: Pass | Completion date: March 10, 2015 | Current use: Commercial | Permit id: Bld2014-08467 | |||||
SCORE 79 Fire alarm modifications Date: November 7, 2011 Contractor: Hunt Electricnational Filter Media Permit type: Low voltage | Permit status: In for review | Completion date: March 5, 2012 | Current use: Commercial | Permit id: Bld2011-07171 | |||||
SCORE 79 Power to panel permit pending agreement. Date: November 4, 2011 Contractor: Hunt Electricnational Filter Media Permit type: Electrical | Permit status: No certificate req | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07233 | |||||
Plumbing Date: November 3, 2011 Permit type: Plumbing | Permit status: No certificate req | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07192 | |||||
SCORE 79 Elec wiring to new building please note: temp power, power to panel (if needed), and fire alarm are authorized by seperate permits. Date: November 3, 2011 Contractor: Hunt Electricnational Filter Media Permit type: Electrical | Permit status: No certificate req | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07172 | |||||
SCORE 64 1 underground fire line d. W. Date: October 26, 2011 Contractor: A R M Construction Llcnational Filter Media Permit type: Fire | Permit status: No certificate req | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-06949 | |||||
New office/manufacturing/warehouse bldg. M-1 zone, new building for peritted uses. Parking and other site improvements per plans / zoning reivew and approval by ah. Date: September 20, 2011 Permit type: Permit | Permit status: Completed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-06009 | |||||
SCORE 61 New commercial building expedited review Date: March 27, 2015 Contractor: National Filter Media Bldg #3michael Mchugh Permit status: Closed | Current use: Commercial | Permit id: Bld2014-07413 | |||||
SCORE 60 New office/manufacturing/warehouse bldg. M-1 zone, new building for peritted uses. Parking and other site improvements per plans / zoning reivew and approval by ah. Date: September 20, 2011 Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-06009 | |||||
Plumbing Date: November 3, 2011 Permit type: Plumbing | Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07192 | |||||
SCORE 77 Fire sprinkler system 1st floor Date: December 2, 2011 Permit type: Fire | Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07926 | |||||
SCORE 56 New commercial building expedited review Date: October 10, 2014 Permit status: Closed | Completion date: March 27, 2015 | Current use: Commercial | Permit id: Bld2014-07413 | |||||
SCORE 61 Underground Date: November 6, 2014 Permit type: Fire | Permit status: Closed | Completion date: March 26, 2015 | Current use: Commercial | Permit id: Bld2014-08187 | |||||
Please pay balance due plumbing in new building. Add gas line Date: November 17, 2014 Permit type: Plumbing | Permit status: Closed | Completion date: March 10, 2015 | Current use: Commercial | Permit id: Bld2014-08467 | |||||
Rough/finish Date: November 24, 2014 Permit type: Electrical | Permit status: Closed | Completion date: March 27, 2015 | Current use: Commercial | Permit id: Bld2014-08650 | |||||
Power to panel Date: February 11, 2015 Permit type: Electrical | Permit status: Closed | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2015-00960 | |||||
SCORE 64 Fire sprinkler Date: December 22, 2014 Contractor: Fire Engineering Company Incnational Filter Permit type: Fire | Permit status: Closed | Completion date: March 12, 2015 | Current use: Commercial | Permit id: Bld2014-09329 | |||||
SCORE 59 Underground Date: November 6, 2014 Permit type: Fire | Permit status: Pass | Completion date: March 26, 2015 | Current use: Commercial | Permit id: Bld2014-08187 | |||||
New commercial building expedited review Date: October 10, 2014 Permit type: Permit | Permit status: Pass | Completion date: March 27, 2015 | Current use: Commercial | Permit id: Bld2014-07413 | |||||
SCORE 77 Fire sprinkler system 1st floor Date: December 2, 2011 Permit type: Fire | Permit status: Completed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07926 | |||||
SCORE 65 New office manufacturing warehouse bldg. M-1 zone, new building for peritted uses. Parking and other site improvements per plans zoning reivew and approval by ah. Date: September 20, 2011 Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-06009 | |||||
SCORE 64 1 underground fire line d. W. Date: October 26, 2011 Contractor: A R M Construction Llcnational Filter Media Permit type: Fire | Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-06949 | |||||
SCORE 79 Fire alarm modifications Date: November 7, 2011 Contractor: Hunt Electricnational Filter Media Permit type: Low voltage | Permit status: In for review | Completion date: March 5, 2012 | Current use: Commercial | Permit id: Bld2011-07171 | |||||
SCORE 79 Elec wiring to new building please note: temp power, power to panel (if needed), and fire alarm are authorized by seperate permits. Date: November 3, 2011 Contractor: Hunt Electricnational Filter Media Permit type: Electrical | Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07172 | |||||
SCORE 59 Plumbing Date: November 3, 2011 Contractor: Atom Plumbing, Inc.National Filter Media Permit type: Plumbing | Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07192 | |||||
SCORE 79 Power to panel permit pending agreement. Date: November 4, 2011 Contractor: Hunt Electricnational Filter Media Permit type: Electrical | Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07233 | |||||
SCORE 77 Fire sprinkler system 1st floor Date: December 2, 2011 Permit type: Fire | Permit status: Closed | Completion date: February 29, 2012 | Current use: Commercial | Permit id: Bld2011-07926 | |||||
SCORE 59 New commercial building expedited review Date: October 10, 2014 Permit status: Closed | Completion date: March 27, 2015 | Current use: Commercial | Permit id: Bld2014-07413 | |||||
SCORE 61 Underground Date: November 6, 2014 Permit type: Fire | Permit status: Closed | Completion date: March 26, 2015 | Current use: Commercial | Permit id: Bld2014-08187 | |||||
SCORE 59 Please pay balance due plumbing in new building. Add gas line Date: November 17, 2014 Contractor: Atom Plumbing Incnational Filter Media Bldg 2 Permit type: Plumbing | Permit status: Closed | Completion date: March 10, 2015 | Current use: Commercial | Permit id: Bld2014-08467 | |||||
SCORE 67 Rough finish Date: November 24, 2014 Contractor: Id Electric Companynational Filter Media Permit type: Electrical | Permit status: Closed | Completion date: March 27, 2015 | Current use: Commercial | Permit id: Bld2014-08650 | |||||
SCORE 77 1 2ton ac and furnace 1 100cfm ef 3 evap coolers 8 radiant heaters Date: January 30, 2015 Contractor: Total Air Handling Incnational Filter Media Permit type: Mechanical | Permit status: Closed | Completion date: March 19, 2015 | Current use: Commercial | Permit id: Bld2015-00647 | |||||
SCORE 67 Power to panel Date: February 11, 2015 Contractor: Id Electric Companynational Filter Media Permit type: Electrical | Permit status: Closed | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2015-00960 | |||||
SCORE 64 Fire sprinkler Date: December 22, 2014 Contractor: Fire Engineering Company Incnational Filter Permit type: Fire | Permit status: Closed | Completion date: March 12, 2015 | Current use: Commercial | Permit id: Bld2014-09329 |