Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 74 Wall-mounted antennas. T. B. Zone: rmf-45 zone, paint to match. Approved per all conditions of 21a. 40. 090. A. H. Date: November 16, 2010 Permit status: Pass | Completion date: October 19, 2012 | Current use: Residential | Permit id: Bld2010-07935 | |||||
SCORE 64 Energy upgrade. Replace single boiler with two new, replace light fixtures, recoat deck surfaces and repaint guard railings. Electrical & mechanical permits reqd g. S. Zone: a. M. Date: March 16, 2010 Contractor: Kier Construction Corporationromney Plaza Permit status: Pass | Completion date: September 29, 2010 | Current use: Residential | Permit id: Bld2010-01439 | |||||
SCORE 74 Install 2 boilers, 1 unit heater, & gas lines. Work may not commence on this project until plan review for permit bld2010-01439 has been approved & building permit issued. Date: April 28, 2010 Contractor: Carson Plumbing And Mechanical Incromney Plaza Permit type: Mechanical | Permit status: Pass | Completion date: September 29, 2010 | Current use: Residential | Permit id: Bld2010-02725 | |||||
SCORE 61 Rooftop boiler room expansion requires (2) additional heads to be added to provide proper coverage for the expanded area. Date: June 22, 2010 Contractor: Interwest Fire Protectionromney Plaza Permit type: Fire | Permit status: Pass | Completion date: September 24, 2010 | Current use: Residential | Permit id: Bld2010-04187 | |||||
SCORE 59 Replace generator Date: January 28, 2010 Permit type: Electrical | Permit status: Pass | Completion date: April 21, 2011 | Current use: Residential | Permit id: Bld2010-00439 | |||||
SCORE 64 Run power to 2 new ton a c units Date: October 10, 2012 Contractor: Elkridgenew A C Permit type: Electrical | Permit status: Pass | Completion date: October 16, 2012 | Current use: Commercial | Permit id: Bld2012-07527 | |||||
SCORE 59 Change existing antennas with new antennas Date: July 18, 2012 Contractor: Tmobiletmobile Sl01571 Permit status: Pass | Completion date: February 7, 2013 | Current use: Commercial | Permit id: Bld2012-05234 | |||||
SCORE 74 Elec work for new boiler room on roof top Date: March 29, 2010 Permit type: Electrical | Permit status: Pass | Completion date: September 29, 2010 | Current use: Commercial | Permit id: Bld2010-01729 | |||||
SCORE 74 Wall-mounted antennas. Date: November 16, 2010 Permit type: Electrical | Permit status: Pass | Completion date: March 22, 2012 | Current use: Residential | Permit id: Bld2010-07936 | |||||
SCORE 100 Replace 14 fan coil units Date: October 25, 2011 Contractor: Ralph Tye And Sons Inc Permit type: Mechanical | Permit status: Pass | Completion date: May 30, 2012 | Current use: Residential | Permit id: Bld2011-06913 | |||||
SCORE 74 Install 4 drains. Work may not commence on this project until plan review for permit bld2010-01439 has been approved & building permit issued. Date: April 28, 2010 Contractor: Carson Plumbing And Mechanical Incromney Plaza Permit type: Plumbing | Permit status: Pass | Completion date: September 15, 2010 | Current use: Residential | Permit id: Bld2010-02727 | |||||
SCORE 59 Remodel kitchen & update bathrooms Date: August 24, 2016 Contractor: Romney Plaza Permit status: Inspections | Completion date: November 8, 2016 | Current use: Commercial | Permit id: Bld2016-07983 | |||||
SCORE 56 Rooftop: remove six (6) rrus, remove three (3) panel antennas, add three (3) new rrus, add three (3) new panel antennas. Ground: remove two (2) spd units and install one (1) new 3206 cabinet within existing lease area. Date: September 20, 2016 Contractor: Cortelsl01571a Tmobile Lte Permit status: Closed | Completion date: November 18, 2016 | Current use: Commercial | Permit id: Bld2016-08804 | |||||
SCORE 56 Replace the first floor break room sink and replace 2 lavs in the first floor public bathrooms. Date: December 14, 2016 Contractor: Mark Mc Bride Plumbing, Inc.Romney Remodel Permit type: Plumbing | Permit status: Inspections | Completion date: December 14, 2016 | Current use: Commercial | Permit id: Bld2016-11387 | |||||
SCORE 59 Elect permit. Date: December 20, 2016 Contractor: Romney Plaza Permit type: Electrical | Permit status: Inspections | Completion date: December 20, 2016 | Current use: Commercial | Permit id: Bld2016-11549 | |||||
SCORE 64 Building items associated with the replacement of (2) roof top cooling units. Zone- not historic. Date: August 30, 2012 Permit status: Pass | Completion date: October 19, 2012 | Current use: Commercial | Permit id: Bld2012-06452 | |||||
SCORE 64 2 - chillers 9 - hp or tons Date: August 30, 2012 Permit type: Mechanical | Permit status: Accepted | Completion date: August 30, 2012 | Current use: Commercial | Permit id: Bld2012-06453 |