Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: November 12, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 505550 | |||||
Plumbing permit Date: October 11, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 500127 | |||||
Zoning permit Date: March 20, 2012 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 393228 | |||||
Demolition permit Date: June 9, 2014 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 504177 | |||||
Plumbing permit Date: October 11, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 500127 | |||||
Demolition permit Date: June 9, 2014 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 504177 | |||||
Zoning permit Date: March 20, 2012 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 393228 | |||||
Electrical permit Date: November 12, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 505550 | |||||
For the complete demolition of all structures and for the relocation of lot lines to create seven (7) lots from one (1) lot. Size and location as shown in the application. Date: March 20, 2012 Client: Maple Hill Group Llc | Permit type: Zoning permit | Permit status: Completed | Completion date: August 26, 2013 | Permit id: 393228 | |||||
SCORE 100 New construction of a single-family dwelling (plumbing construction) - (11)fixtures total - note: separate fire suppression permit required for 1" 13d fire suppression water service Date: October 11, 2013 Contractor: Tommys Plumbing Client: Maple Hill Group Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 25, 2015 | Permit id: 500127 | |||||
SCORE 96 The complete demolition of an existing building on site (one (1)- two (2) story detached building) as shown per approved plans and submitted documentation. Work must comply with code bulletin b-1032. If field conditions vary, contact structural engineer prior to the start of any work. Safety plan must be on site at all times. Date: June 9, 2014 Contractor: James Dibartolo Client: Maple Hill Group Llc | Permit type: Demolition permit | Permit status: Completed | Completion date: October 31, 2014 | Permit id: 504177 | |||||
SCORE 96 Install 200amp service, 63 outlets, 45 lights in fixutres, 23 switches, electric range, hot water heater, dryer, s moke& carbon dectectors, heating and ac unit as per 2008 nec (north district) Date: November 12, 2013 Contractor: Sfb Wiring Systems Llc Client: Maple Hill Group Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: December 2, 2014 | Permit id: 505550 |