Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: August 14, 2007 Client: Archdiocese Of Phila | Permit status: Completed | Permit id: 91998 | |||||
Alteration permit Date: July 29, 2016 Client: Archdiocese Of Phila | Permit status: Active | Permit id: 711092 | |||||
Electrical permit Date: July 27, 2016 Client: Archdiocese Of Phila | Permit status: Active | Permit id: 710494 | |||||
Alteration permit Date: November 8, 2016 Client: First Church Of Our Lord Jesus Christ Inc | Permit status: Active | Permit id: 735233 | |||||
Electrical permit Date: July 27, 2016 Client: First Church Of Our Lord Jesus Christ Inc | Permit status: Abandoned | Permit id: 710494 | |||||
Mechanical permit Date: August 14, 2007 Client: First Church Of Our Lord Jesus Christ Inc | Permit status: Completed | Permit id: 91998 | |||||
SCORE 99 Ez permit stadard alterations- for alterations as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans Date: November 8, 2016 Contractor: Azure Builders And Designers Cor Client: First Church Of Our Lord | Permit type: Alteration permit | Permit status: Active | Completion date: October 26, 2017 | Permit id: 735233 | |||||
SCORE 100 Install hood suppression system as per form. Date: August 14, 2007 Contractor: Keystone Fire Protection Client: First Church Of Our Lord | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 24, 2007 | Permit id: 91998 | |||||
SCORE 100 2-200amp panels, recessed lights, lights, recepts, swicthes, gfci recepts, hvac hook ups, change out breakers not wiring upper sanctuary and non-plenum rated cat5e network lines with a longest run of about 80ft as per 2008 nec (east district) Date: March 3, 2017 Contractor: Christopher Adair Client: First Church Of Our Lord | Permit type: Electrical permit | Permit status: Expired | Completion date: March 3, 2017 | Permit id: 755169 | |||||
SCORE 100 Amend ap# 710268 alteration to womens restroom for new baptism area. Date: September 8, 2017 Contractor: Ingrams Drain And Sewer Cleaning Client: First Church Of Our Lord | Permit type: Plumbing permit | Permit status: Active | Completion date: September 8, 2017 | Permit id: 806660 | |||||
SCORE 100 Roof replacement - install a shingle and modified bitumen roof systems (commercial) Date: July 29, 2016 Contractor: Joseph Fisher And Sons Roofing Client: First Church Of Our Lord | Permit type: Alteration permit | Permit status: Completed | Completion date: December 28, 2016 | Permit id: 711092 | |||||
SCORE 100 Alteration: interior plumbing;commercial, church (ez bp); separate permit by pwd required for backflow protection - the installation will comply with the philadephia plubming code 2004 Date: February 10, 2017 Contractor: Ingrams Drain And Sewer Cleaning Client: First Church Of Our Lord | Permit type: Plumbing permit | Permit status: Active | Completion date: August 25, 2017 | Permit id: 710268 | |||||
SCORE 100 Recessed lights,lights,rec,switches,gfci rec,hvac hook ups,network lines,chnage out breakers per 2008 nec (house of worship)east district Date: July 27, 2016 Contractor: Christopher Adair Client: First Church Of Our Lord | Permit type: Electrical permit | Permit status: Abandoned | Completion date: November 15, 2016 | Permit id: 710494 | |||||
SCORE 100 1 fire panel, 1 radio, smokes, heats, pull stations, strobes, horn strobes, annihilator ,smoke beams per nfpa 72 (house of worship)east district Date: September 5, 2017 Contractor: Christopher Adair Client: First Church Of Our Lord | Permit type: Electrical permit | Permit status: Active | Completion date: September 5, 2017 | Permit id: 742060 |