Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: August 21, 2013 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 490514 | |||||
Addition permit Date: January 4, 2016 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 652049 | |||||
Plumbing permit Date: May 14, 2012 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 404945 | |||||
Mechanical permit Date: March 20, 2013 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 460037 | |||||
Zoning permit Date: November 20, 2015 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 523349 | |||||
Addition permit Date: January 4, 2016 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 652049 | |||||
Mechanical permit Date: March 20, 2013 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 460037 | |||||
Plumbing permit Date: May 14, 2012 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 404945 | |||||
Electrical permit Date: August 21, 2013 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 490514 | |||||
Zoning permit Date: November 20, 2015 Client: Frask Jeffrey J | Permit status: Completed | Permit id: 523349 | |||||
SCORE 99 Installation of (1) payne hvac unit including ductwork (sfd) Date: March 20, 2013 Contractor: David Mercado Client: Frask Jeffrey J | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 9, 2014 | Permit id: 460037 | |||||
For a bathroom addition in rear & a new porch roof over existing porch floor. For interior alteration as shown on the approved plans. This work activity has beeen performed by the home owner. The home owner has the reposnsibility of code compliance. Post this permit post the project information sign Date: January 4, 2016 Client: Frask Jeffrey J | Permit type: Addition permit | Permit status: Completed | Completion date: October 24, 2016 | Permit id: 652049 | |||||
To legalize the erection of a 8x 13 flat roof over existing concrete patio and the erection of an addiiton size and location as shown on submitted plan. Date: November 20, 2015 Client: Frask Jeffrey J | Permit type: Zoning permit | Permit status: Completed | Completion date: November 20, 2015 | Permit id: 523349 | |||||
SCORE 86 Complete rewire, 35-sw, 30-outlets, smoke detectors & carbon monoxide det, gfci recpts, 20-recessed lights & 15-fixtures as per nec 2008 (sfd) Date: August 21, 2013 Contractor: Charlie Dunlop Elec Contractor Client: Frask Jeffrey J | Permit type: Electrical permit | Permit status: Completed | Completion date: November 10, 2015 | Permit id: 490514 | |||||
SCORE 100 Roughin new 3 piece bath,new laundry,new kitchen,new main drain,new toilet,vanity ,tub,new water heater Date: May 14, 2012 Contractor: Lawrence Caro Client: Frask Jeffrey J | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 404945 |