Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 92 Temporary power pole Date: February 8, 2002 Contractor: S R Bray Power Plus Applicant: S R Bray Corp | Permit status: Finaled | Completion date: October 4, 2002 | Expiration date: August 7, 2002 | Permit id: 202080012 | |||||
SCORE 97 Mechanical for new sfr. Date: March 4, 2002 Contractor: Miu Construction Inc Engineer: Paul Houng | Applicant: Miu Hong A | Permit status: Finaled | Completion date: October 3, 2002 | Expiration date: August 31, 2002 | Permit id: 203010007 | |||||
SCORE 90 Connect new residence to public sewer Date: December 3, 2002 Contractor: Beecher Construction Applicant: Beecher Construction | Permit status: Finaled | Completion date: December 10, 2003 | Expiration date: June 1, 2003 | Permit id: 212030001 | |||||
SCORE 97 New 2story s. F. R.-3478 s. F.&new 1 car gar.-264 s. F.(att. To orig. 2 car gar.) Engineer: Paul Houng | Applicant: Miu Hong A | Permit status: Finaled | Completion date: October 3, 2002 | Expiration date: August 31, 2002 | Permit id: 9280057 | |||||
Demo existing 10 sq ft sfr. Date: March 26, 2001 Value: $1,500 Applicant: Same As Owner | Permit status: Finaled | Completion date: March 13, 2002 | Expiration date: September 22, 2001 | Permit id: 103260057 | |||||
SCORE 97 Electrial for new sfr. Date: March 4, 2002 Contractor: Miu Construction Inc Engineer: Paul Houng | Applicant: Miu Hong A | Permit status: Finaled | Completion date: October 3, 2002 | Expiration date: August 31, 2002 | Permit id: 203010015 |