Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Construction of a 18-unit mixed-use structure containing 17 residential units and 1 live work unit on an existing surface parking lot. ![]() ![]() Applicant: Oppenheimer, Gary | Permit type: Construction | Permit status: Permit issued | Current use: Multifamily | Permit id: 6354431 | |||||
Construction of a 18-unit mixed-use structure containing 17 residential units and 1 live/work unit on an existing surface parking lot. ![]() ![]() Applicant: Oppenheimer, Gary | Permit type: Construction | Permit status: Permit closed | Current use: Multifamily | Permit id: 6354431 | |||||
SCORE 95 Install (1) 20a 120v dedicated circuit for heat trace install ![]() ![]() Permit type: Electrical | Permit status: Permit closed | Completion date: July 22, 2015 | Expiration date: July 14, 2016 | Current use: Commercial | Permit id: 6484450 | |||||
SCORE 99 Closed - parent permit issued30-day get started permit for branch circuits only. Plan review under permit #6449873 ![]() ![]() Permit type: Electrical | Permit status: Permit closed | Expiration date: January 9, 2015 | Current use: Multifamily | Permit id: 6449875 | |||||
SCORE 99 Complete wiring of new 18 unit apartment building Permit type: Electrical | Permit status: Permit closed | Completion date: July 28, 2015 | Expiration date: January 5, 2016 | Current use: Multifamily | Permit id: 6449873 | |||||
SCORE 100 Install new fire alarm system. ![]() ![]() Permit type: Electrical | Permit status: Permit closed | Completion date: July 28, 2015 | Expiration date: December 30, 2015 | Current use: Commercial | Permit id: 6441484 | |||||
SCORE 99 [temporary power. Ufer ground. ] ![]() ![]() Permit type: Electrical | Permit status: Permit closed | Completion date: December 5, 2014 | Expiration date: October 10, 2015 | Current use: Commercial | Permit id: 6440754 | |||||
Land use application to allow a four story, 17 unit residential building with one live-work unit located at street level. ![]() ![]() Applicant: Oppenheimer, Gary | Permit type: Design review with edg, sepa threshold determination | Permit status: Permit issued | Current use: Multifamily | Permit id: 3014898 | |||||
SCORE 98 Supply and install exhaust ventilation for 18 residential units and fans. Applicant: House, April | Permit type: Mechanical | Permit status: Permit closed | Completion date: July 28, 2015 | Expiration date: September 2, 2016 | Current use: Multifamily | Permit id: 6461858 | |||||
SCORE 95 Trash exhaust and corridor make up air. Applicant: Moore, Amanda | Permit type: Mechanical | Permit status: Permit closed | Completion date: July 28, 2015 | Expiration date: September 30, 2016 | Current use: Commercial | Permit id: 6447390 | |||||
SCORE 96 New sewer/storm connections for new building ![]() ![]() Applicant: True Contracting, Llc | Permit type: Side sewer | Permit status: Permit closed | Completion date: September 11, 2015 | Expiration date: April 27, 2016 | Current use: Commercial | Permit id: 6443261 | |||||
Construction of a 18-unit mixed-use structure containing 17 residential units and 1 live work unit on an existing surface parking lot. ![]() ![]() Applicant: Oppenheimer, Gary | Permit type: Construction | Permit status: Permit closed | Completion date: August 14, 2015 | Expiration date: April 13, 2016 | Current use: Multifamily | Permit id: 6354431 | |||||
SCORE 100 New sewer storm connections for new building ![]() ![]() Applicant: True Contracting, Llc | Permit type: Side sewer | Permit status: Permit closed | Completion date: September 11, 2015 | Expiration date: April 27, 2016 | Current use: Commercial | Permit id: 6443261 |