SCORE 95 Demo exsiting single family residence subject to field inspection (stfi) Date: May 17, 2016 Contractor: Build Urban Llc Applicant: Voigt, Jake | Permit type: Demolition | Permit status: Permit closed | Completion date: June 17, 2016 | Expiration date: November 17, 2017 | Current use: Multifamily | Permit id: 6535415 | |||||
SCORE 100 [ufer ground. ] Date: July 13, 2016 Contractor: Active Engineering Permit type: Electrical | Permit status: Permit closed | Completion date: July 14, 2016 | Expiration date: July 13, 2017 | Current use: Multifamily | Permit id: 6545664 | |||||
SCORE 100 [temporary power. ] Date: June 23, 2016 Contractor: Active Engineering Permit type: Electrical | Permit status: Permit closed | Completion date: June 27, 2016 | Expiration date: June 23, 2017 | Current use: Multifamily | Permit id: 6542272 | |||||
[temporary power. ] Date: September 16, 2015 Permit type: Electrical | Permit status: Permit closed | Completion date: September 16, 2016 | Expiration date: September 15, 2016 | Current use: Multifamily | Permit id: 6495092 | |||||
Land use application to allow a 3-story structure containing 27 apartment units. Existing structures to be demolished. No vehicle parking proposed. Twenty-two bike spaces provided. Date: August 19, 2015 Value: $1,100,000 Applicant: Wegener, Jeff | Permit type: Sepa threshold determination | Permit status: Permit issued | Current use: Multifamily | Permit id: 3017589 | |||||
SCORE 100 On site utilities. New storm to curb discharge, new sanitary to new connection to main. Add 1 pump. Assoc bldg permit 6415493. Date: June 24, 2016 Contractor: Hobart Excavation Service Inc Applicant: Hobart Excavation Service Inc | Permit type: Side sewer | Permit status: Permit issued | Expiration date: December 24, 2017 | Current use: Single family / duplex | Permit id: 6542659 | |||||
SCORE 100 [a one-line diagram will be required on site at the time of inspection of any renewable energy system. A cover inspection is required before installation begins, but after the equipment is on-site. ] installation of a 24. 96(kw) solar photovoltaic system will be installed on roof of property. 6/28/16 jk approved plans. Date: June 16, 2016 Contractor: Puget Sound Solar Llc Permit type: Electrical | Permit status: Permit issued | Expiration date: June 16, 2017 | Current use: Commercial | Permit id: 6541123 | |||||
SCORE 100 Installation of fire alarm system Date: November 21, 2016 Contractor: Alarmtech Inc Permit type: Electrical | Permit status: Permit issued | Expiration date: November 21, 2017 | Current use: Multifamily | Permit id: 6560976 | |||||
SCORE 100 New 27 unit multi-family amp over head service Permit type: Electrical | Permit status: Permit issued | Expiration date: December 7, 2017 | Current use: Multifamily | Permit id: 6566561 | |||||
SCORE 100 Day get started, for branch circuits only. Assoc. Permit 6566561 Date: November 10, 2016 Contractor: Active Engineering Permit type: Electrical | Permit status: Permit closed | Completion date: December 7, 2016 | Expiration date: December 10, 2016 | Current use: Multifamily | Permit id: 6566562 | |||||
SCORE 100 Stand alone sprinkler new system phinney apartments Date: January 6, 2017 Contractor: Fire Sprinklers Inc Applicant: Sergeev, Oleg | Permit type: Mechanical | Permit status: Permit issued | Expiration date: July 6, 2018 | Current use: Multifamily | Permit id: 6562885 | |||||
SCORE 99 Closed as incomplete[a one-line diagram will be required on site at the time of inspection of any renewable energy system. A cover inspection is required before installation begins, but after the equipment is on-site. ] installation of a 24. 96(kw) solar photovoltaic system will be installed on roof of property. 6 28 16 jk approved plans. 3 2 17 cpg installation of 24. 96(kw) solar photovoltaic system will be installed on roof of residence. (t. Rasmussen poc assoc. Field elec. #6541123) 03 02 17 change from 24. 96 kw system to 25. 92 kw system. 03 10 17 jk approved revised plans. Permit type: Electrical | Permit status: Permit closed | Completion date: June 7, 2017 | Expiration date: June 16, 2017 | Current use: Commercial | Permit id: 6541123 | |||||
SCORE 95 Establish use as multifamily apartments, construct apartment building and occupy as a boarding house, per plan. Applicant: Holloway, Leon | Permit type: Construction | Permit status: Application accepted | Current use: Multifamily | Permit id: 6415493 |