SCORE 100 New (2) story s f r 4023 sf w attd (3) car garage 825 sf & 3 decks (one w/exterior stairway) 108 sf Applicant: Gonzales Emma | Permit status: Finaled | Completion date: January 17, 2007 | Permit id: 0204120010 | |||||
SCORE 95 Roof mounted solar photovoltaic (28) panels 7. 14kw system Applicant: Ricardo Gonzalez | Permit status: Finaled | Completion date: June 14, 2012 | Permit id: 1204170034 | |||||
SCORE 82 Drywall patching as needed Applicant: Larry M. Sofer | Permit status: Finaled | Completion date: June 14, 2012 | Permit id: 1205230025 | |||||
Electrical for new sfr Date: April 16, 2003 Applicant: Same As Owner | Permit status: Finaled | Completion date: January 17, 2007 | Permit id: 0304160010 | |||||
SCORE 95 Roof mounted solar photovoltaic (28) panels 7. 14kw system (2) inverters Date: April 17, 2012 Contractor: Verengo Inc Applicant: Ricardo Gonzalez | Permit status: Finaled | Completion date: June 14, 2012 | Permit id: 1204170014 | |||||
SCORE 95 Upgrade service panel 225 Date: April 17, 2012 Contractor: Verengo Inc Applicant: Ricardo Gonzalez | Permit status: Finaled | Completion date: June 14, 2012 | Permit id: 1204170015 | |||||
Mechanical for new sfr Date: April 16, 2003 Applicant: Same As Owner | Permit status: Finaled | Completion date: January 17, 2007 | Permit id: 0304160003 | |||||
Plumbing for new sfr Date: April 16, 2003 Applicant: Same As Owner | Permit status: Finaled | Completion date: January 17, 2007 | Permit id: 0304160004 | |||||
SCORE 82 Relocate gas line Date: May 23, 2012 Contractor: Larry Michael Sofer Applicant: Larry M. Sofer | Permit status: Finaled | Completion date: June 14, 2012 | Permit id: 1205230009 | |||||
SCORE 99 Connect new sfr to public sewer Date: March 29, 2005 Contractor: Carter Sanitation Applicant: Carter | Permit status: Finaled | Completion date: January 17, 2007 | Permit id: 0304160006 |