Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Mechanical for new sfd Date: October 3, 2000 Contractor: Alliance Mechanical Corporation Applicant: Alliance Mechanical Inc. | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: April 2, 2001 | Permit id: 10020011 | |||||
SCORE 86 Sewer for new sfd Date: August 2, 2000 Contractor: Addington Construction Applicant: Addington Construction Inc, | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: January 30, 2001 | Permit id: 7270010 | |||||
SCORE 86 Plumbing for new sfd Date: June 20, 2000 Contractor: Addington Construction Applicant: Addington Construction Inc, | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: December 17, 2000 | Permit id: 6200021 | |||||
Mechanical for loft addition Date: June 7, 2004 Applicant: Same As Owner | Permit status: Finaled | Completion date: June 28, 2004 | Expiration date: December 4, 2004 | Permit id: 406070008 | |||||
Electrical for loft addition Date: June 7, 2004 Applicant: Same As Owner | Permit status: Finaled | Completion date: June 28, 2004 | Expiration date: December 4, 2004 | Permit id: 406040006 | |||||
SCORE 82 Electrical for new sfd Date: June 27, 2000 Contractor: T Mcgee Electric Inc Applicant: T Mcgee Electric, Inc. | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: December 24, 2000 | Permit id: 6270043 | |||||
Add aluminum patio cover solid roof 596 sq ft Date: March 11, 2002 Value: $9,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: March 27, 2002 | Expiration date: September 7, 2002 | Permit id: 203110047 | |||||
New sfd plan 3cr 2739/643 sq ft Date: June 7, 2000 Value: $242,000 Engineer: Lagoni Bassenian | Applicant: Same As Owner | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: December 4, 2000 | Permit id: 6050075 | |||||
New loft addition over living room 273 sq ft Date: May 27, 2004 Value: $15,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: June 28, 2004 | Expiration date: May 22, 2005 | Permit id: 405270012 | |||||
New sfd plan 3cr 2739 643 sq ft Date: June 7, 2000 Value: $242,000 Engineer: Lagoni Bassenian | Applicant: Same As Owner | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: December 4, 2000 | Permit id: 6050075 | |||||
SCORE 82 Electrical for new sfd Date: June 27, 2000 Contractor: T Mcgee Electric, Inc Applicant: T Mcgee Electric, Inc. | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: December 24, 2000 | Permit id: 6270043 | |||||
SCORE 100 Mechanical for new sfd Date: October 3, 2000 Contractor: Alliance Mechanical Corporation Applicant: Alliance Mechanical Inc. | Permit status: Finaled | Completion date: February 6, 2001 | Expiration date: April 2, 2001 | Permit id: 10020011 |