Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 New sfd plan 2b 3073/635/79 porch Applicant: Davidon Homes | Permit status: Finaled | Completion date: January 29, 2003 | Permit id: 0206280044 | |||||
SCORE 95 New roof mount solar pv 813 sq ft,47 panels,11. 985 kw Applicant: Verengo Inc C. Huaracha | Permit status: Permisud | Permit id: 1203010034 | |||||
SCORE 100 Pool and spa 321 sq ft standard plan 25634 Applicant: Bouquet Construction* | Permit status: Finaled | Completion date: July 8, 2003 | Permit id: 0304010001 | |||||
Electrical for new sfd Date: July 23, 2002 Applicant: Same As Owner | Permit status: Finaled | Completion date: January 29, 2003 | Permit id: 0207100003 | |||||
SCORE 95 Electrical for new roof mount solar pv 47 panels,11. 985 kw upgrade to 225 amp panel,add 125 amp sub panel Date: March 7, 2012 Contractor: Verengo Inc Applicant: Verengo Inc C. Huaracha | Permit status: Permisud | Permit id: 1203010036 | |||||
Mechanical for sfd Date: July 22, 2002 Applicant: Same As Owner | Permit status: Finaled | Completion date: January 29, 2003 | Permit id: 0207090032 | |||||
Plumbing for sfd Date: July 22, 2002 Applicant: Same As Owner | Permit status: Finaled | Completion date: January 29, 2003 | Permit id: 0207090063 | |||||
SCORE 93 Replace water heater Date: November 9, 2009 Contractor: Sriple S Plumbing Applicant: Safaryan Edvard | Permit status: Finaled | Completion date: November 12, 2009 | Permit id: 0911090014 |