Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Retaining wall 46"-86"hx 76long Applicant: Newhall Land And Farm | Permit status: Finaled | Completion date: March 20, 2001 | Permit id: 0002080055 | |||||
SCORE 78 Ti for offices and warehouse,manufacturing 40,0 sq ft Applicant: Combs Miguel (jim Combs) | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 0004200039 | |||||
SCORE 78 Revision for relocate column & beam add at front entrance and mezzanine floor thickness change to 4" thickness Applicant: Combs Miguel (jim Combs) | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 0012260011 | |||||
SCORE 93 Ti for racks storage 12 high Applicant: Grace To You | Permit status: Permisud | Permit id: 0103140003 | |||||
SCORE 93 Re-enforce concrete pit slab for dock leveler to west side of the bldg Applicant: Yaeger Michael F | Permit status: Finaled | Completion date: April 10, 2001 | Permit id: 0104090001 | |||||
SCORE 87 Remove 13 ft of non-bearing wall Applicant: Chacon Construction | Permit status: Permisud | Completion date: October 19, 2009 | Permit id: 0910070006 | |||||
SCORE 87 T. I. To add non-bear walls & (3) doors to create (4) new offices. Add t-bar ceiling 793 sq ft Applicant: Chacon Roy | Permit status: Finaled | Completion date: October 3, 2013 | Permit id: 1305140032 | |||||
SCORE 78 New commercial bldg 400 sq ft shell only Applicant: Combs Miguel (jim Combs) | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 9912300001 | |||||
SCORE 100 (n) ps 800a main cb 800a bus,277/480v; fire alarm tapped ahead of main sump pump truck dock. Date: June 26, 2000 Contractor: John Manninger Electric Applicant: Newhall Land And Farm | Permit status: Finaled | Completion date: December 26, 2000 | Permit id: 0002160019 | |||||
SCORE 96 Tpp for construction Date: May 11, 2000 Contractor: S And S Construction Services Applicant: S And S Construction Services | Permit status: Finaled | Completion date: May 12, 2000 | Permit id: 0005110036 | |||||
SCORE 78 Underground plumbing for future use Date: June 7, 2000 Contractor: Intertex Inc Applicant: Combs Miguel (jim Combs) | Permit status: Permisud | Completion date: March 23, 2001 | Permit id: 0006070007 | |||||
SCORE 78 T. I. Install (1) 100a,(2) 400a service panels,(6) exhaust fans,(2) vending machines,etc. Date: August 25, 2000 Contractor: Intertex Inc Applicant: Combs Miguel (jim Combs) | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 0007190042 | |||||
SCORE 87 Relocate 2 switches Date: October 7, 2009 Contractor: Chacon Construction Services Applicant: Chacon Construction | Permit status: Finaled | Completion date: October 19, 2009 | Permit id: 0910070003 | |||||
SCORE 87 Electrical for tenant improvement to create new office space Date: July 2, 2013 Contractor: Chacon Construction Services Applicant: Chacon Roy | Permit status: Finaled | Completion date: October 3, 2013 | Permit id: 1307020004 | |||||
SCORE 98 Landscape plans 18,695 sq ft Date: May 31, 2000 Contractor: Intertex General Contractors Inc Applicant: Combs & Miguel Architects | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 0005310001 | |||||
SCORE 98 Fine grading for new bldg 75 cyds Date: May 11, 2000 Contractor: Intertex General Contractors Inc Applicant: Sikand Engineering | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 9912230005 | |||||
SCORE 78 T. I. Mechanical Date: September 18, 2000 Contractor: Intertex Inc Applicant: Combs Miguel (jim Combs) | Permit status: Finaled | Completion date: March 23, 2001 | Permit id: 0008140036 | |||||
SCORE 88 Mechanical to replace heating boiler at same location; alter exist duct system add new outlets Date: May 2, 2012 Contractor: Enerlon Inc Applicant: Enerlon | Permit status: Finaled | Completion date: October 3, 2013 | Permit id: 1205020010 | |||||
SCORE 94 Plum for the ti for offices and warehouse Date: March 27, 2001 Contractor: Timken Plumbing Inc Applicant: Timken Plumbing Inc | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 0103270001 | |||||
SCORE 78 Sewer for new commercial bldg Date: June 7, 2000 Contractor: Intertex Inc Applicant: Combs Miguel (jim Combs) | Permit status: Finaled | Completion date: April 18, 2001 | Permit id: 0006070001 |