Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: December 11, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 118217 | |||||
Electrical permit Date: October 30, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 112435 | |||||
Zoning/use permit Date: September 4, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 94803 | |||||
Plumbing permit Date: September 26, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 105493 | |||||
New construction permit Date: September 11, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 100106 | |||||
New construction permit Date: September 11, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 100106 | |||||
Mechanical permit Date: December 11, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 118217 | |||||
Plumbing permit Date: September 26, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 105493 | |||||
Electrical permit Date: October 30, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 112435 | |||||
Zoning use permit Date: September 4, 2007 Client: Nguyen Anthony Nguyen Hong | Permit status: Completed | Permit id: 94803 | |||||
SCORE 96 Installation of carrier gas-fired warm air furnace w ac (sfd) Date: September 21, 2007 Contractor: Maynard Wayne Client: Nguyen Anthony Nguyen Hong | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 5, 2008 | Permit id: 104596 | |||||
SCORE 82 Install new plumbing system Date: September 26, 2007 Contractor: Thomas Scanlan Client: Nguyen Anthony Nguyen Hong | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 30, 2008 | Permit id: 105493 | |||||
SCORE 100 2 amp service and wiring as per nec art 210-12 (east dist) Date: October 30, 2007 Contractor: Vitale Philip J Client: Nguyen Anthony Nguyen Hong | Permit type: Electrical permit | Permit status: Completed | Completion date: April 24, 2008 | Permit id: 112435 | |||||
SCORE 89 Install direct vent fireplace (sfd) Date: December 11, 2007 Contractor: Jack Isacc Azran Client: Nguyen Anthony Nguyen Hong | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 5, 2008 | Permit id: 118217 | |||||
Erect sfd Date: September 4, 2007 Client: Nguyen Anthony Nguyen Hong | Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 4, 2007 | Permit id: 94803 | |||||
SCORE 100 1 amp svs and wiring as per nec 2005 art 210-12 (east dist) Date: December 5, 2007 Contractor: Vitale Philip J Client: Nguyen Anthony Nguyen Hong | Permit type: Electrical permit | Permit status: Completed | Completion date: January 12, 2012 | Permit id: 119882 | |||||
Construct single family dwelling with attached garage in accordance with plans approved under a p #33744 (gladwyn model). Date: September 11, 2007 Client: Nguyen Anthony Nguyen Hong | Permit type: New construction permit | Permit status: Completed | Completion date: January 30, 2008 | Permit id: 100106 |