1hr electrical inspection (main panel) Date: September 9, 2009 Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 9, 2010 | Permit id: 909090039 | |||||
Remove existing secondary containment, lower the area (40x40) by 36"& build secondary contaiment per fire dept. Date: December 16, 2010 Value: $20,000 Applicant: Same As Owner | Permit status: Permisud | Expiration date: December 16, 2011 | Permit id: 1012160032 | |||||
Maintenance & repair work of concrete slab & secondary containment area in the anodizing process bldg. Date: December 28, 2007 Value: $9,000 Applicant: Same As Owner | Permit status: Permisud | Expiration date: June 25, 2008 | Permit id: 712200036 | |||||
Remove damaged & worn-out concrete, (replace with new reinforced concrete floor & sides approx. 6 sq ft). Date: May 4, 2006 Value: $8,000 Applicant: Same As Owner | Permit status: Permisud | Expiration date: April 29, 2007 | Permit id: 605040023 | |||||
Maintenance/repair work of concrete slab & concrete block secondary containments, 6 sq ft. Date: September 1, 2005 Value: $3,000 Applicant: Same As Owner | Permit status: Permisud | Expiration date: August 27, 2006 | Permit id: 509010047 | |||||
New 2nd story wood frame (8 sq ft) & stucco finish for office type usage on the second floor and file storage the first floor. Date: January 8, 2001 Value: $90,000 Engineer: Cooke And Associates | Applicant: Same As Owner | Permit status: Permisud | Expiration date: July 7, 2001 | Permit id: 101080033 | |||||
Maintenance repair work of concrete slab & concrete block secondary containments, 6 sq ft. Date: September 1, 2005 Value: $3,000 Applicant: Same As Owner | Permit status: Permisud | Expiration date: August 27, 2006 | Permit id: 509010047 | |||||
SCORE 84 Install 107. 7 kw roof mounted pv system Engineer: D.Meurs Ecco Engineering | Applicant: Abel Marin | Permit status: Permisud | Expiration date: February 28, 2017 | Permit id: 1511120036 | |||||
SCORE 84 2 amp panel upgrade Date: February 29, 2016 Contractor: Sun Integration Engineer: D.Meurs Ecco Engineering | Applicant: Abel Marin | Permit status: Permisud | Expiration date: February 28, 2017 | Permit id: 1602290014 |