1st flr cnvrt bdrm to den,new family rm,bedroom,laundry, storage carport 3 2nd flr mster bedroom bath 1505 deck 1 Date: January 27, 2011 Value: $211,500 Applicant: Same As Owner | Permit status: Finaled | Completion date: June 18, 2012 | Permit id: 1009230029 | |||||
SCORE 93 Install roof mounted photovoltaic system. Applicant: Alvandi Shawn | Permit status: Finaled | Completion date: May 8, 2013 | Permit id: 1304150055 | |||||
SCORE 64 Temporary power pole Date: March 25, 2011 Contractor: Morado Applicant: Morado Francisco | Permit status: Finaled | Completion date: March 29, 2011 | Permit id: 1103250022 | |||||
SCORE 64 Electrical for addition Date: April 13, 2011 Contractor: Morado Applicant: Morado Francisco | Permit status: Finaled | Completion date: June 18, 2012 | Permit id: 1104130042 | |||||
SCORE 93 Electrical for roof mounted photovoltaic system. Date: April 29, 2013 Contractor: La Solar Systems Inc Applicant: Alvandi Shawn | Permit status: Finaled | Completion date: May 8, 2013 | Permit id: 1304150019 | |||||
SCORE 92 Install new hvac Date: May 10, 2011 Contractor: Air Regional Applicant: Infante Pedro | Permit status: Finaled | Completion date: May 18, 2012 | Permit id: 1105100022 | |||||
SCORE 98 Plumbing for addition Date: March 8, 2011 Contractor: Rudys Mechanical Plumbing Applicant: Cerrillo Rudy | Permit status: Finaled | Completion date: June 18, 2012 | Permit id: 1103080013 | |||||
SCORE 98 Replace existing sewer pipe and connect additional work to house sewer Date: March 8, 2011 Contractor: Rudys Mechanical Plumbing Applicant: Cerrillo Rudy | Permit status: Finaled | Completion date: June 18, 2012 | Permit id: 1103080003 |