Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 61 Ti-build new partition walls to create office spaces. Repair ceiling a Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-40000-189 | |||||
SCORE 95 Install one back-up split system a/c unit on 2nd floor and one new con Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-106 | |||||
Electrical Date: October 13, 2010 Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-40000-203 | |||||
Hvac Date: June 1, 2012 Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-057 | |||||
Install a new fire alarm system in the "marine operation" building. (p Date: November 18, 2010 Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-231 | |||||
SCORE 65 Plan check and permit for additional sprinklers and relocated sprinkl Date: January 12, 2011 Contractor: Vishi Shah Permit type: Fire sprinkler | Permit status: Permit expired | Current use: Commercial | Permit id: 10043-10001-022 | |||||
SCORE 65 Install new crane#2 at port of l. A., apm terminals. Plan check for po Date: November 17, 2010 Contractor: Jose Yutadco Permit type: Electrical | Permit status: Permit closed | Current use: Commercial | Permit id: 10041-10000-151 | |||||
SCORE 61 Electrical Date: November 1, 2010 Contractor: Louis Demeglio Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-210 | |||||
SCORE 65 Fire sprinkler Date: October 12, 2010 Contractor: Vishi Shah Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-022 | |||||
SCORE 56 Installation of medium voltage substation to provide power to future r Date: October 30, 2012 Contractor: Dave Conners Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-032 | |||||
SCORE 100 Electrical Date: December 11, 2012 Contractor: Scott Rothenberger Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-298 | |||||
SCORE 87 Electrical Date: December 27, 2010 Contractor: Sam Amicay Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-40000-255 | |||||
SCORE 89 Elevator Date: May 3, 2011 Contractor: Daniel Caulfield Permit status: Permit finaled | Current use: Commercial | Permit id: 11046-90000-005 | |||||
SCORE 56 Install a new fire alarm system in the building. Date: October 29, 2010 Contractor: Vishtasb Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-216 | |||||
SCORE 100 Plumbing Date: March 2, 2012 Contractor: Yair Porat Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-90000-039 | |||||
SCORE 73 Ti--build new partitions to create office spaces. Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 10016-40000-232 | |||||
SCORE 97 Electrical Date: November 5, 2012 Contractor: Jennifer Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-40000-264 | |||||
SCORE 65 Plan check for addition heads for t-bar. Date: October 12, 2010 Contractor: Vishi Shah Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-022 | |||||
SCORE 87 Construction of 4 s. F. Concrete pad, guard posts, & fencing chain li Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10000-002 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 6of 6 m Date: December 27, 2012 Contractor: Alex Nashalian Permit type: Electrical | Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10005-277 | |||||
SCORE 87 Electrical Date: December 16, 2010 Contractor: Sam Amicay Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-250 | |||||
SCORE 69 Electrical Date: February 11, 2010 Contractor: Arthur Graham Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-024 | |||||
SCORE 97 Electrical Date: October 5, 2012 Contractor: Robert Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10001-222 | |||||
SCORE 61 Ti-build new partition walls to create office spaces. Repair ceiling a Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-40000-180 | |||||
SCORE 98 Prefab (10x25) with high, new monitoring booth, lic. # 1734 app Permit type: Bldg-new | Permit status: Cofo issued | Current use: Commercial | Permit id: 12010-20000-019 | |||||
SCORE 73 Ti- work in maint/repair bldg(pier-400) Date: October 13, 2010 Contractor: Louis Dimeglio Permit type: Hvac | Permit status: Permit expired | Current use: Commercial | Permit id: 10044-10000-097 | |||||
SCORE 98 Four mechanical equipments, size (15 cantelivered steel truces) Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-20000-017 | |||||
Install new crane #1 for port of l. A., apm terminals. Plan check for Date: November 17, 2010 Permit type: Electrical | Permit status: Permit closed | Current use: Commercial | Permit id: 10041-10000-151 | |||||
SCORE 89 Electrical Date: July 18, 2012 Contractor: Sugheim Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-166 | |||||
SCORE 97 Electrical Date: February 26, 2013 Contractor: Jennifer Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-40001-264 | |||||
SCORE 61 Installation of two above ground fuel tanks with four pumps. Class 1 Date: October 14, 2014 Contractor: David Hofeper Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-046 | |||||
SCORE 89 Electrical Date: April 22, 2013 Contractor: Alex Nashalian Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-40007-277 | |||||
Remove, 12 (e) panel antennas, install 2 (n) panel antennas, install 4 Date: October 9, 2013 Value: $25,000 Permit type: Nonbldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13026-10000-003 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 4of 6 r Date: January 15, 2013 Contractor: Alex Nashalian Permit type: Electrical | Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10003-277 | |||||
SCORE 70 Electrical Date: November 12, 2015 Contractor: Britt Edmondson Permit status: Issued | Current use: Commercial | Permit id: 15041-10000-382 | |||||
(n)foundations for manufactured truck recognition systems Date: August 6, 2014 Value: $270,000 Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 14020-40000-017 | |||||
SCORE 72 Electrical Date: July 10, 2013 Contractor: Aric Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-40000-181 | |||||
SCORE 69 Plan check for new installation (5) shore to ship power, including 34. Date: March 20, 2013 Contractor: Mike Gasper Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-057 | |||||
SCORE 66 Electrical Date: May 5, 2014 Contractor: Jeff Bussard Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-118 | |||||
Electrical Date: October 24, 2013 Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-297 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 2of 6 m Date: January 15, 2013 Contractor: Alex Nashalian Permit type: Electrical | Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10001-277 | |||||
SCORE 72 New concrete pads at (2) locations for new electric truck charger Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 13020-40000-009 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 5of 6 t Date: January 15, 2013 Contractor: Alex Nashalian Permit type: Electrical | Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10004-277 | |||||
SCORE 82 Electrical Date: August 6, 2013 Contractor: Wanyue Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-40001-181 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 3of 6 c Date: January 15, 2013 Contractor: Alex Nashalian Permit type: Electrical | Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10002-277 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 1of 6 a Date: January 25, 2013 Contractor: Alex Nashalian Permit type: Electrical | Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10000-277 | |||||
SCORE 89 (4) concrete pads for electrical equipment Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-40000-010 | |||||
SCORE 84 Alteration of (e) wireless installation: add (2) new panel antennas & Permit type: Nonbldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-179 | |||||
SCORE 62 Use of land permit for two 12,0 gallon above ground storage tanks , Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10000-025 | |||||
SCORE 95 Remove, 12 (e) panel antennas, install 2 (n) panel antennas, install 4 Permit type: Nonbldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13026-10000-003 | |||||
SCORE 95 Electrical Date: October 24, 2013 Contractor: Broken Arrow Communications Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-297 | |||||
SCORE 66 (n)foundations for manufactured truck recognition systems Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 14020-40000-017 | |||||
SCORE 97 Date: February 26, 2013 Contractor: Jennifer Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-40001-264 | |||||
SCORE 89 Date: April 22, 2013 Contractor: Alex Nashalian Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-40006-277 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 5of 6 t Date: January 15, 2013 Contractor: Alex Nashalian Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10004-277 | |||||
SCORE 82 Date: August 6, 2013 Contractor: Wanyue Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-40001-181 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 3of 6 c Date: January 15, 2013 Contractor: Alex Nashalian Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10002-277 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 1of 6 a Date: January 25, 2013 Contractor: Alex Nashalian Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10000-277 | |||||
SCORE 89 (4) concrete pads for electrical equipment Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-40000-010 | |||||
SCORE 84 Alteration of (e) wireless installation: add (2) new panel antennas & Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-179 | |||||
SCORE 62 Use of land permit for two 12,0 gallon above ground storage tanks , Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10000-025 | |||||
SCORE 70 Date: November 12, 2015 Contractor: Britt Edmondson Permit status: Issued | Current use: Commercial | Permit id: 15041-10000-382 | |||||
SCORE 61 Installation of two above ground fuel tanks with four pumps. Class 1 Date: October 14, 2014 Contractor: David Hofeper Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-046 | |||||
SCORE 95 Remove, 12 (e) panel antennas, install 2 (n) panel antennas, install 4 Permit status: Permit finaled | Current use: Commercial | Permit id: 13026-10000-003 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 4of 6 r Date: January 15, 2013 Contractor: Alex Nashalian Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10003-277 | |||||
SCORE 66 (n)foundations for manufactured truck recognition systems Permit status: Issued | Current use: Commercial | Permit id: 14020-40000-017 | |||||
SCORE 72 Date: July 10, 2013 Contractor: Aric Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-40000-181 | |||||
SCORE 69 Plan check for new installation (5) shore to ship power, including 34. Date: March 20, 2013 Contractor: Mike Gasper Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-057 | |||||
SCORE 66 Date: May 5, 2014 Contractor: Jeff Bussard Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-118 | |||||
SCORE 95 Date: October 24, 2013 Contractor: Broken Arrow Communications Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-297 | |||||
SCORE 89 Modify existing fire alarm system for pola maersk (port of la) 2of 6 m Date: January 15, 2013 Contractor: Alex Nashalian Permit status: Permit finaled | Current use: Public safety only | Permit id: 12041-10001-277 | |||||
SCORE 72 New concrete pads at (2) locations for new electric truck charger Permit status: Permit finaled | Current use: Commercial | Permit id: 13020-40000-009 |