Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning permit Date: July 10, 2014 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 548242 | |||||
Use permit Date: October 2, 2009 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 240554 | |||||
Electrical permit Date: October 7, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 286577 | |||||
Plumbing permit Date: November 23, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 313327 | |||||
Alteration permit Date: October 29, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 254873 | |||||
Suppression permit Date: July 29, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 291914 | |||||
Mechanical permit Date: May 24, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 280875 | |||||
Plumbing permit Date: January 13, 2011 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 320708 | |||||
Use permit Date: October 2, 2009 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 240554 | |||||
Alteration permit Date: October 29, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 254873 | |||||
Electrical permit Date: October 7, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 286577 | |||||
Mechanical permit Date: May 24, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 280875 | |||||
Zoning permit Date: July 10, 2014 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 548242 | |||||
Plumbing permit Date: January 13, 2011 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 320708 | |||||
Suppression permit Date: July 29, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 291914 | |||||
Plumbing permit Date: November 23, 2010 Client: Khmer Buddhist Humanitari | Permit status: Completed | Permit id: 313327 | |||||
SCORE 96 Make safe permit case no. 597124 for the demolition of the balcony at the 2nd and 3rd floor level and to mechanically fasten the doors and partition off the openings with non-combustible material. Date: September 14, 2017 Contractor: Diantonio And Bongiovanni Client: Khmer Buddhist Humanitari | Permit type: Alteration permit | Permit status: Completed | Completion date: October 2, 2017 | Permit id: 795244 | |||||
SCORE 100 Install heating and air conditioning unit for church. 112,0 btu 90% direct vent appliance Date: May 24, 2010 Contractor: Thorn Dy Client: Khmer Buddhist Humanitari | Permit type: Mechanical permit | Permit status: Completed | Completion date: August 23, 2011 | Permit id: 280875 | |||||
Interior renovations to all three floors as per plans. Separate permits required for mechanical, electrical, plumbing and fire sprinkler. Date: October 29, 2010 Client: Khmer Buddhist Humanitari | Permit type: Alteration permit | Permit status: Completed | Completion date: January 30, 2012 | Permit id: 254873 | |||||
SCORE 56 Converting a prining and sign shop into a church Date: October 2, 2009 Contractor: Bervest Of Penna Inc Client: Khmer Buddhist Humanitari | Permit type: Use permit | Permit status: Completed | Completion date: October 2, 2009 | Permit id: 240554 | |||||
For the relocation of lot lines to create one (1) lot from two (2) existing lots (24 s. 6th street & 2412-26 s. 6th street). Size and location as shown in plans. Date: July 10, 2014 Client: Khmer Buddhist Humanitari | Permit type: Zoning permit | Permit status: Completed | Completion date: July 10, 2014 | Permit id: 548242 | |||||
SCORE 100 Install 1" water service line from city main to curb Date: January 13, 2011 Contractor: Joseph Giannone, Inc Client: Khmer Buddhist Humanitari | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 1, 2011 | Permit id: 320708 | |||||
SCORE 100 16 water closets, 5 vanities, 4 double bowl sinks, 3 bathtubs, 1 stall shower Date: November 23, 2010 Contractor: Anthony S. Rachuba Jr Client: Khmer Buddhist Humanitari | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 12, 2011 | Permit id: 313327 | |||||
SCORE 89 Rough in for elect lights & recps as per 2008 nec, install fire alarm as per nfpa 72 Date: October 7, 2010 Contractor: Don Clayton Client: Khmer Buddhist Humanitari | Permit type: Electrical permit | Permit status: Completed | Completion date: November 3, 2011 | Permit id: 286577 | |||||
SCORE 96 Installation of an automatic sprinkler system Date: July 29, 2010 Contractor: S S Sprinkler Company Inc Client: Khmer Buddhist Humanitari | Permit type: Suppression permit | Permit status: Completed | Completion date: November 21, 2011 | Permit id: 291914 |