SCORE 100 For the installation of a combined automatic fire suppression system throughout a single-family dwelling in accordance with nfpa 13d standards. System is serviced via a 1" fire service main line. Date: August 19, 2016 Contractor: B. M. Consulting Services Inc Client: Harrington Jerome D Ii Short Meg E | Permit type: Suppression permit | Permit status: Completed | Completion date: June 21, 2017 | Permit id: 705362 | |||||
SCORE 100 Install new roof cover as per manufacturers specifications. . New roof coverings shall not be installed without first removing all existing layers when the roof has two or more applications of any type of roof covering. Submit roof certification to inspector for final inspection. Date: July 2, 2014 Contractor: Ne Contractors Inc Client: Harrington Jerome D Ii Short Meg E | Permit type: Alteration permit | Permit status: Expired | Completion date: February 26, 2015 | Permit id: 546964 | |||||
New construction - foundation only - as per approved plans and geotechnical report, Date: May 26, 2016 Client: Harrington Jerome D Ii Short Meg E | Permit type: New construction permit | Permit status: Completed | Completion date: March 27, 2017 | Permit id: 685888 | |||||
SCORE 89 Interior alterations to include framing and sheetrock. Refinsh hardwood floors. Install new kitchen and bathroom. New windows and doors in existing openings. Applicant agrees to limit the construction to comply with ez permit standard for interior alterations, dated january 2011. Deviation from the standard will result in revocation of this permit and imposition of further penalties. All necessary mechanical, electrical, plumbing and fire suppression permits to be obtained. Date: September 4, 2015 Contractor: Red Oak Builders Llc Client: Harrington Jerome D Ii Short Meg E | Permit type: Alteration permit | Permit status: Completed | Completion date: March 27, 2017 | Permit id: 636192 | |||||
For the erection of an attached structure ( nte 38 high); roof deck access from pilothouse; deck at 2nd story rear for a single family household living . Size and location as shown in the application. Date: April 15, 2016 Client: Harrington Jerome D Ii Short Meg E | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 15, 2016 | Permit id: 681695 | |||||
Relocation of lot lines creating 8 lots from 2, converting church rectory into attached sfd w addition to 2128-2134 at 2nd & 3rd floors and third floor addition to 2126 w decks @ 2nd & 3rd floors as detailed on plans Date: May 14, 2015 Client: Harrington Jerome D Ii Short Meg E | Permit type: Zoning permit | Permit status: Completed | Completion date: May 15, 2015 | Permit id: 580378 | |||||
SCORE 100 Rerough and set 6 new fixtures-2 toilets, 1 kitchen sink, 2 lavs, 1 tub the installation will comply with the philadelphia plumbing code 2004 Date: November 3, 2015 Contractor: Star Plumbing And Heating Client: Harrington Jerome D Ii Short Meg E | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 24, 2016 | Permit id: 649641 | |||||
SCORE 100 Install outlets, switches, 36 ceiling lights, (8) 120volt smoke detectors. (1) 220volt 30amp ac circuit. A 200amp service with new circuit breaker box as per nec 2008 Date: October 21, 2015 Contractor: Greg Terinoni Client: Harrington Jerome D Ii Short Meg E | Permit type: Electrical permit | Permit status: Completed | Completion date: March 23, 2017 | Permit id: 646778 | |||||
SCORE 96 Sealing 5" lateral pa20152992461 (commercial)self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: October 27, 2015 Contractor: Frankie D And Benny G Plumbing And Client: Harrington Jerome D Ii Short Meg E | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 1, 2015 | Permit id: 647993 | |||||
SCORE 89 Install (2) hvac systems with ductwork. (sfd) Date: September 7, 2016 Contractor: Alkaun Co Client: Harrington Jerome D Ii Short Meg E | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 21, 2017 | Permit id: 720313 | |||||
SCORE 100 Install 200amp main service,install circuit mb panel. Install all wiring throughout,120v smokes & co detectors throughout per 2008nec (sfd)east district Date: September 13, 2016 Contractor: Baldwin Electrical Const Llc Client: Harrington Jerome D Ii Short Meg E | Permit type: Electrical permit | Permit status: Completed | Completion date: June 30, 2017 | Permit id: 721421 | |||||
Use permit Date: February 11, 2016 Client: Harrington Jerome D Ii Short Meg E | Permit status: Completed | Completion date: February 11, 2016 | Permit id: 668195 | |||||
SCORE 89 New 60,0 btu-92% gas furnace new3-ton condenser and coil. New supply & return duct. Date: November 19, 2015 Contractor: J And J Heating And A C Inc Client: Harrington Jerome D Ii Short Meg E | Permit type: Mechanical permit | Permit status: Completed | Completion date: May 17, 2016 | Permit id: 653407 | |||||
For the lot adjustment to create six(6) lots ( parcel # 1, 2, 3,4, 5 and 6) from one(1) opa account ( 2121-17 e cumberland street)( parcel "a") . Size and location as shown in the application. Date: March 16, 2016 Client: Harrington Jerome D Ii Short Meg E | Permit type: Zoning permit | Permit status: Completed | Completion date: March 16, 2016 | Permit id: 656159 | |||||
SCORE 96 3 wc,4 lavs,2 bath tubs,1 kitchen sink,1 washer box, pex and pvc thorughout, 1" rfss, 5" lateral and 4" main drain (sfd)pa20162351364 self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: August 23, 2016 Contractor: Frankie D And Benny G Plumbing And Client: Harrington Jerome D Ii Short Meg E | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 30, 2017 | Permit id: 716847 | |||||
SCORE 100 For the complete demolition of the exisitng structure. For use as vacant lot. Date: November 25, 2015 Contractor: David Schwartz Contracting Llc Client: Harrington Jerome D Ii Short Meg E | Permit type: Zoning/use permit | Permit status: Completed | Completion date: November 25, 2015 | Permit id: 650557 | |||||
Construction of (six), three story structures with basements and roof decks. Roof decks to be accesssed by pilot house (stairs and landings only), with exception of 2121 cumberland st, which utilizes code compliant spiral staircase. Date: June 14, 2016 Client: Harrington Jerome D Ii Short Meg E | Permit type: New construction permit | Permit status: Completed | Completion date: June 30, 2017 | Permit id: 691189 | |||||
SCORE 100 Asbestos remediation required prior to demolition for the complete demolition of the church on the lot. All work to be done by hand and in a horizontal manner. Protection of pedestrians to be maintained during all demolition activities. Separate permits required for sidewalk closure. Newly exposed wall to be treated. Date: December 9, 2015 Contractor: David Schwartz Contracting Llc Client: Harrington Jerome D Ii Short Meg E | Permit type: Demolition permit | Permit status: Completed | Completion date: March 14, 2016 | Permit id: 650560 |