Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Suppression permit Date: July 12, 2016 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Active | Permit id: 682347 | |||||
New construction permit Date: December 16, 2015 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Active | Permit id: 653423 | |||||
Mechanical permit Date: April 25, 2016 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Active | Permit id: 686769 | |||||
Zoning/use permit Date: August 24, 2015 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Completed | Permit id: 630737 | |||||
Electrical permit Date: December 28, 2016 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Completed | Permit id: 728144 | |||||
Administrative permit Date: January 6, 2017 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Completed | Permit id: 748432 | |||||
Zoning use permit Date: August 24, 2015 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Completed | Permit id: 630737 | |||||
Administrative permit Date: November 2, 2016 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Active | Permit id: 733912 | |||||
Plumbing permit Date: October 21, 2016 Client: Frankford Stacks Lp | Client Company: Robert Shaw | Permit status: Completed | Permit id: 730912 | |||||
SCORE 96 Temporary certificate of occupancy for unit 2c only. Date: January 12, 2017 Contractor: E Built Llc Permit type: Administrative permit | Permit status: Completed | Completion date: January 12, 2017 | Permit id: 749503 | |||||
SCORE 100 250amp service with 4 meters,100amp subpanel each apt,100amp house panel,75 recessed fixtures,1 tamper proof receptacles,interconnect smokes,carbon dioxide detectors,9 phones and 9 cables per 2008m nec (triplex)install fire alarm Date: December 28, 2016 Contractor: Bala Electric Corporation Permit type: Electrical permit | Permit status: Completed | Completion date: January 9, 2017 | Permit id: 728144 | |||||
SCORE 87 For the installation of hvac system to include register diffusers, supply exhaust ductwork, appliances, kitchenhood exhaust fans, and all other work as per approved plans. Separate permit required for any mep and fire suppression work. See ap#702367 for plans. Date: November 22, 2016 Contractor: Alfred M. Edmunds Jr Permit type: Mechanical permit | Permit status: Completed | Completion date: March 9, 2017 | Permit id: 716689 | |||||
SCORE 87 The installation of three high efficency 96%, two stage, multispeed, 40k btu, gas furnaces with evaportor coils and 1. 5 condensers. (all units and ductwork self-contained within tenant space. No penetrations through rated assemblies) Date: April 25, 2016 Contractor: Alfred M. Edmunds Jr Permit type: Mechanical permit | Permit status: Completed | Completion date: January 9, 2017 | Permit id: 686769 | |||||
SCORE 100 Installation of automatic sprinkler system with two inch (2") fire service line, backflow prevention device and fire department connection in accordance with nfpa 13 throughout a four (4) story structure with roof decks. Separate permits required for all electrical and plumbing work. See permit # 681649 for plan. Date: July 12, 2016 Contractor: B. M. Consulting Services Inc Permit type: Suppression permit | Permit status: Completed | Completion date: January 9, 2017 | Permit id: 682347 | |||||
SCORE 96 For the new construction of a four (4) story structure as per plans. Separate permits required for mechanical, electrical, plumbing and fire suppression system. Sprinkler head shall be positioned in the center of bay windows the fire alarm system shall included strobe and horn on the roof deck per bbs variance no. 26167. Part of unity of use as per approved zoning. See application 638741 for plans Date: December 16, 2015 Contractor: E Built Llc Permit type: New construction permit | Permit status: Completed | Completion date: March 7, 2017 | Permit id: 653423 | |||||
SCORE 96 Foundations only as per plans. See permit # 638745 for plans Date: November 13, 2015 Contractor: E Built Llc Permit type: New construction permit | Permit status: Completed | Completion date: February 21, 2017 | Permit id: 644091 | |||||
Relocation of lot lines to create (4) lots from (1) lot. Unity of use. Date: August 24, 2015 Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 24, 2015 | Permit id: 630737 | |||||
SCORE 96 Temporary certificate of occupancy for units 2a,2b and 2c only. Date: November 2, 2016 Contractor: E Built Llc Permit type: Administrative permit | Permit status: Completed | Completion date: March 9, 2017 | Permit id: 733912 | |||||
SCORE 96 Temporary certificate of occupancy for unit 2b only. Date: January 6, 2017 Contractor: E Built Llc Permit type: Administrative permit | Permit status: Completed | Completion date: January 9, 2017 | Permit id: 748432 | |||||
SCORE 93 Excavate and install new sewer line and water line Date: October 21, 2016 Contractor: Madidez Contractors Llc Permit type: Plumbing permit | Permit status: Completed | Completion date: January 9, 2017 | Permit id: 730912 | |||||
Plumbing permit Date: July 20, 2016 Client: Frankford Stacks Lp | Permit status: Active | Permit id: 673687 | |||||
Plumbing permit Date: July 20, 2016 Client: Frankford Stacks Lp | Permit status: Active | Permit id: 673687 | |||||
SCORE 93 New construction: interior plumbing of a 4-story bldg. With (3) dwelling units. The installation will comply with the philadelphia plumbing code 2004. A separate permit is required for the 6" combination sewer and the 2" domestic water service to the street mains. Fuel gas piping and equipment is not included in this permit. Date: July 20, 2016 Contractor: Madidez Contractors Llc Client: Frankford Stacks Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 7, 2017 | Permit id: 673687 |