Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 64 Remove existing roofing material, install new tpo membrane r. M. A. H. Date: July 28, 2014 Contractor: Centimark Corporationford Building Permit type: Roofing | Permit status: Pass | Completion date: July 28, 2014 | Current use: Commercial | Permit id: Bld2014-05360 | |||||
SCORE 59 This project will keep much of the infrastructure in place while demoing portions of the office area in preference to open office configuration. The exiting will remain the same as is currently assigned, no new demising walls. Date: July 9, 2015 Permit type: Permit | Permit status: Accepted - login review | Completion date: July 28, 2015 | Current use: Commercial | Permit id: Bld2015-05172 | |||||
Parking structure repairs, special inspections required. Submit inspection reports as authorized Date: July 22, 2015 Permit type: Permit | Permit status: Pass | Completion date: July 22, 2015 | Current use: Commercial | Permit id: Bld2015-05676 | |||||
Existing wet pipe fire sprinkler system. All areas exposed to structure - no new suspended ceilings. Relocate existing upright sprinklers at roof deck where new partitions create sprinkler over-spacing. Provide additional sprinklers where architectural elements or building support systems create obstructions to discharge. Estimate 16 sprinklers affected. Date: September 9, 2010 Permit type: Fire | Permit status: Pass | Completion date: October 6, 2010 | Current use: Commercial | Permit id: Bld2010-06175 | |||||
SCORE 64 Electrical remodel for new tenant. Date: September 28, 2015 Permit type: Electrical | Permit status: Closed | Completion date: April 20, 2016 | Current use: Commercial | Permit id: Bld2015-07897 | |||||
SCORE 59 280. 5 lin. Ft. Of 6 open fence and gate. Location approved by transportation dept. And slc rea property div. Date: December 14, 2015 Contractor: Allied Fence Coford Building Permit type: Fencing | Permit status: Inspections | Completion date: December 14, 2015 | Current use: Commercial | Permit id: Bld2015-10625 | |||||
SCORE 64 4 fixtures Date: September 28, 2015 Contractor: Reliable Plumbing And Heating Incbuns And Wilcox Permit type: Plumbing | Permit status: Closed | Completion date: April 20, 2016 | Current use: Commercial | Permit id: Bld2015-07878 | |||||
SCORE 59 Parking structure repairs, special inspections required. Submit inspection reports as authorized Date: July 22, 2015 Permit status: Inspections | Completion date: July 22, 2015 | Current use: Commercial | Permit id: Bld2015-05676 | |||||
SCORE 59 This project will keep much of the infrastructure in place while demoing portions of the office area in preference to open office configuration. The exiting will remain the same as is currently assigned, no new demising walls. Date: July 9, 2015 Permit status: Closed | Completion date: April 20, 2016 | Current use: Commercial | Permit id: Bld2015-05172 | |||||
Elec work for interior remodel of office area Date: October 1, 2010 Permit type: Electrical | Permit status: Pass | Completion date: November 1, 2010 | Current use: Commercial | Permit id: Bld2010-06773 | |||||
SCORE 66 No equipment replacement. We are removing existing ducting and replacing with new design. Ducting over 1k. Date: September 14, 2010 Permit type: Mechanical | Permit status: Pass | Completion date: April 22, 2013 | Current use: Commercial | Permit id: Bld2010-06292 | |||||
1 sink Date: September 10, 2010 Permit type: Plumbing | Permit status: Pass | Completion date: October 27, 2010 | Current use: Commercial | Permit id: Bld2010-06234 | |||||
SCORE 66 Interior remodel of office area (non-structural) l. L. Zone: no new plumbing a. H. Date: August 12, 2010 Permit type: Permit | Permit status: Pass | Completion date: November 1, 2010 | Current use: Commercial | Permit id: Bld2010-05521 | |||||
SCORE 66 Interior nonstructural demo only Date: July 2, 2010 Permit type: Permit | Permit status: Pass | Completion date: August 7, 2012 | Current use: Commercial | Permit id: Bld2010-04478 |