New construction permit Date: January 15, 2016 Client: V2 Properties Llc | Permit status: Completed | Permit id: 663699 | |||||
Zoning/use permit Date: January 15, 2016 Client: V2 Properties Llc | Permit status: Completed | Permit id: 663693 | |||||
Plumbing permit Date: February 24, 2016 Client: V2 Properties Llc | Permit status: Completed | Permit id: 671979 | |||||
Mechanical permit Date: March 30, 2016 Client: V2 Properties Llc | Permit status: Completed | Permit id: 680409 | |||||
Suppression permit Date: April 20, 2016 Client: V2 Properties Llc | Permit status: Completed | Permit id: 678621 | |||||
Electrical permit Date: April 18, 2016 Client: V2 Properties Llc | Permit status: Completed | Permit id: 681179 | |||||
Mechanical permit Date: March 30, 2016 Client: Kilcullen Timothy J | Permit status: Completed | Permit id: 680409 | |||||
Zoning use permit Date: January 15, 2016 Client: Kilcullen Timothy J | Permit status: Completed | Permit id: 663693 | |||||
Plumbing permit Date: February 24, 2016 Client: Kilcullen Timothy J | Permit status: Completed | Permit id: 671979 | |||||
New construction permit Date: January 15, 2016 Client: Kilcullen Timothy J | Permit status: Completed | Permit id: 663699 | |||||
Suppression permit Date: April 20, 2016 Client: Kilcullen Timothy J | Permit status: Completed | Permit id: 678621 | |||||
Electrical permit Date: April 18, 2016 Client: Kilcullen Timothy J | Permit status: Completed | Permit id: 681179 | |||||
For the new construction of an attached three-story structure with cellar and roof deck, to be used as a single-family dwelling as per approved plans. See app# 657508 for approved plans. Date: January 15, 2016 Client: Kilcullen Timothy J | Permit type: New construction permit | Permit status: Completed | Completion date: August 4, 2016 | Permit id: 663699 | |||||
SCORE 100 Install one complete hvac system with 90k btu furnace @ 90% with 3 ton a c all new duct work Date: March 30, 2016 Contractor: Ss Mechanicals Hvac Client: Kilcullen Timothy J | Permit type: Mechanical permit | Permit status: Completed | Completion date: August 3, 2016 | Permit id: 680409 | |||||
SCORE 100 Install sanitary drain and water supply lines to all fixtures 1 ks,1 washer machine,1 hwh,3 water closets,4 lavs,2 showers and 1 tub (sfd)the installation will comply with the philadelphia plumbing code 2004 Date: February 24, 2016 Contractor: Shegda Construction Corp Client: Kilcullen Timothy J | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 4, 2016 | Permit id: 671979 | |||||
SCORE 93 Installation of new 13d fire sprinkler system. 1 combo Date: April 20, 2016 Contractor: Harring Fire Protection Llc Client: Kilcullen Timothy J | Permit type: Suppression permit | Permit status: Completed | Completion date: August 4, 2016 | Permit id: 678621 | |||||
New construction of a three story, sfd, with cellar and roof deck accessible by pilot house Date: January 15, 2016 Client: Kilcullen Timothy J | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 15, 2016 | Permit id: 663693 | |||||
SCORE 89 Installing new 200amp service,new wiring throughout,new switches, outlets, gfci, and light fixtures per 2008 nec (sfd)south district Date: April 18, 2016 Contractor: Green Team Electric Inc Client: Kilcullen Timothy J | Permit type: Electrical permit | Permit status: Completed | Completion date: August 4, 2016 | Permit id: 681179 | |||||
SCORE 100 Installation of 5 sewer,curb trap,fai and 1" rfss water service pa20161061294 (sfd)self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: April 21, 2016 Contractor: Shegda Construction Corp Client: Kilcullen Timothy J | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 12, 2016 | Permit id: 686089 |