Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 T/o,instl. Class a b. U. R. On portion of house only Applicant: Bilt-Well Roofing | Permit status: Finaled | Completion date: July 12, 2002 | Permit id: 0106280068 | |||||
SCORE 99 Install 10kw photovoltaic system on roof Applicant: Mcdonald Maureen | Permit status: Finaled | Completion date: April 22, 2007 | Permit id: 0702270040 | |||||
SCORE 77 Build new retaining wall 2 to 8 feet tall x 1 long with 7 piles. Applicant: Anderson Kevin | Permit status: Finaled | Completion date: July 26, 2012 | Permit id: 1202160042 | |||||
SCORE 99 Electrical for photovoltaic Date: February 27, 2007 Contractor: Maxwell Industries Inc Applicant: Mcdonald Maureen | Permit status: Finaled | Completion date: April 22, 2007 | Permit id: 0702270024 | |||||
SCORE 99 Electrical for back up generator. Date: April 25, 2012 Contractor: Maxwell Industries Inc Applicant: Maxwell Industries Inc. | Permit status: Finaled | Completion date: June 28, 2012 | Permit id: 1204250039 | |||||
SCORE 63 Upgrade main service panel to 4 amps. Date: September 10, 2014 Contractor: Maxwell Industries Applicant: Maxwell Dana | Permit status: Finaled | Completion date: December 16, 2014 | Permit id: 1409100059 | |||||
SCORE 89 Copper repipe w/13 fixtures Date: February 15, 2002 Contractor: Plumbing 65 Applicant: Plumbing 65 | Permit status: Finaled | Completion date: February 19, 2002 | Permit id: 0202150016 |