Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning/use permit Date: August 28, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 232775 | |||||
Mechanical permit Date: February 5, 2010 Client: Devine Kevin | Permit status: Completed | Permit id: 259998 | |||||
Zoning permit Date: March 25, 2010 Client: Devine Kevin | Permit status: Completed | Permit id: 258229 | |||||
Alteration permit Date: March 29, 2010 Client: Devine Kevin | Permit status: Completed | Permit id: 268816 | |||||
New construction permit Date: September 8, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 232776 | |||||
Plumbing permit Date: October 15, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 242721 | |||||
Electrical permit Date: November 10, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 247209 | |||||
Permit for the partial demolition of a third story portion of an existing three (3) story attached structure, for the erection of a third story roof deck and for the erection of a roof deck 19" above the third story roof (fourth story addition) as part of an existing single family dwelling. Date: February 3, 2010 Client: Devine Kevin | Applicant: James Lamaina | Permit type: Appeal | Permit status: Granted | Completion date: April 6, 2010 | Permit id: 11008 | |||||
Plumbing permit Date: October 15, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 242721 | |||||
Zoning use permit Date: August 28, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 232775 | |||||
Zoning permit Date: March 25, 2010 Client: Devine Kevin | Permit status: Completed | Permit id: 258229 | |||||
Electrical permit Date: November 10, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 247209 | |||||
New construction permit Date: September 8, 2009 Client: Devine Kevin | Permit status: Completed | Permit id: 232776 | |||||
Alteration permit Date: March 29, 2010 Client: Devine Kevin | Permit status: Completed | Permit id: 268816 | |||||
Mechanical permit Date: February 5, 2010 Client: Devine Kevin | Permit status: Completed | Permit id: 259998 | |||||
Permit for the partial demolition of a third story portion of an existing three (3) story attached structure, for the erection of a third story roof deck and for the erection of a roof deck 19" above the third story roof (fourth story addition) as part of an existing single family dwelling. Date: February 3, 2010 Client: Devine Kevin | Applicant: James Lamaina | Permit type: Appeal | Permit status: Granted | Completion date: April 6, 2010 | Permit id: 11008 | |||||
SCORE 100 New construction of 3 story structure, as per submitted plans. Date: September 8, 2009 Contractor: Lawndale Construction Mgmt Llc Client: Evine Kevin | Permit type: New construction permit | Permit status: Completed | Completion date: February 10, 2010 | Permit id: 232776 | |||||
SCORE 100 Roughin and set fixtures, water closet, bathtub, lav, kitchen sink, washer box Date: October 15, 2009 Contractor: Jr Mcgee Plumbing Llc Client: Evine Kevin | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 10, 2010 | Permit id: 242721 | |||||
SCORE 100 For the erection of a three (3) story attached structure (nte 35 high) with a cellar and a rear deck. Size and location as shown in the application. Single family dwelling. Date: August 28, 2009 Contractor: Lawndale Construction Mgmt Llc Client: Evine Kevin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 28, 2009 | Permit id: 232775 | |||||
SCORE 100 New roof deck over existing 3 story residence. Date: March 29, 2010 Contractor: Lawndale Construction Mgmt Llc Client: Evine Kevin | Permit type: Alteration permit | Permit status: Completed | Completion date: March 28, 2011 | Permit id: 268816 | |||||
New roof deck over existing three story dwelling as per site plans. Date: March 25, 2010 Client: Evine Kevin | Permit type: Zoning permit | Permit status: Completed | Completion date: March 25, 2010 | Permit id: 258229 | |||||
SCORE 100 Installation of 200a service. 25 circuits, outlets, 12 switches, 15 light fixtures, 7 - 120v smokes, 3 phone cable as per 2005 nec (south district) Date: November 10, 2009 Contractor: Sean Kearns Client: Evine Kevin | Permit type: Electrical permit | Permit status: Completed | Completion date: June 22, 2010 | Permit id: 247209 | |||||
SCORE 100 Install direct vent goodman 90% warm air furnace and 3ton a c and related duct work. Date: February 5, 2010 Contractor: Christopher G. Long Client: Evine Kevin | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 4, 2010 | Permit id: 259998 |