Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: August 14, 2014 Client Company: A S I Mgt | Permit status: Completed | Permit id: 545099 | |||||
Use permit Date: September 11, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 101943 | |||||
Plumbing permit Date: April 18, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 678788 | |||||
Electrical permit Date: April 19, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 63338 | |||||
Mechanical permit Date: May 3, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 687143 | |||||
Zoning/use permit Date: July 12, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 680338 | |||||
Use permit Date: March 16, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 673337 | |||||
Suppression permit Date: April 22, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 686614 | |||||
Alteration permit Date: March 14, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 59083 | |||||
Electrical permit Date: April 29, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 686438 | |||||
Fast form building permit Date: May 23, 2007 Client Company: A S I Mgt | Permit status: Active | Permit id: 66966 | |||||
Demolition permit Date: March 21, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 678029 | |||||
Plumbing permit Date: November 14, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 115685 | |||||
Mechanical permit Date: April 19, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 70109 | |||||
Demolition permit Date: November 17, 2015 Client Company: A S I Mgt | Permit status: Completed | Permit id: 652586 | |||||
Alteration permit Date: February 12, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 659628 | |||||
Sign permit Date: July 12, 2016 Client Company: A S I Mgt | Permit status: Active | Permit id: 680340 | |||||
Plumbing permit Date: October 16, 2013 Client Company: A S I Mgt | Permit status: Completed | Permit id: 500550 | |||||
Alteration permit Date: July 31, 2014 Client Company: A S I Mgt | Permit status: Completed | Permit id: 544837 | |||||
Plumbing permit Date: March 27, 2008 Client Company: A S I Mgt | Permit status: Completed | Permit id: 141254 | |||||
Plumbing permit Date: June 20, 2014 Client Company: A S I Mgt | Permit status: Completed | Permit id: 544586 | |||||
Fast form building permit Date: May 23, 2007 Client Company: A S I Mgt | Permit status: Active | Permit id: 66966 | |||||
Mechanical permit Date: April 19, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 70109 | |||||
Plumbing permit Date: October 16, 2013 Client Company: A S I Mgt | Permit status: Completed | Permit id: 500550 | |||||
Suppression permit Date: March 2, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 673523 | |||||
Zoning use permit Date: July 12, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 680338 | |||||
Plumbing permit Date: June 20, 2014 Client Company: A S I Mgt | Permit status: Completed | Permit id: 544586 | |||||
Electrical permit Date: April 29, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 686438 | |||||
Electrical permit Date: August 14, 2014 Client Company: A S I Mgt | Permit status: Completed | Permit id: 545099 | |||||
Alteration permit Date: July 31, 2014 Client Company: A S I Mgt | Permit status: Completed | Permit id: 544837 | |||||
Alteration permit Date: October 10, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 102654 | |||||
Mechanical permit Date: February 25, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 660706 | |||||
Plumbing permit Date: April 18, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 678788 | |||||
Plumbing permit Date: November 14, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 115685 | |||||
Demolition permit Date: November 17, 2015 Client Company: A S I Mgt | Permit status: Completed | Permit id: 652586 | |||||
Electrical permit Date: November 28, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 111524 | |||||
Demolition permit Date: March 21, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 678029 | |||||
Use permit Date: September 11, 2007 Client Company: A S I Mgt | Permit status: Completed | Permit id: 101943 | |||||
Alteration permit Date: February 12, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 659628 | |||||
Sign permit Date: July 12, 2016 Client Company: A S I Mgt | Permit status: Active | Permit id: 680340 | |||||
Use permit Date: February 12, 2016 Client Company: A S I Mgt | Permit status: Completed | Permit id: 663306 | |||||
Plumbing permit Date: March 27, 2008 Client Company: A S I Mgt | Permit status: Completed | Permit id: 141254 | |||||
SCORE 100 Install four new sinks to original rough in Date: June 20, 2014 Contractor: Dominic Garofolo Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 8, 2014 | Permit id: 544586 | |||||
SCORE 84 Installation of (up to 2) 120volt 20amp circuits for freezer in stock area as per nec 2008 (cc district) Date: April 3, 2014 Contractor: Lin R Rogers Electrical Cont Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: June 17, 2014 | Permit id: 528168 | |||||
SCORE 99 For level ii interior alterations to fit-out an existing space for a sit-down coffee shop. Work to include new employee and customer areas, interior non-bearing partitions, finishes and seating areas. Separate permits required for mechanical, electrical, plumbing, and fire suppression systems. Date: July 31, 2014 Contractor: Piece Management Inc Client Company: A S I Mgt | Permit type: Alteration permit | Permit status: Completed | Completion date: September 8, 2014 | Permit id: 544837 | |||||
SCORE 100 Provide relocation of existing equipment and provide lighting,power and communications changes & adds per 2008 nec (coffee shop)installation to comply with article 210. 8(b)(2) of the 2008 nec. Date: August 14, 2014 Contractor: Arrow Electric Services Inc Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: September 27, 2014 | Permit id: 545099 | |||||
SCORE 98 Interior demolition and repairs Date: March 14, 2007 Contractor: Teel Construction Inc Client Company: A S I Mgt | Permit type: Alteration permit | Permit status: Completed | Completion date: September 5, 2007 | Permit id: 59083 | |||||
SCORE 100 Alterations to existing hvac system for first floor retail tenant space #1 to include new ductowrk as per approved plans. Date: May 19, 2017 Contractor: Enerplex Mechanical Systems Client Company: A S I Mgt | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 5, 2017 | Permit id: 781607 | |||||
Temporary certificate of occupancy for 2nd floor Date: September 18, 2017 Client Company: A S I Mgt | Permit type: Administrative permit | Permit status: Completed | Completion date: September 19, 2017 | Permit id: 817069 | |||||
SCORE 100 For mechanical alterations on the second floor of an existing structure, to inlcude new registers diffuers and associated ductwork, as per approved plans. Date: October 13, 2017 Contractor: Direct Air Llc Client Company: A S I Mgt | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 1, 2017 | Permit id: 807261 | |||||
SCORE 100 Alteration: interior plumbing for a 1st floor restaurant. To comply with the philadelphia plumbing code, 2004. Date: April 12, 2016 Contractor: Mmb Contractors Inc Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 19, 2016 | Permit id: 659669 | |||||
SCORE 100 Furnish and install sheet metal duct for 31 hvac systems Date: February 25, 2016 Contractor: Enerplex Mechanical Systems Client Company: A S I Mgt | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 28, 2016 | Permit id: 660706 | |||||
SCORE 99 For use as a sit down restaurant in space a, in the same building with uses as previousy approved. Date: February 12, 2016 Contractor: Mmb Contractors Client Company: A S I Mgt | Permit type: Use permit | Permit status: Completed | Completion date: February 12, 2016 | Permit id: 663306 | |||||
SCORE 99 For level ii interior alterations to fit-out an existing space for a sit-down restaurant. Work to include new employee and customer areas, interior non-bearing partitions, finishes and seating areas. Separate permits required for mechanical, electrical, plumbing, and fire suppression systems. Space shall have access to common restrooms on the 1st floor. Certificate of occupancy on this permit for documentation. Date: February 12, 2016 Contractor: Mmb Contractors Client Company: A S I Mgt | Permit type: Alteration permit | Permit status: Completed | Completion date: July 26, 2016 | Permit id: 659628 | |||||
SCORE 56 Outfitting of new office and classroom space: lighting and receptacles and feeder 4 volt, 225 amp 3 phase feeder in 2-1 2" conduit. (north district) Date: April 19, 2007 Contractor: Harkins John F Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: August 13, 2007 | Permit id: 63338 | |||||
SCORE 100 Ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: November 17, 2015 Contractor: Mmb Contractors Inc Client Company: A S I Mgt | Permit type: Demolition permit | Permit status: Completed | Completion date: May 9, 2016 | Permit id: 652586 | |||||
SCORE 100 Alterations:interior plumbing; 2nd floor; massage therapist -the installation shall comply with the philadelphia plumbing code, 2004 Date: May 24, 2017 Contractor: Terry Abrams Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 1, 2017 | Permit id: 781804 | |||||
SCORE 96 Furnish and install sub panel to feed tenants space, made up of receptacles,switches, feed for heater, massage chair,lights,emergency lights, exit signs. Date: June 19, 2017 Contractor: Pittaoulis Electric Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: September 13, 2017 | Permit id: 782230 | |||||
SCORE 99 For the erection of one (1) flat wall sign in an attached structure as per plans, size and location as shown in application plans, for signage accessory to a retail sales of consumer goods on first floor with other uses in the same building as previously approved, Date: June 15, 2017 Contractor: Horizon Signs Llc Client Company: A S I Mgt | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 15, 2017 | Permit id: 788671 | |||||
SCORE 99 Secure the floor with the metal i beam Date: September 5, 2017 Contractor: Mmb Contractors Client Company: A S I Mgt | Permit type: Alteration permit | Permit status: Completed | Completion date: November 1, 2017 | Permit id: 792825 | |||||
SCORE 99 Replace existing fire alarm devices and relocate and layout for new tenant fitout as per nfpa 72 cc district Date: September 6, 2017 Contractor: William Enley Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: October 19, 2017 | Permit id: 804706 | |||||
SCORE 100 Install a 3 4" backflow prevention isolation device - pwd pre-approval not required - the device must comply with table 608. 1 of the 2009 international plumbing code Date: April 12, 2016 Contractor: Mmb Contractors Inc Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 3, 2016 | Permit id: 683430 | |||||
SCORE 99 To make final connection of a buckeye fire suppressionsystem, for a 48" griddle table system. Fire suppression system is pre-installed by factory ez standard kitchen fire suppression- for the installation of new wet chemical kitchen hood fire suppression system as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: April 18, 2016 Contractor: Reliable Fire Protection Inc Client Company: A S I Mgt | Permit type: Suppression permit | Permit status: Completed | Completion date: July 29, 2016 | Permit id: 684955 | |||||
Fast form building permit Date: November 12, 2007 Client Company: A S I Mgt | Permit status: Completed | Completion date: December 12, 2007 | Permit id: 115019 | |||||
SCORE 86 Provide electrical fitout work for retail store. No fire alarm included. (cc dist) Date: November 28, 2007 Contractor: Michael Varallo Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: December 18, 2007 | Permit id: 111524 | |||||
SCORE 100 Install 3 sinks used for shaving Date: November 14, 2007 Contractor: Ed Scannapieco Plumbing Inc Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 23, 2008 | Permit id: 115685 | |||||
SCORE 99 Relocate 13 registers diffusers - art of shaving (ground floor) Date: November 28, 2007 Contractor: Thomas Hughes Client Company: A S I Mgt | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 21, 2007 | Permit id: 118299 | |||||
SCORE 95 Replace house drain from sidewalk on side of foundation to basement Date: March 27, 2008 Contractor: Roto Rooter Services Company Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 27, 2008 | Permit id: 141254 | |||||
SCORE 100 Replace backflow preventor (retail & office bldg) Date: October 16, 2013 Contractor: Mmb Contractors Inc Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 14, 2015 | Permit id: 500550 | |||||
SCORE 100 Relocate 25 sprinkler heads on 1st floor Date: April 22, 2016 Contractor: Oneida Fire Protection Client Company: A S I Mgt | Permit type: Suppression permit | Permit status: Completed | Completion date: October 28, 2016 | Permit id: 686614 | |||||
SCORE 100 Installation of mechanicals, duct work, new diffusers grills, louvers, accesssories with exising ahu and system. Date: May 3, 2016 Contractor: Enerplex Mechanical Systems Client Company: A S I Mgt | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 28, 2016 | Permit id: 687143 | |||||
SCORE 100 Install wiring and devices for power, lights, phones, internet and cable per 2008 nec (retail)cc district Date: June 7, 2016 Contractor: Wysocki Electric Inc Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: July 18, 2016 | Permit id: 688995 | |||||
SCORE 99 Install new fire alarm notification and initiation devices per nfpa 72 (retail)cc district Date: June 1, 2016 Contractor: William Enley Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: July 18, 2016 | Permit id: 694070 | |||||
SCORE 98 For the installation of an hvac system to include registers diffusers, supply exhaust ductwork, and all other work as per approved plans. Separate permit required for any plumbing and electrical work Date: April 19, 2007 Contractor: Teel Construction Inc Client Company: A S I Mgt | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 24, 2016 | Permit id: 70109 | |||||
For level ii alterations to a mercantile space on the ground floor level of an existing building. Alterations to include the erection of partition walls, provide finishes, furnishing and accessiblity improvements throughout. Building is fully sprinklered. All work to be done per approved plans. If field conditions vary contact design professional prior to the start of any work. Separate permits required for mechanical, electrical, plumbing and fire suppression work. Date: April 5, 2017 Client Company: A S I Mgt | Permit type: Alteration permit | Permit status: Completed | Completion date: June 30, 2017 | Permit id: 763814 | |||||
For a retail sale of consumer goods at space # 1 first floor in the same building with all other uses as previously approved. No sign on this application. Date: March 3, 2017 Client Company: A S I Mgt | Permit type: Use permit | Permit status: Completed | Completion date: March 3, 2017 | Permit id: 763820 | |||||
SCORE 100 Relocate (60) existing sprinkler heads to accommodate newly renovated tenant space. (commercial) Date: April 5, 2017 Contractor: Oneida Fire Protection Client Company: A S I Mgt | Permit type: Suppression permit | Permit status: Completed | Completion date: September 19, 2017 | Permit id: 772724 | |||||
SCORE 96 For a for personal services on 2nd floor, space no. 2 as part of existing structure on the same building with all other approved uses as previously approved. (massage operated by a medical practicioner, professional physical therapist or massage therapist licensed by the commonwealth of pa and not as defined in section 14-603(13) in an existing structure. No sign on this permit. Date: April 18, 2017 Contractor: Innovative Const Solutions Inc Client Company: A S I Mgt | Permit type: Use permit | Permit status: Completed | Completion date: April 18, 2017 | Permit id: 774141 | |||||
SCORE 96 For interior alterations to existing space to include new interior non-load bearing partitions walls, and interior finishes to create a spa salon, as per approved plans. Abatement of asbestos required prior to start of work Date: May 2, 2017 Contractor: Innovative Const Solutions Inc Client Company: A S I Mgt | Permit type: Alteration permit | Permit status: Completed | Completion date: October 27, 2017 | Permit id: 776452 | |||||
SCORE 100 Furnish and install lights, switches and recepts to existing panel as per 2008 nec (cc district) Date: June 2, 2017 Contractor: Michael Kowal Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: June 29, 2017 | Permit id: 779050 | |||||
SCORE 96 Remove 2- pantry sinks; install soil, sanitary, vent and domestic water pipe to large pantry area with 4 sinks Date: May 3, 2017 Contractor: T Kelly Inc Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 6, 2017 | Permit id: 779309 | |||||
SCORE 95 Relocate (3) existing sprinkler heads.(commercial) Date: May 4, 2017 Contractor: Preferred Fire Protection Inc Client Company: A S I Mgt | Permit type: Suppression permit | Permit status: Completed | Completion date: July 5, 2017 | Permit id: 780181 | |||||
SCORE 100 Fast form building permit Date: May 23, 2007 Contractor: Advance Management Corp Client Company: A S I Mgt | Permit status: Active | Completion date: May 23, 2007 | Permit id: 66966 | |||||
SCORE 100 Install 400amp panels 120 2 wiring and devices for restaurant in existing bldg. Work includes lights, power, cctv as per nec 2008 cc district Date: June 17, 2016 Contractor: Wysocki Electric Inc Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: July 25, 2016 | Permit id: 672514 | |||||
SCORE 99 Use to retail sale of eye glasses (retail sale of wearing apparels and accessories) in space # 5 in an existing structure. No sign on this permit. Date: March 16, 2016 Contractor: Mmb Contractors Client Company: A S I Mgt | Permit type: Use permit | Permit status: Completed | Completion date: March 16, 2016 | Permit id: 673337 | |||||
SCORE 100 Ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: March 2, 2016 Contractor: Oneida Fire Protection Client Company: A S I Mgt | Permit type: Suppression permit | Permit status: Completed | Completion date: October 28, 2016 | Permit id: 673523 | |||||
SCORE 100 Ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: March 21, 2016 Contractor: Mmb Contractors Inc Client Company: A S I Mgt | Permit type: Demolition permit | Permit status: Completed | Completion date: May 9, 2016 | Permit id: 678029 | |||||
SCORE 100 Interior alterations to existing space #5 to include partial demolition and construction of new non-load bearing interior partirions to create a retail sales of wearing apparel, as per approved plans. Date: March 29, 2016 Contractor: Mmb Contractors Inc Client Company: A S I Mgt | Permit type: Alteration permit | Permit status: Completed | Completion date: July 18, 2016 | Permit id: 678033 | |||||
SCORE 100 Plumbing alterations in retail space #5 (pearle vision) per the approved plans - the "as noted" pipe sizing on sanitary isometric drawing sheet ecc1 indicates the minimum sizes that must be used to comply with table p-904. 4 and section p-1105 of the philadelphia plumbing code 2004 Date: April 18, 2016 Contractor: Mmb Contractors Inc Client Company: A S I Mgt | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 29, 2016 | Permit id: 678788 | |||||
SCORE 82 Permit to install one flat wall, channel letter sign as per plans. Date: July 12, 2016 Contractor: Elmark Sign And Graphics Inc Client Company: A S I Mgt | Permit type: Sign permit | Permit status: Completed | Completion date: November 27, 2017 | Permit id: 680340 | |||||
SCORE 99 Install new notification devices as per nfpa 72 cc district Date: April 29, 2016 Contractor: William Enley Client Company: A S I Mgt | Permit type: Electrical permit | Permit status: Completed | Completion date: July 18, 2016 | Permit id: 686438 |