Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: May 18, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 341167 | |||||
Electrical permit Date: August 17, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Expired | Permit id: 358723 | |||||
Zoning/use permit Date: July 11, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 350851 | |||||
Mechanical permit Date: August 17, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 358699 | |||||
Suppression permit Date: June 28, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 346417 | |||||
New construction permit Date: June 10, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 339745 | |||||
Zoning use permit Date: July 11, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 350851 | |||||
New construction permit Date: June 10, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 339745 | |||||
Electrical permit Date: August 17, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Expired | Permit id: 358723 | |||||
Suppression permit Date: June 28, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 346417 | |||||
Mechanical permit Date: August 17, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 358699 | |||||
Plumbing permit Date: May 18, 2011 Client: Depalma Joseph Depalma Maria | Permit status: Completed | Permit id: 341167 | |||||
SCORE 91 Install house drain and water distribution piping - hook up sanitary and water supply piping installed by others (modular building company) - turn water on and test throughout - note: stormwater drainage by others - note: revised to show water distribution as 1" to accomodate combination domestic sprinkler Date: May 18, 2011 Contractor: Midatlantic Mechanical Client: Epalma Joseph Depalma Maria | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 10, 2012 | Permit id: 341167 | |||||
SCORE 100 Install 2 amp underground service, install power for amp a c unit, make final connection in junction boxes, test house, as per 2008 nec (east dist) Date: August 17, 2011 Contractor: Rue Electric Inc Client: Epalma Joseph Depalma Maria | Permit type: Electrical permit | Permit status: Expired | Completion date: August 17, 2011 | Permit id: 358723 | |||||
SCORE 100 Install 1 direct vent hvac unit (sfd)- to include conditioned crawl space. Date: August 17, 2011 Contractor: W F Smith Inc Client: Epalma Joseph Depalma Maria | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 10, 2012 | Permit id: 358699 | |||||
Erection of a (1) story townhome max. Height of 28-5 3 8" with acc. Parking for one (1) car. Date: July 11, 2011 Client: Epalma Joseph Depalma Maria | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 13, 2011 | Permit id: 350851 | |||||
SCORE 100 Install new sprinkler system, 13d, 1" line Date: June 28, 2011 Contractor: Fire Protection Industries Inc Client: Epalma Joseph Depalma Maria | Permit type: Suppression permit | Permit status: Completed | Completion date: July 10, 2012 | Permit id: 346417 | |||||
Construction of foundations and placement of a modular townhouse unit in accordance with the pa industrialized housing act. This unit is one of seven units in a row of of townhouses including 15012 thru 15024 dahlia drive. Plans for all seven units indlucded under permit application #339410. Date: June 10, 2011 Client: Epalma Joseph Depalma Maria | Permit type: New construction permit | Permit status: Completed | Completion date: June 29, 2012 | Permit id: 339745 |