Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Alteration permit Date: May 21, 2015 Client: Ssj Group Llc | Permit status: Completed | Permit id: 611789 | |||||
Plumbing permit Date: August 18, 2015 Client: Ssj Group Llc | Permit status: Completed | Permit id: 632436 | |||||
Electrical permit Date: September 24, 2015 Client: Ssj Group Llc | Permit status: Expired | Permit id: 640819 | |||||
Mechanical permit Date: September 21, 2015 Client: Ssj Group Llc | Permit status: Completed | Permit id: 640118 | |||||
Plumbing permit Date: August 18, 2015 Client: Ssj Group Llc | Permit status: Completed | Permit id: 632436 | |||||
Alteration permit Date: July 21, 2015 Client: Ssj Group Llc | Permit status: Completed | Permit id: 622373 | |||||
Electrical permit Date: September 24, 2015 Client: Ssj Group Llc | Permit status: Expired | Permit id: 640819 | |||||
Mechanical permit Date: September 21, 2015 Client: Ssj Group Llc | Permit status: Completed | Permit id: 640118 | |||||
SCORE 100 Replace curb trap,main drain and water service pa20152270125(sfd)self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: August 18, 2015 Contractor: Best Choice Plumbing Inc Client: Ssj Group Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 16, 2015 | Permit id: 632436 | |||||
SCORE 93 Repairs to rear bay overhang. Return to level, sister existing joists, install a new exterior support beam with 8" x 8" support posts on concrete footings. Install r- insulation in joist space at overhang. Provide proper capping and flashing. Work to include the enlargement of stair opening, joist sistering and replacement of three second floor joists with ledger board and hangers. Work to be done in accordance with engineers sketches and review documents. Date: July 21, 2015 Contractor: Aaron Weiner Construction Inc Client: Ssj Group Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: February 18, 2016 | Permit id: 622373 | |||||
SCORE 100 Plumbing alterations throughout an existing single-family dwelling as per philadelphia plumbing code rough in for new plumbing for rehab Date: June 8, 2015 Contractor: Dpc Inc Client: Ssj Group Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 8, 2016 | Permit id: 615657 | |||||
SCORE 93 Interior alterations to include drywall throughout, moisture resistant drywall in the bathroom and kitchen, new windows and doors in existing opening. Applicant agrees to limit the construction to comply with ez permit standard for interior alterations, dated january 2011. Deviation from the standard will result in revocation of this permit and imposition of further penalties. Separate permits required for plumbing, electrical and mechanical work Date: May 21, 2015 Contractor: Aaron Weiner Construction Inc Client: Ssj Group Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: February 18, 2016 | Permit id: 611789 | |||||
SCORE 100 Install new wiring throughout, install 100a service... In accordance with 2008 nec for a one family building Date: September 24, 2015 Contractor: Barry J Yeslow Inc Client: Ssj Group Llc | Permit type: Electrical permit | Permit status: Expired | Completion date: September 24, 2015 | Permit id: 640819 | |||||
SCORE 100 Install (1) hvac system with ductwork (sfd) Date: September 21, 2015 Contractor: Above And Below Heating And Air Client: Ssj Group Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 18, 2016 | Permit id: 640118 |