Electrical permit Date: May 12, 2009 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 214319 | |||||
Electrical permit Date: December 19, 2013 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 507590 | |||||
Operations permit Date: October 14, 2009 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 19943 | |||||
Suppression permit Date: March 1, 2011 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 320734 | |||||
Electrical permit Date: September 14, 2007 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 76787 | |||||
Plumbing permit Date: February 17, 2009 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 201438 | |||||
Electrical permit Date: February 20, 2009 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 201667 | |||||
Electrical permit Date: December 19, 2013 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 507590 | |||||
Operations permit Date: October 14, 2009 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 19943 | |||||
Suppression permit Date: March 1, 2011 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 320734 | |||||
Electrical permit Date: September 14, 2007 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 76787 | |||||
Plumbing permit Date: February 17, 2009 Client: National Investors Penna Limited Partners | Permit status: Completed | Permit id: 201438 | |||||
SCORE 100 Replace 1 lighting fxts with higher efficiency fxts utilizing existing ctrs and sws, re-arrange elect svs feeder connections to balance loads, add new panel, feeder & branch cts per power riser diagram(center city district) Date: September 14, 2007 Contractor: A T B Electric Inc Client: National Investors Penna Limited Partners | Permit type: Electrical permit | Permit status: Completed | Completion date: January 4, 2008 | Permit id: 76787 | |||||
SCORE 100 Add 44 smoke detectors, 19 horn strobes, 8 strobes, 3 hat detectors to existing as per nfpa72 (cc district) Date: December 19, 2013 Contractor: B H Holding Company Client: National Investors Penna Limited Partners | Permit type: Electrical permit | Permit status: Completed | Completion date: April 11, 2014 | Permit id: 507590 | |||||
SCORE 100 Install a new backflow preventer as per plans Date: March 1, 2011 Contractor: Oliver Sprinkler Co Inc Client: National Investors Penna Limited Partners | Permit type: Suppression permit | Permit status: Completed | Completion date: August 19, 2011 | Permit id: 320734 | |||||
SCORE 99 Install 220v branch circuit for make-up air fan in kiln room with switch control. Date: November 4, 2009 Contractor: Shamberg Jules Client: National Investors Penna Limited Partners | Permit type: Electrical permit | Permit status: Completed | Completion date: February 9, 2010 | Permit id: 246211 | |||||
SCORE 86 Install (6) 120v, 20a circuits to supply power. Receptacles for (10) air filter units (cord and plug). All filter equipment will be wired for pir motion control devices and power relays... In accordance with 2005 nec Date: May 12, 2009 Contractor: Joseph Fusco Client: National Investors Penna Limited Partners | Permit type: Electrical permit | Permit status: Completed | Completion date: November 5, 2009 | Permit id: 214319 | |||||
SCORE 86 Install 4 ceiling light fixtures, 4 gfci protected duplex receptacles, 1 switch & 2 120v 20a branch circuits. Date: February 20, 2009 Contractor: Joseph Fusco Client: National Investors Penna Limited Partners | Permit type: Electrical permit | Permit status: Completed | Completion date: December 9, 2009 | Permit id: 201667 | |||||
SCORE 100 First floor, install 3 compartment sink and grease trap. Date: February 17, 2009 Contractor: Ingrams Drain And Sewer Cleaning Client: National Investors Penna Limited Partners | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 14, 2009 | Permit id: 201438 | |||||
SCORE 100 10 9 09-erection of tent for private party Date: October 14, 2009 Contractor: Jefmar Party Rentals Client: National Investors Penna Limited Partners | Permit type: Operations permit | Permit status: Completed | Permit id: 19943 |