Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: December 20, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 375507 | |||||
Mechanical permit Date: May 30, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 401513 | |||||
Zoning/use permit Date: June 21, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 348620 | |||||
Mechanical permit Date: December 30, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 375551 | |||||
Administrative permit Date: August 21, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 423265 | |||||
Electrical permit Date: June 6, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Expired | Permit id: 400526 | |||||
Plumbing permit Date: July 11, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 412330 | |||||
Suppression permit Date: August 1, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 413600 | |||||
Administrative permit Date: May 2, 2013 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 468714 | |||||
Demolition permit Date: August 1, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 355967 | |||||
Zoning admin review Date: May 17, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 336682 | |||||
New construction permit Date: August 18, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 349201 | |||||
Permit for the erection of a two (2) story lodge with overnight sleeping accommodations for a total of twelve (12) persons in twelve (12) units (transient in nature; all persons capable of self-preservation and self-sustaining), a two (2) story conference center with meeting space and dining area each containing sixty (60) seats (total of 1 seats throughout), a one (1) story administration building with offices and accessory storage (not to exceed twenty-five percent (25%) of the gross floor area) and a one (1) story chapel (place of worship) with thirty (30) seats on the same lot with existing two (2) story structure with storage of lawn maintenance equipment and interior off-street parking for two (2) vehicles in the first floor and single-family dwelling unit for use by staff only in the second floor and existing three (3) story convent with overnight accommodations for nineteen (19) persons in ten (10) rooming units (all persons capable of self-preservation and self-sustaining, for Date: December 8, 2010 Client: Cranalieth Spiritual Ctr | Applicant: Stephen G. Pollock, Esquire | Permit type: Appeal | Permit status: Withdrawn | Completion date: January 7, 2011 | Permit id: 14069 | |||||
Permit for the erection of a accessory fence 6feet in height at existing religious assembly site; size & location as shown in application Date: November 5, 2014 Client: Cranalieth Spiritual Ctr | Applicant: Veneta Lorraine | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24028 | |||||
Electrical permit Date: July 13, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Expired | Permit id: 409346 | |||||
Zoning use permit Date: January 21, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 308031 | |||||
Plumbing permit Date: May 22, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 406759 | |||||
Plumbing permit Date: December 20, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 375507 | |||||
Suppression permit Date: August 1, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 413600 | |||||
Demolition permit Date: June 21, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 348622 | |||||
Administrative permit Date: August 7, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 420622 | |||||
New construction permit Date: September 30, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 364461 | |||||
Administrative permit Date: May 2, 2013 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 468708 | |||||
Mechanical permit Date: May 30, 2012 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 401513 | |||||
Mechanical permit Date: December 29, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 375549 | |||||
Zoning admin review Date: May 17, 2011 Client: Cranalieth Spiritual Ctr | Permit status: Completed | Permit id: 336682 | |||||
Permit for the erection of a two (2) story lodge with overnight sleeping accommodations for a total of twelve (12) persons in twelve (12) units (transient in nature; all persons capable of self-preservation and self-sustaining), a two (2) story conference center with meeting space and dining area each containing sixty (60) seats (total of 1 seats throughout), a one (1) story administration building with offices and accessory storage (not to exceed twenty-five percent (25%) of the gross floor area) and a one (1) story chapel (place of worship) with thirty (30) seats on the same lot with existing two (2) story structure with storage of lawn maintenance equipment and interior off-street parking for two (2) vehicles in the first floor and single-family dwelling unit for use by staff only in the second floor and existing three (3) story convent with overnight accommodations for nineteen (19) persons in ten (10) rooming units (all persons capable of self-preservation and self-sustaining, for Date: December 8, 2010 Client: Cranalieth Spiritual Ctr | Applicant: Stephen G. Pollock, Esquire | Permit type: Appeal | Permit status: Withdrawn | Completion date: January 7, 2011 | Permit id: 14069 | |||||
Permit for the erection of a accessory fence 6feet in height at existing religious assembly site; size & location as shown in application Date: November 5, 2014 Client: Cranalieth Spiritual Ctr | Applicant: Veneta Lorraine | Permit type: Appeal | Permit status: Withdrawn | Permit id: 24028 | |||||
SCORE 100 For the construction of a new two (2) story conference center as per plans. Date: May 19, 2011 Contractor: Dale Corp Client: Cranalieth Spiritual Ctr | Permit type: New construction permit | Permit status: Completed | Completion date: November 4, 2013 | Permit id: 330618 | |||||
For administrative approval to zoning use registration permit # 308031, cal. # 14069, for modifications to the originally approved building line of the "conference center" structure. Size and location of changes as shown in application plan. Use within building to remain as meeting space and dining area as part of a charitable institution with spiritual retreats, seminars and conferences as previously approved. Date: May 17, 2011 Client: Cranalieth Spiritual Ctr | Permit type: Zoning admin review | Permit status: Completed | Completion date: October 21, 2014 | Permit id: 336682 | |||||
SCORE 100 2 wc, 2 lavs, 1 ss,1 sink, 1 wh(admin bldg) Date: May 22, 2012 Contractor: Tandem Associates Inc Client: Cranalieth Spiritual Ctr | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 15, 2014 | Permit id: 406759 | |||||
SCORE 93 Install fire alarm as per 2008 nec & nfpa72 Date: July 13, 2012 Contractor: Alan N Isadore Client: Cranalieth Spiritual Ctr | Permit type: Electrical permit | Permit status: Expired | Completion date: July 13, 2012 | Permit id: 409346 | |||||
SCORE 93 Branch,lighting,power to hvac equiptment,200amp 3 phase svc as per 2008 nec. Date: June 6, 2012 Contractor: Alan N Isadore Client: Cranalieth Spiritual Ctr | Permit type: Electrical permit | Permit status: Expired | Completion date: June 6, 2012 | Permit id: 400526 | |||||
SCORE 84 To include installation of 2 hoods - exhaust and make up fans, type 1 kitchen hood and type 2 dishwasher hood as part of prior mechanical permit ap375551. Addl permit req: ansul suppression system for type 1 hood. Date: May 30, 2012 Contractor: Costa And Rihl Inc Client: Cranalieth Spiritual Ctr | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 9, 2013 | Permit id: 401513 | |||||
SCORE 84 Install two (2) kitchen hoods as per plan. Separate fire suppression permit required. Date: April 17, 2012 Contractor: Costa And Rihl Inc Client: Cranalieth Spiritual Ctr | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 9, 2013 | Permit id: 395166 | |||||
SCORE 100 Added work to original permit #341302-installation of one 8" lateral including house trap and vent boxes at curb line. Sanitary drain to connect to existing sanitary piping on property approximately 4 lf of new 8" d. I. P. To be installed with cleanouts (spiritual center) Date: December 9, 2011 Contractor: Meco Constructors Inc Client: Cranalieth Spiritual Ctr | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 15, 2014 | Permit id: 377932 | |||||
SCORE 100 1-ks, 1-lt, 2-wc, 2-lav Date: July 11, 2012 Contractor: Tandem Associates Inc Client: Cranalieth Spiritual Ctr | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 15, 2014 | Permit id: 412330 | |||||
SCORE 76 Running low vo;ltage cabling for audio, video and burglar alarm systems. All cabling will be ran independent of line voltage cabling. Longest run 100ft as per 2008 nec(church)(east dist) Date: July 27, 2012 Contractor: Jb Mac Inc Client: Cranalieth Spiritual Ctr | Permit type: Electrical permit | Permit status: Completed | Completion date: November 7, 2012 | Permit id: 412994 | |||||
SCORE 100 Install kitchen hood fire suppression system. Date: August 1, 2012 Contractor: Atlantic Fire Equipment Co Inc Client: Cranalieth Spiritual Ctr | Permit type: Suppression permit | Permit status: Completed | Completion date: December 9, 2013 | Permit id: 413600 | |||||
SCORE 93 Install 6 phone data lines per 2008 nec Date: July 13, 2012 Contractor: Alan N Isadore Client: Cranalieth Spiritual Ctr | Permit type: Electrical permit | Permit status: Expired | Completion date: July 13, 2012 | Permit id: 416085 | |||||
SCORE 93 Install 12 phone data lines per 2008 nec Date: July 13, 2012 Contractor: Alan N Isadore Client: Cranalieth Spiritual Ctr | Permit type: Electrical permit | Permit status: Expired | Completion date: July 13, 2012 | Permit id: 416087 | |||||
SCORE 83 T. C. O. Days Date: August 21, 2012 Contractor: Dale Construction Company Inc Client: Cranalieth Spiritual Ctr | Permit type: Administrative permit | Permit status: Completed | Completion date: August 22, 2012 | Permit id: 423265 | |||||
SCORE 100 T. C. O. Days Date: August 7, 2012 Contractor: Dale Corp Client: Cranalieth Spiritual Ctr | Permit type: Administrative permit | Permit status: Completed | Completion date: August 14, 2012 | Permit id: 420622 | |||||
180-day tco Date: May 2, 2013 Client: Cranalieth Spiritual Ctr | Permit type: Administrative permit | Permit status: Completed | Completion date: May 2, 2013 | Permit id: 468708 | |||||
For the erection of a 17-0" x 36-0" storage shed. Accessory to an existing religious assembly site; size & location as shown in application. Date: October 5, 2017 Client: Cranalieth Spiritual Ctr | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 5, 2017 | Permit id: 797780 | |||||
SCORE 100 Excavation and installation 3-6" h traps,1-5" h trap,14 area drain inlets,32 rain water conductor,4" domestic water distribution piping to 3 proposed bldg,installation of 4 bio retention stormwater management system Date: May 26, 2011 Contractor: Meco Constructors Inc Client: Cranalieth Spiritual Ctr | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 15, 2014 | Permit id: 341302 | |||||
SCORE 93 Demolition of storage barn. Other structures to be left. Date: June 21, 2011 Contractor: Meco Demolition Inc Client: Cranalieth Spiritual Ctr | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 21, 2011 | Permit id: 348620 | |||||
Construction of foundations for future two story administraivt bldg. Building owner agrees to make any changes necessary after final bldg permit review. Date: August 18, 2011 Client: Cranalieth Spiritual Ctr | Permit type: New construction permit | Permit status: Completed | Completion date: July 5, 2012 | Permit id: 349201 | |||||
SCORE 93 Primary and secondary service, site lighting, branch power, lighting, power to hvac equipment,conduit for telephone and cable temporary service, temporary power and lighting, as per 2008 nec (east dist) Date: April 20, 2012 Contractor: Alan N Isadore Client: Cranalieth Spiritual Ctr | Permit type: Electrical permit | Permit status: Expired | Completion date: April 20, 2012 | Permit id: 349213 | |||||
SCORE 100 Remove one 1,0 gallon gasoline underground storage tank. Soil samples will be collected from excavation. Closure report will be submitted to philadelphila license and inspections. A new building will be constructed in this area, as a result j&j will not backfill the tank excation because footers for the new building will be poured. Date: August 1, 2011 Contractor: J And J Spill Service And Supplies Client: Cranalieth Spiritual Ctr | Permit type: Demolition permit | Permit status: Completed | Completion date: August 30, 2011 | Permit id: 355967 | |||||
Construction of a detached building for used as an administration building foundations constructed under permit 349201 Date: September 30, 2011 Client: Cranalieth Spiritual Ctr | Permit type: New construction permit | Permit status: Completed | Completion date: November 4, 2013 | Permit id: 364461 | |||||
SCORE 100 Install wc, 2 urn, 8 lavs, 1 ms, 7fd, 6 floor sinks, 1-2 comp sink, 1-3 comp sink(administration bldg) Date: December 20, 2011 Contractor: Tandem Associates Inc Client: Cranalieth Spiritual Ctr | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 15, 2014 | Permit id: 375507 | |||||
For the erection of a two (2) story lodge, a two (2) story conference center, a one (1) story administration building and a one (1) story chapel. For the erection of ornamental block walls (n. T. E four feet (4-0") in height). Sizes and locations as shown in application plan. No changes in height or area to other structures existing on the lot. Lodge for overnight accommodations for a total of twelve (12) persons in twelve (12) units (transient in nature; all persons capable of self-preservation); conference center with meeting space and dining area each containing sixty (60) seats; administration building with offices and acc. Storage (n. T. E. 25% of the gfa); chapel (place of worship) with thirty (30) seats all as part of existing charitable institution and for extension of previously approved activities (spiritual retreats, seminars, conferences) on the same lot with existing structures with uses as previously approved. For the creation of thirty-six (36) additional open-air off-stre Date: January 21, 2011 Client: Cranalieth Spiritual Ctr | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 21, 2014 | Permit id: 308031 | |||||
SCORE 84 Installation of hvac equipment, (3) gas furnaces and associated duct and pipe for administrative bldg. Date: December 29, 2011 Contractor: Costa And Rihl Inc Client: Cranalieth Spiritual Ctr | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 9, 2013 | Permit id: 375549 | |||||
SCORE 84 Installation of (6) gas furnaces splits, (1) make up air unit, (1) package unit with incidental ductwork Date: December 30, 2011 Contractor: Costa And Rihl Inc Client: Cranalieth Spiritual Ctr | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 9, 2013 | Permit id: 375551 |