Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Servicechange to 125 amp with overhead Date: January 19, 2006 Contractor: Candlelight Electric Client: D Burton,Mildred Burton | Applicant: Candlelight Electric | Permit type: Electrical | Permit status: Cmp | Completion date: July 22, 2008 | Current use: Single family d | |||||
SCORE 100 Rerun overhead power lines Date: February 20, 2004 Contractor: Xcel Energy Client: D Burton,Mildred Burton | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 90 Replace forced air furnaces - there are two new forced air furnaces among the three units. Date: December 3, 2001 Contractor: Mid West Systems Client: Donald Scrimgeour | Applicant: Mid West Systems | Permit type: Mechanical | Permit status: Cmp | Completion date: May 29, 2002 | Current use: Single family d | |||||
SCORE 96 Adding three gas inserts. One each for units 1, 2, and 3. Date: August 27, 2001 Contractor: The Gas Connection Client: Donald Scrimgeour | Applicant: The Gas Connection | Permit type: Mechanical | Permit status: Cmp | Completion date: January 31, 2002 | Current use: Multifamily dwe | |||||
SCORE 95 Install epdm 1 2 inch woodfiber reroof exist structure Client: Wanee Butler, Professional Property Mgmt | Applicant: Black Roofing Inc | Permit type: Roofing | Permit status: N&v | Current use: Multifamily dwe | |||||
SCORE 100 Manhole access to pull fiber and set new hand hole. Trench to new cool ped. And existing box. Bore from power ped to transformer, (s. Side of cedar). Date: June 5, 2008 Contractor: Qwest Comm Centurylink Client: D Burton,Mildred Burton | Applicant: Qwest Comm/centurylink | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 91 In property sanitary sewer service replacement Date: September 20, 2010 Contractor: The Xcavator Client: Cedar 1240.0 | Applicant: The X-Cavator | Permit type: Wastewater | Permit status: Act | Current use: Multifamily dwe | |||||
SCORE 100 Tennant finish fire alarm addition of new cellular dialer Date: February 23, 2011 Contractor: First Call Electric And Fire Client: Cedar 1240.0 | Applicant: First Call Electric & Fire | Permit type: Fire | Permit status: Cmp | Completion date: April 20, 2011 | Current use: Office - profes | |||||
SCORE 100 Replacement forced air furnace Date: June 24, 2011 Contractor: Save Home Heat Co. Inc Client: Donald Scrimgeour | Applicant: Save Home Heat Co., Inc. | Permit type: Mechanical | Permit status: Cmp | Completion date: September 19, 2011 | Current use: Single family d | |||||
SCORE 95 In-property sewer service repair only Date: September 23, 2013 Contractor: Pipe X Llc Client: Steven Wenglowskyj | Applicant: Pipe X Llc | Permit type: Wastewater | Permit status: Iss | |||||
Contractor tbd. New 2 story duplex having unfinished basements. Scope of work includes associated meps. Date: August 17, 2016 Value: $700,000 Client: Costin Denning | Permit type: Building, electrical, mechanical, plumbing, water, wastewater | Permit status: Iss | Current use: Single family attached dwelling, new, de | Permit id: Pmt2016-01486 | |||||
SCORE 95 Ww replacement in alley and new 1inch tap and water line. Associated with pmt2016-01486 Date: October 18, 2016 Contractor: Premier Excavation Services Client: Costin Denning | Permit type: Water, wastewater, right-of-way | Permit status: Iss | Permit id: Pmt2016-04821 | |||||
SCORE 96 Adding three gas inserts. One each for units 1, 2, and 3. Client: Donald Scrimgeour | Permit type: Mechanical | Permit status: Cmp | Completion date: January 31, 2002 | Current use: Multifamily dwellings, existing | Permit id: Pmt2001-03808 | |||||
SCORE 90 Replace forced air furnaces - there are two new forced air furnaces among the three units. Client: Donald Scrimgeour | Permit type: Mechanical | Permit status: Cmp | Completion date: May 29, 2002 | Current use: Single family detached dwelling, existin | Permit id: Pmt2001-05284 | |||||
Rerun overhead power lines Date: February 20, 2004 Client: D Burton | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2004-00570 | |||||
SCORE 96 Manhole access to pull fiber and set new hand hole. Trench to new cool ped. And existing box. Bore from power ped to transformer, (s. Side of cedar). Date: June 5, 2008 Contractor: Infrasource Construction Services Client: D Burton | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2008-02183 | |||||
SCORE 100 Tennant finish fire alarm addition of new cellular dialer Client: Cedar | Permit type: Fire | Permit status: Cmp | Completion date: April 20, 2011 | Current use: Office - professional, existing | Permit id: Pmt2011-00659 | |||||
SCORE 100 Replacement forced air furnace Client: Donald Scrimgeour | Permit type: Mechanical | Permit status: Cmp | Completion date: September 19, 2011 | Current use: Single family detached dwelling, existin | Permit id: Pmt2011-20179 | |||||
SCORE 65 Total demo of existing house and detached garage built in 19 per his2015-00222 approval. Date: October 19, 2015 Contractor: Viking Holdings Inc Client: Living Burton | Permit type: Demolition | Permit status: Cmp | Completion date: June 30, 2016 | Current use: Single family detached dwelling, existin | Permit id: Pmt2015-04641 | |||||
Contractor tbd. New 2 story duplex having unfinished basements. Scope of work includes associated meps. (change in description of work -- both basements to be finished sf with a full bathroom as shown on original plans but labeled inchunfinished basementinch) Date: August 17, 2016 Value: $700,000 Client: Costin Denning | Permit type: Building, electrical, mechanical, plumbing, water, wastewater | Permit status: Iss | Current use: Single family attached dwelling, new, de | Permit id: Pmt2016-01486 | |||||
Q3 will be installing a new gas service via directional bore, there will be one 5x5 pit, & two potholes, job# 12504035 Date: May 17, 2017 Client: Costin Denning | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2017-02086 | |||||
SCORE 95 Install epdm 1 2 inch woodfiber reroof exist structure Client: Wanee Butler | Permit type: Roofing | Permit status: N&v | Current use: Multifamily dwellings | Permit id: Pmt2000-00017 | |||||
SCORE 95 Servicechange to 125 amp with overhead Client: D Burton | Permit type: Electrical | Permit status: Cmp | Completion date: July 22, 2008 | Current use: Single family detached dwelling, existin | Permit id: Pmt2006-00210 | |||||
SCORE 91 In property sanitary sewer service replacement Contractor: The Xcavator Client: Cedar | Permit type: Wastewater | Permit status: Act | Current use: Multifamily dwellings, repair | Permit id: Pmt2010-04069 | |||||
SCORE 59 Construction of new 3-story duplex with full finished basement. Basement unit to have 2 bedrooms with 2 full baths. Second unit to have 4 bedrooms with a study bedroom 5 and 4. 5 baths. Detached garage by separate permit pmt2015-04835. Value: $600,000 Contractor: Siggstaver Construction Llc Client: Living Burton | Permit type: Building, electrical, mechanical, plumbing, water, wastewater | Permit status: N&v | Current use: Single family attached dwelling, new, de | Permit id: Pmt2015-04834 | |||||
SCORE 59 New, detached, single-story, 2-car garage accessory to duplex constructed through pmt2015-04834 Value: $40,000 Contractor: Siggstaver Construction Llc Client: Living Burton | Permit type: Building, electrical | Permit status: N&v | Current use: Garage - detached, new | Permit id: Pmt2015-04835 | |||||
SCORE 100 New 1 amp service hook up for phone cabinet. In row in front of 2844 broadway. Date: March 9, 2009 Contractor: Mc Kusker Electric Client: R Name | Applicant: Mc Kusker Electric | Permit type: Electrical | Permit status: Cmp | Completion date: March 24, 2009 | Current use: Telecommunicati | |||||
SCORE 100 New 1 amp service hook up for phone cabinet. In row in front of 2844 broadway. Client: R Name | Permit type: Electrical | Permit status: Cmp | Completion date: March 24, 2009 | Current use: Telecommunications, existing | Permit id: Pmt2009-00768 |