Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 8" water tap Date: August 9, 2002 Contractor: Twin Peaks Utilities And Infrast. Co Client: Lizard Vail | Applicant: Twin Peaks Utilities & Infrast. Co | Permit type: Water, flood not req | Permit status: Act | |||||
SCORE 100 Set crane Date: December 20, 2001 Contractor: Wyatt Construction Co Inc Client: Lizard Vail | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Demolition of bank drive-up facility. Conditions of site review disposition must be met prior to application of future building permits. Date: July 16, 2001 Contractor: Wyatt Construction Company Client: Lizard Vail | Applicant: Wyatt Construction Company | Permit type: Demolition | Permit status: N&v | Current use: Financial insti | |||||
SCORE 89 Tenant remodel of the existing walk up plazas at the east and west ends. Client: Lizard Vail | Applicant: Deneuve Construction | Permit type: Building, electrical | Permit status: Cmp | Completion date: April 10, 2001 | Current use: Financial insti | |||||
SCORE 89 Tenant remodel of the existing walk up plazas at the east and west ends. Client: Lizard Vail | Permit type: Building, electrical | Permit status: Cmp | Completion date: April 10, 2001 | Current use: Financial institution, tenant remodel | Permit id: Pmt2001-00448 | |||||
SCORE 95 Set crane Date: December 20, 2001 Contractor: Wyatt Construction Co, Inc Client: Lizard Vail | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2001-05486 | |||||
SCORE 95 8inch water tap Contractor: Twin Peaks Utilities And Infrast. Co Client: Lizard Vail | Permit type: Water, flood not required | Permit status: Act | Permit id: Pmt2002-03458 | |||||
SCORE 95 Tower crane 6-15-2006 to 3-15-2007 unloading offof 11th Date: June 1, 2006 Contractor: Wyatt Construction Company Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Right-of-way | Permit status: N&v | |||||
SCORE 95 Erection of a tower crane at "trios" site. Date: May 31, 2006 Contractor: Wyatt Construction Company Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Right-of-way | Permit status: N&v | Current use: Commercial/reta | |||||
SCORE 95 18 residential units and core and shell commercial, two units on the fourth floor are unfinished a separate permit will be applied for later to finish these units. Four stories. 48862 sf residential and 43,443 sf commercial. See lur2005-00033. Client: Limited 1155.0 | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Co | Current use: Commercial/reta | |||||
SCORE 100 Electrical permit for temporary construction power. Date: May 4, 2006 Contractor: Core Electric Inc Client: Limited 1155.0 | Applicant: Core Electric, Inc. | Permit type: Electrical | Permit status: N&v | Current use: Commercial/reta | |||||
SCORE 100 Removal of 1 street light pole and opening of street light feed on the corner of canyon and 11th. Date: April 6, 2006 Contractor: Xcel Energy Client: Limited 1155.0 | Applicant: Xcel Energy | Permit type: Right-of-way, flood | Permit status: Iss | |||||
SCORE 100 Pedestrian control for shoring work. Close 11th sidewalk from canyon to alley. Close canyon sidewalk from broadway to 11th. April 2006-march 2007 Date: March 28, 2006 Contractor: Wyatt Construction Co Inc Client: Limited 1155.0 | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Install temporary sidewalk. Pedestrian control 3 23 06-3 27 06. Date: March 23, 2006 Contractor: Wyatt Construction Co Inc Client: Limited 1155.0 | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Cut off existing 10" mw gas main in 11th street. Tie new 2" fb ip gas main into existing 2" fb on west side of 11th. Traffic control 3 27 06-4 27 06. Job no 10774367 Date: March 21, 2006 Contractor: Xcel Energy Client: Limited 1155.0 | Applicant: Xcel Energy | Permit type: Right-of-way, flood | Permit status: Iss | |||||
SCORE 100 Traffic control on wednesday 1 25 06 from 9am to 12 noon only. Date: January 24, 2006 Contractor: Wyatt Construction Co Inc Client: Limited 1155.0 | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Remove padmount transformer and re-feed primary conductor back to switch cabinet. (1 23 06-2 1 06) Date: January 30, 2006 Contractor: Xcel Energy Client: Limited 1155.0 | Applicant: Xcel Energy | Permit type: Right-of-way, flood | Permit status: Iss | |||||
SCORE 60 Flood development permit: the existing building will be demolished and replaced with a new 4 story mixed use building with underground parking. The proposed building will be floodproofed. Revised on 7 19 07 to include planter pots in the flood fringe. Date: March 12, 2006 Contractor: Limited 1155.0 Client: Limited 1155.0 | Applicant: Limited 1155.0 | Permit type: Flood floodproof str | Permit status: Cmp | Completion date: March 19, 2008 | |||||
SCORE 100 Demo of existing office restaurant retail building. 14,4 sf Date: January 17, 2006 Contractor: William D. Hillen Corporation Client: Limited 1155.0 | Applicant: William D. Hillen Corporation | Permit type: Demolition | Permit status: Cmp | Completion date: July 3, 2008 | Current use: Commercial/reta | |||||
SCORE 100 Cut off 1 1 4" gas service at main due to demo of building. Date: December 19, 2005 Contractor: Xcel Energy Client: Limited 1155.0 | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Foundation package for mixed used building. See lur2005-00033. Client: Limited 1155.0 | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: N&v | Current use: Parking garage, | |||||
SCORE 95 Grading permit to allow a 5 c. Y. Stockpile for backfill for 13 walnut. Date: February 11, 2005 Contractor: Wyatt Construction Company Client: Limited 1155.0 | Applicant: Wyatt Construction Company | Permit type: Grading | Permit status: N&v | |||||
SCORE 100 Remove primary in conduit and re-install new primary conductor from sw cab in alley to manhole on east side of broadway. Job no 10647393. Date: April 21, 2006 Contractor: Xcel Energy Client: Limited 1155.0 | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 71 Floodplain development permit for redevelopment of the existing trios site. The scope includes demolition of the existing building and construction of a new four-story mixed use building with a 28,5 s. F. Footprint. Date: June 8, 2004 Contractor: Scott Cox And Associates Inc Client: Limited 1155.0 | Applicant: Scott, Cox & Associates, Inc. | Permit type: Flood floodproof str | Permit status: Wdn | Current use: Commercial/reta | |||||
SCORE 60 1 1 2" water tap - city of boulder project; barb kenyon, project manager Date: August 13, 2003 Contractor: Limited 1155.0 Client: Limited 1155.0 | Applicant: Limited 1155.0 | Permit type: Water | Permit status: Act | |||||
SCORE 63 Erect 2 tents, 1 x 30, and 1 x 10, both open sided, for temporary wine food festival in the trios parking lot to be held 8 31 02 Client: Limited 1155.0 | Applicant: Heather Christensen | Permit type: Temporary event | Permit status: N&v | Current use: Restaurant, exi | |||||
SCORE 93 Fire suppression system Date: March 27, 2001 Contractor: Rocky Mountain Fire And Safety Client: Limited 1155.0 | Applicant: Rocky Mountain Fire & Safety | Permit type: Fire | Permit status: Cmp | Completion date: April 11, 2001 | Current use: Restaurant, exi | |||||
SCORE 95 Changes to 4th level removing 2 dwellings and expantion of east side for core and shell future office space. Changes add 3,167 sf to existing 92,308 sf building. Due to call-up schedule permit cannot be issued until 10 7 06 or after. Check with brent bean or brian holmes to see if called up Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building | Permit status: N&v | Current use: Office - profes | |||||
SCORE 100 Backfill & crane work traffic control 9-12-06 to 10-30-06 Date: September 11, 2006 Contractor: Wyatt Construction Co Inc Client: Condominiu Canyon | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Fire alarm system - core and shell Date: September 19, 2006 Contractor: Core Electric Inc Client: Condominiu Canyon | Applicant: Core Electric, Inc. | Permit type: Fire | Permit status: N&v | Current use: Commercial/reta | |||||
SCORE 100 New 6" fire line, water main extension, fire hydrant and water services & sewer manhole. Sales tax on this permit. Date: October 6, 2006 Contractor: Ez Excavating Inc Client: Condominiu Canyon | Applicant: E-Z Excavating, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Fire sprinkler system - core and shell with finish residential on the 2nd and 3rd floor only. Date: October 24, 2006 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cls | Current use: Commercial/reta | |||||
SCORE 95 Tenant finish for first national bank. 19,584 sf. Two floors Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Financial insti | |||||
SCORE 70 Finish of core and shell space as residential unit #406. Proposed 5,2 s. F. Unit to have 2 bedrooms and 4 baths. Client: Condominiu Canyon | Applicant: Wyatt Lofts Ii | Permit type: Building, electrical | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Multifamily dwe | |||||
SCORE 95 Sign permit for new internally illuminated wall signs - first national bank of colorado and atm Date: March 13, 2007 Contractor: Young Electric Sign Co Client: Condominiu Canyon | Applicant: Young Electric Sign Co | Permit type: Electrical, sign | Permit status: Cmp | Completion date: December 17, 2007 | Current use: Financial insti | |||||
SCORE 70 Residential tenant finish for unit #404. 4297 sf unit with three bedrooms, 4 bathrooms. Client: Condominiu Canyon | Applicant: Wyatt Lofts Ii | Permit type: Building, electrical | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Multifamily dwe | |||||
SCORE 98 Set crane in broadway for 4 hrs. Date: December 13, 2006 Contractor: Sterling Crane Llc Client: Condominiu Canyon | Applicant: Sterling Crane Llc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Installation of a 4 stop, # 60 temporary equipment material & man lift on exterior of building. Anticipated removal date aug sept 2007. Date: January 24, 2007 Contractor: Wyatt Construction Company Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Elevator | Permit status: Cmp | Completion date: March 16, 2007 | Current use: Commercial/reta | |||||
SCORE 95 Elevator new 5 stop elevator hydraulic. Passenger Date: February 5, 2007 Contractor: Thyssenkrupp Elevator Client: Condominiu Canyon | Applicant: Thyssenkrupp Elevator | Permit type: Elevator | Permit status: Cmp | Completion date: April 25, 2007 | Current use: Commercial/reta | |||||
SCORE 100 Fire sprinkler system - first national bank Date: January 30, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: January 2, 2008 | Current use: Office - profes | |||||
SCORE 93 Tenant finish of fourth floor office space, 105 sf for accounting office. Client: Condominiu Canyon | Applicant: Layne Mitchell | Permit type: Building, electrical | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Office - profes | |||||
SCORE 98 Interior tenant finish, 26 sf, to include the addition of one hand sink, one kitchen sink and a dishwasher. Client: Condominiu Canyon | Applicant: Rhinotrax Construction Inc | Permit type: Building, electrical | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Office - admini | |||||
SCORE 95 Tenant finish for 6264 sf office space for amg national trust bank, suite 310 Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Financial insti | |||||
SCORE 98 Setting crane in canyon to remove tower crane Date: March 1, 2007 Contractor: Sterling Crane Llc Client: Condominiu Canyon | Applicant: Sterling Crane Llc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 1155 canyon fourth floor east side tennant finish sprinkler system Date: March 2, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: December 29, 2007 | Current use: Office - profes | |||||
SCORE 100 Install street lighting Date: March 7, 2007 Contractor: Xcel Energy Client: Condominiu Canyon | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Electrical permit for tilt-up solar pv system on rooftop. 34. 4 kw system. Date: March 7, 2007 Contractor: Independent Power Systems Client: Condominiu Canyon | Applicant: Independent Power Systems | Permit type: Photovoltaic | Permit status: Cmp | Completion date: July 27, 2007 | Current use: Commercial/reta | |||||
SCORE 100 R&r sidewalk on broadway, pour detached walk on canyon, & r&r c&g on 11th, resurface 11th from canyon to alley traffic control for 2 months Date: March 14, 2007 Contractor: Wyatt Construction Co Inc Client: Condominiu Canyon | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Tenant finish for elevator lobby on second floor. (526 sf) no plumbing Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: N&v | Current use: Office - profes | |||||
SCORE 100 1155 canyon fire alarm 1st national bank Date: March 27, 2007 Contractor: Core Electric Inc Client: Condominiu Canyon | Applicant: Core Electric, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: April 13, 2011 | Current use: Office - profes | |||||
SCORE 100 Fire alarm 1155 canyon ekh&s tennant finish Date: March 28, 2007 Contractor: Core Electric Inc Client: Condominiu Canyon | Applicant: Core Electric, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: June 7, 2007 | Current use: Office - profes | |||||
SCORE 95 Tenant finish of 6224 sf on 2nd floor, professional business offices for "wachovia securities" Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Co | Current use: Office - profes | |||||
SCORE 100 1155 canyon amg national trust bank fire alarm tennant finish Date: April 11, 2007 Contractor: Core Electric Inc Client: Condominiu Canyon | Applicant: Core Electric, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: April 13, 2011 | Current use: Office - profes | |||||
SCORE 100 1155 canyon amg national trust bank tennant finish sprinkler plans Date: April 6, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: April 8, 2011 | Current use: Office - profes | |||||
SCORE 59 Plumbing permit for backflow preventor for irrigation system Date: April 13, 2007 Contractor: G.E. Enterprises Inc Client: Condominiu Canyon | Applicant: G.E. Enterprises, Inc. | Permit type: Plumbing | Permit status: Cmp | Completion date: June 25, 2010 | Current use: Commercial/reta | |||||
SCORE 100 Tennant finish for 1155 canyon acquire first floor south west side. Date: April 18, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: May 20, 2008 | Current use: Office - profes | |||||
SCORE 95 Tennant finish for office space, suite 302, first western trust bank. Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Co | Current use: Financial insti | |||||
SCORE 71 Acquire tennant finish fire alarm Date: May 3, 2007 Contractor: Hamilton Electric Const Co Client: Condominiu Canyon | Applicant: Hamilton Electric Const Co | Permit type: Fire | Permit status: Cmp | Completion date: May 20, 2008 | Current use: Office - profes | |||||
SCORE 100 Wachovia fire alarm ti Date: May 7, 2007 Contractor: Core Electric Inc Client: Condominiu Canyon | Applicant: Core Electric, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: August 30, 2007 | Current use: Office - profes | |||||
SCORE 95 Sign permit application for acquire ste 1 for new permanent non-electric suspended soffit sign. Date: May 23, 2007 Contractor: 20 Communications Client: Condominiu Canyon | Applicant: 20/ Communications | Permit type: Sign | Permit status: Cmp | Completion date: March 14, 2008 | Current use: Office - profes | |||||
SCORE 100 Suite 406 pepperzak loft Date: May 30, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: April 8, 2011 | Current use: Single family a | |||||
SCORE 95 Units 307 and 209 will be remodelled and combined into a new unit 516, unit 207 will also be remodelled. Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Co | Current use: Multifamily dwe | |||||
SCORE 100 Tennant finish suite 404 polk residence Date: May 31, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: February 8, 2008 | Current use: Single family a | |||||
SCORE 100 Tennant finish first western trust bank 3rd floor east side Date: May 31, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: April 8, 2011 | Current use: Financial insti | |||||
SCORE 95 Sign permit for 3 signs for new permanent internally illuminated wall signs see (pmt2007-02282) Date: June 22, 2007 Contractor: Young Electric Sign Co Client: Condominiu Canyon | Applicant: Young Electric Sign Co | Permit type: Sign | Permit status: Cmp | Completion date: October 1, 2007 | Current use: Office - profes | |||||
SCORE 95 Sign permit for new elecric awning sign see (pmt2007-02281) Date: June 22, 2007 Contractor: Young Electric Sign Co Client: Condominiu Canyon | Applicant: Young Electric Sign Co | Permit type: Sign | Permit status: Cmp | Completion date: October 1, 2007 | Current use: Office - profes | |||||
SCORE 95 Close west bound lane of canyon for 2 days. Move in Date: June 11, 2007 Contractor: Wyatt Construction Company Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Right-of-way | Permit status: N&v | |||||
SCORE 95 Sign permit for 2 non-electric wall signs "wacovia securities" Date: June 22, 2007 Contractor: Husky Signs And Graphics Inc Client: Condominiu Canyon | Applicant: Husky Signs & Graphics Inc | Permit type: Sign | Permit status: N&v | Current use: Financial insti | |||||
SCORE 95 Office remodel to existing space. Second floor. 3 sf Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: N&v | Current use: Financial insti | |||||
SCORE 100 First western bank fire alarm tenant finish Date: June 25, 2007 Contractor: Core Electric Inc Client: Condominiu Canyon | Applicant: Core Electric, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: August 28, 2007 | Current use: Office - profes | |||||
SCORE 100 Wachovia tenant finish Date: June 29, 2007 Contractor: Fire Defense Inc Client: Condominiu Canyon | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: October 3, 2007 | Current use: Office - profes | |||||
SCORE 56 Date: July 2, 2007 Contractor: Condominiu Canyon Client: Condominiu Canyon | Applicant: Condominiu Canyon | Permit status: Act | |||||
SCORE 95 Install temporary scaffold stair 5 from building face with overhead walkway. August 15-november 1. Date: August 10, 2007 Contractor: Wyatt Construction Company Client: Condominiu Canyon | Applicant: Wyatt Construction Company | Permit type: Right-of-way | Permit status: N&v | |||||
SCORE 95 Installation of non-illuminated wall sign "amg national trust bank" on south elevation of building. Date: August 20, 2007 Contractor: Rainbow Signs Inc Client: Condominiu Canyon | Applicant: Rainbow Signs Inc | Permit type: Sign | Permit status: Cmp | Completion date: March 14, 2008 | Current use: Financial insti | |||||
SCORE 100 Set dumpster on west side of 11th street in on-street parking spaces. 12 27 2007 to 2 28 2008 Date: August 16, 2007 Contractor: Wyatt Construction Co Inc Client: Condominiu Canyon | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Electrical and building permit for tilt-up solar pv system on existing rooftop. 10. 32 kw system. Date: August 17, 2007 Contractor: Namaste Solar Electric Inc Client: Condominiu Canyon | Applicant: Namaste Solar Electric Inc | Permit type: Building, photovolta | Permit status: Cmp | Completion date: February 22, 2008 | Current use: Multifamily dwe | |||||
SCORE 95 Sign permit for non-electric wall sign "baqnk drive-up & atm, parking" Date: August 31, 2007 Contractor: Young Electric Sign Co Client: Condominiu Canyon | Applicant: Young Electric Sign Co | Permit type: Sign | Permit status: Cmp | Completion date: March 14, 2008 | Current use: Financial insti | |||||
SCORE 100 Set boom truck in parking on 11th to lift material into building. Intermittanly for 2 months Date: September 6, 2007 Contractor: Wyatt Construction Co Inc Client: Condominiu Canyon | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 New wall sign first western trust bank Date: October 18, 2007 Contractor: Rainbow Signs Inc Client: Condominiu Canyon | Applicant: Rainbow Signs Inc | Permit type: Sign | Permit status: N&v | Current use: Financial insti | |||||
SCORE 93 Fire suppression system Client: Limited | Permit type: Fire | Permit status: Cmp | Completion date: April 11, 2001 | Current use: Restaurant, existing | Permit id: Pmt2001-01095 | |||||
Cut off 1 1 4" gas service at main due to demo of building. Date: December 19, 2005 Client: Limited | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2005-04843 | |||||
Floodplain development permit for redevelopment of the existing trios site. The scope includes demolition of the existing building and construction of a new four-story mixed use building with a 28,5 s. F. Footprint. Client: Limited | Permit type: Flood floodproof structure | Permit status: Wdn | Current use: Commercial/retail, new | Permit id: Pmt2004-02189 | |||||
1 1 2" water tap - city of boulder project; barb kenyon, project manager Date: August 13, 2003 Client: Limited | Permit type: Water | Permit status: Act | Permit id: Pmt2003-03417 | |||||
Tenant finish of fourth floor office space, 105 sf for accounting office. Date: March 1, 2007 Value: $222 Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Office - professional, tenant finish | Permit id: Pmt2007-00419 | |||||
Install street lighting Date: March 7, 2007 Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-00740 | |||||
SCORE 95 R&r sidewalk on broadway, pour detached walk on canyon, & r&r c&g on 11th, resurface 11th from canyon to alley traffic control for 2 months Date: March 14, 2007 Contractor: Wyatt Construction Co, Inc Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-00781 | |||||
SCORE 95 1155 canyon amg national trust bank fire alarm tennant finish Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: April 13, 2011 | Current use: Office - professional, existing | Permit id: Pmt2007-01205 | |||||
SCORE 59 Plumbing permit for backflow preventor for irrigation system Client: Condominiu Canyon | Permit type: Plumbing | Permit status: Cmp | Completion date: June 25, 2010 | Current use: Commercial/retail, existing | Permit id: Pmt2007-01354 | |||||
SCORE 95 Wachovia fire alarm ti Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: August 30, 2007 | Current use: Office - professional, existing | Permit id: Pmt2007-01741 | |||||
SCORE 95 Sign permit application for acquire ste 1 for new permanent non-electric suspended soffit sign. Client: Condominiu Canyon | Permit type: Sign | Permit status: Cmp | Completion date: March 14, 2008 | Current use: Office - professional, existing | Permit id: Pmt2007-01975 | |||||
SCORE 95 First western bank fire alarm tenant finish Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: August 28, 2007 | Current use: Office - professional, existing | Permit id: Pmt2007-02571 | |||||
SCORE 95 Set dumpster on west side of 11th street in on-street parking spaces. 12 27 2007 to 2 28 2008 Date: August 16, 2007 Contractor: Wyatt Construction Co, Inc Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-03536 | |||||
SCORE 95 Set boom truck in parking on 11th to lift material into building. Intermittanly for 2 months Date: September 6, 2007 Contractor: Wyatt Construction Co, Inc Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2007-03877 | |||||
SCORE 95 New wall sign first western trust bank Client: Condominiu Canyon | Permit type: Sign | Permit status: N&v | Current use: Financial institution, existing | Permit id: Pmt2007-04626 | |||||
Erect 2 tents, 1 x 30, and 1 x 10, both open sided, for temporary wine food festival in the trios parking lot to be held 8 31 02 Date: August 29, 2002 Value: $100 Client: Limited | Permit type: Temporary event | Permit status: N&v | Current use: Restaurant, existing | Permit id: Pmt2002-03807 | |||||
Flood development permit: the existing building will be demolished and replaced with a new 4 story mixed use building with underground parking. The proposed building will be floodproofed. Revised on 7 19 07 to include planter pots in the flood fringe. Date: March 12, 2006 Client: Limited | Permit type: Flood floodproof structure | Permit status: Cmp | Completion date: March 19, 2008 | Permit id: Pmt2006-00172 | |||||
SCORE 95 Traffic control on wednesday 1 25 06 from 9am to 12 noon only. Date: January 24, 2006 Contractor: Wyatt Construction Co, Inc Client: Limited | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-00268 | |||||
Remove padmount transformer and re-feed primary conductor back to switch cabinet. (1 23 06-2 1 06) Date: January 30, 2006 Client: Limited | Permit type: Right-of-way, flood fence flood permit | Permit status: Iss | Permit id: Pmt2006-00293 | |||||
Cut off existing 10" mw gas main in 11th street. Tie new 2" fb ip gas main into existing 2" fb on west side of 11th. Traffic control 3 27 06-4 27 06. Job no 10774367 Date: March 21, 2006 Client: Limited | Permit type: Right-of-way, flood fence flood permit | Permit status: Iss | Permit id: Pmt2006-00859 | |||||
SCORE 95 Install temporary sidewalk. Pedestrian control 3 23 06-3 27 06. Date: March 23, 2006 Contractor: Wyatt Construction Co, Inc Client: Limited | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-01008 | |||||
SCORE 95 Pedestrian control for shoring work. Close 11th sidewalk from canyon to alley. Close canyon sidewalk from broadway to 11th. April 2006-march 2007 Date: March 28, 2006 Contractor: Wyatt Construction Co, Inc Client: Limited | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-01045 | |||||
Removal of 1 street light pole and opening of street light feed on the corner of canyon and 11th. Date: April 6, 2006 Client: Limited | Permit type: Right-of-way, flood fence flood permit | Permit status: Iss | Permit id: Pmt2006-01047 | |||||
Remove primary in conduit and re-install new primary conductor from sw cab in alley to manhole on east side of broadway. Job no 10647393. Date: April 21, 2006 Client: Limited | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-01386 | |||||
SCORE 95 Backfill & crane work traffic control 9-12-06 to 10-30-06 Date: September 11, 2006 Contractor: Wyatt Construction Co, Inc Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-03771 | |||||
SCORE 95 Changes to 4th level removing 2 dwellings and expantion of east side for core and shell future office space. Changes add 3,167 sf to existing 92,308 sf building. Due to call-up schedule permit cannot be issued until 10 7 06 or after. Check with brent bean or brian holmes to see if called up Client: Condominiu Canyon | Permit type: Building | Permit status: N&v | Current use: Office - professional, addition, multifa | Permit id: Pmt2006-03792 | |||||
SCORE 95 New 6" fire line, water main extension, fire hydrant and water services & sewer manhole. Sales tax on this permit. Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-04339 | |||||
Erect 2 tents, 1 30foot x 30foot, and 1 10foot x 10foot, both open sided, for temporary wine food festival in the triofoots parking lot to be held 8 foot31 02 Date: August 29, 2002 Value: $100 Client: Limited | Permit type: Temporary event | Permit status: N&v | Current use: Restaurant, existing | Permit id: Pmt2002-03807 | |||||
1 1 2inch water tap - city of boulder project; barb kenyon, project manager Date: August 13, 2003 Client: Limited | Permit type: Water | Permit status: Act | Permit id: Pmt2003-03417 | |||||
Floodplain development permit for redevelopment of the existing triofoots site. The scope includes demolition of the existing building and construction of a new four-story mixed use building with a 28,5 s. F. Footprint. Client: Limited | Permit type: Flood floodproof structure | Permit status: Wdn | Current use: Commercial/retail, new | Permit id: Pmt2004-02189 | |||||
Cut off 1 1 4inch gas service at main due to demo of building. Date: December 19, 2005 Client: Limited | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2005-04843 | |||||
SCORE 95 Foundation package for mixed used building. See lur2005-00033. Client: Limited | Permit type: Building, electrical, mechanical, plumbing, sitework | Permit status: N&v | Current use: Parking garage, new | Permit id: Pmt2006-00272 | |||||
Cut off existing 10inch mw gas main in 11th street. Tie new 2inch fb ip gas main into existing 2inch fb on west side of 11th. Traffic control 3 27 06-4 27 06. Job no 10774367 Date: March 21, 2006 Client: Limited | Permit type: Right-of-way, flood fence flood permit | Permit status: Iss | Permit id: Pmt2006-00859 | |||||
SCORE 95 18 residential units and core and shell commercial, two units on the fourth floor are unfinished a separate permit will be applied for later to finish these units. Four stories. 48862 sf residential and 43,443 sf commercial. See lur2005-00033. Client: Limited | Permit type: Building, electrical, mechanical, plumbing, water, wastewater, sitework | Permit status: Co | Current use: Commercial/retail, core and shell, multi | Permit id: Pmt2006-01626 | |||||
SCORE 95 Electrical permit for temporary construction power. Client: Limited | Permit type: Electrical | Permit status: N&v | Current use: Commercial/retail, existing | Permit id: Pmt2006-01654 | |||||
SCORE 95 Erection of a tower crane at inchtriofootsinch site. Contractor: Wyatt Construction Company Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: N&v | Current use: Commercial/retail, existing | Permit id: Pmt2006-02070 | |||||
SCORE 95 Fire alarm system - core and shell Client: Condominiu Canyon | Permit type: Fire | Permit status: N&v | Current use: Commercial/retail, existing | Permit id: Pmt2006-03980 | |||||
SCORE 95 New 6inch fire line, water main extension, fire hydrant and water services & sewer manhole. Sales tax on this permit. Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-04339 | |||||
SCORE 95 Fire sprinkler system - core and shell with finish residential on the 2nd and 3rd floor only. Client: Condominiu Canyon | Permit type: Fire | Permit status: Cls | Current use: Commercial/retail, existing | Permit id: Pmt2006-04517 | |||||
SCORE 95 Tenant finish for first national bank. 19,584 sf. Two floors Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Financial institution, tenant finish | Permit id: Pmt2006-04651 | |||||
SCORE 70 Finish of core and shell space as residential unit #406. Proposed 5,2 s. F. Unit to have 2 bedrooms and 4 baths. Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Multifamily dwellings, remodel | Permit id: Pmt2006-04752 | |||||
SCORE 95 Sign permit for new internally illuminated wall signs - first national bank of colorado and atm Client: Condominiu Canyon | Permit type: Electrical, sign | Permit status: Cmp | Completion date: December 17, 2007 | Current use: Financial institution, existing | Permit id: Pmt2006-04878 | |||||
SCORE 70 Residential tenant finish for unit #404. 4297 sf unit with three bedrooms, 4 bathrooms. Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Multifamily dwellings, remodel | Permit id: Pmt2006-04986 | |||||
SCORE 95 Installation of a 4 stop, # 60 temporary equipment material & man lift on exterior of building. Anticipated removal date aug sept 2007. Client: Condominiu Canyon | Permit type: Elevator | Permit status: Cmp | Completion date: March 16, 2007 | Current use: Commercial/retail, existing | Permit id: Pmt2007-00202 | |||||
SCORE 95 Elevator new 5 stop elevator hydraulic. Passenger Client: Condominiu Canyon | Permit type: Elevator | Permit status: Cmp | Completion date: April 25, 2007 | Current use: Commercial/retail, existing, multifamily | Permit id: Pmt2007-00237 | |||||
SCORE 95 Fire sprinkler system - first national bank Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: January 2, 2008 | Current use: Office - professional, existing | Permit id: Pmt2007-00283 | |||||
Tenant finish of fourth floor office space, 105 sf for accounting office. Date: March 1, 2007 Value: $222,810 Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Office - professional, tenant finish | Permit id: Pmt2007-00419 | |||||
SCORE 98 Interior tenant finish, 26 sf, to include the addition of one hand sink, one kitchen sink and a dishwasher. Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Office - administrative, tenant finish | Permit id: Pmt2007-00574 | |||||
SCORE 95 Tenant finish for 6264 sf office space for amg national trust bank, suite 310 Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: March 24, 2008 | Current use: Financial institution, tenant finish | Permit id: Pmt2007-00598 | |||||
SCORE 95 1155 canyon fourth floor east side tennant finish sprinkler system Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: December 29, 2007 | Current use: Office - professional, existing | Permit id: Pmt2007-00680 | |||||
SCORE 100 Electrical permit for tilt-up solar pv system on rooftop. 34. 4 kw system. Client: Condominiu Canyon | Permit type: Photovoltaic | Permit status: Cmp | Completion date: July 27, 2007 | Current use: Commercial/retail, existing | Permit id: Pmt2007-00760 | |||||
SCORE 95 Tenant finish for elevator lobby on second floor. (526 sf) no plumbing Client: Condominiu Canyon | Permit type: Building, electrical, mechanical | Permit status: N&v | Current use: Office - professional, tenant finish | Permit id: Pmt2007-00967 | |||||
SCORE 95 1155 canyon fire alarm 1st national bank Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: April 13, 2011 | Current use: Office - professional, existing | Permit id: Pmt2007-01054 | |||||
SCORE 95 Fire alarm 1155 canyon ekh&s tennant finish Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: June 7, 2007 | Current use: Office - professional, existing | Permit id: Pmt2007-01067 | |||||
SCORE 95 Tenant finish of 6224 sf on 2nd floor, professional business offices for inchwachovia securitiesinch Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Co | Current use: Office - professional, tenant finish | Permit id: Pmt2007-01151 | |||||
SCORE 95 1155 canyon amg national trust bank tennant finish sprinkler plans Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: April 8, 2011 | Current use: Office - professional, existing | Permit id: Pmt2007-01226 | |||||
SCORE 95 Tennant finish for 1155 canyon acquire first floor south west side. Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: May 20, 2008 | Current use: Office - professional, existing | Permit id: Pmt2007-01403 | |||||
SCORE 95 Tennant finish for office space, suite 302, first western trust bank. Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Co | Current use: Financial institution, tenant finish | Permit id: Pmt2007-01423 | |||||
SCORE 71 Acquire tennant finish fire alarm Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: May 20, 2008 | Current use: Office - professional, existing | Permit id: Pmt2007-01668 | |||||
SCORE 95 Suite 406 pepperzak loft Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: April 8, 2011 | Current use: Single family attached dwelling, existin | Permit id: Pmt2007-02127 | |||||
SCORE 95 Units 307 and 209 will be remodelled and combined into a new unit 516, unit 207 will also be remodelled. Client: Condominiu Canyon | Permit type: Building, electrical, mechanical, plumbing | Permit status: Co | Current use: Multifamily dwellings, remodel | Permit id: Pmt2007-02142 | |||||
SCORE 95 Tennant finish suite 404 polk residence Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: February 8, 2008 | Current use: Single family attached dwelling, existin | Permit id: Pmt2007-02146 | |||||
SCORE 95 Tennant finish first western trust bank 3rd floor east side Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: April 8, 2011 | Current use: Financial institution, existing | Permit id: Pmt2007-02150 | |||||
SCORE 95 Sign permit for 3 signs for new permanent internally illuminated wall signs see (pmt2007-02282) Client: Condominiu Canyon | Permit type: Sign | Permit status: Cmp | Completion date: October 1, 2007 | Current use: Office - professional, existing | Permit id: Pmt2007-02281 | |||||
SCORE 95 Sign permit for new elecric awning sign see (pmt2007-02281) Client: Condominiu Canyon | Permit type: Sign | Permit status: Cmp | Completion date: October 1, 2007 | Current use: Office - professional, existing | Permit id: Pmt2007-02282 | |||||
SCORE 95 Close west bound lane of canyon for 2 days. Move in Contractor: Wyatt Construction Company Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: N&v | Permit id: Pmt2007-02310 | |||||
SCORE 95 Sign permit for 2 non-electric wall signs inchwacovia securitiesinch Client: Condominiu Canyon | Permit type: Sign | Permit status: N&v | Current use: Financial institution, existing | Permit id: Pmt2007-02468 | |||||
SCORE 95 Office remodel to existing space. Second floor. 3 sf Client: Condominiu Canyon | Permit type: Building, electrical | Permit status: N&v | Current use: Financial institution, tenant remodel | Permit id: Pmt2007-02526 | |||||
SCORE 95 Wachovia tenant finish Client: Condominiu Canyon | Permit type: Fire | Permit status: Cmp | Completion date: October 3, 2007 | Current use: Office - professional, existing | Permit id: Pmt2007-02692 | |||||
SCORE 95 Install temporary scaffold stair 5foot from building face with overhead walkway. August 15-november 1. Contractor: Wyatt Construction Company Client: Condominiu Canyon | Permit type: Right-of-way | Permit status: N&v | Permit id: Pmt2007-03443 | |||||
SCORE 95 Installation of non-illuminated wall sign inchamg national trust bankinch on south elevation of building. Client: Condominiu Canyon | Permit type: Sign | Permit status: Cmp | Completion date: March 14, 2008 | Current use: Financial institution, existing | Permit id: Pmt2007-03523 | |||||
SCORE 95 Electrical and building permit for tilt-up solar pv system on existing rooftop. 10. 32 kw system. Client: Condominiu Canyon | Permit type: Building, photovoltaic | Permit status: Cmp | Completion date: February 22, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2007-03543 | |||||
SCORE 95 Sign permit for non-electric wall sign inchbaqnk drive-up & atm, parkinginch Client: Condominiu Canyon | Permit type: Sign | Permit status: Cmp | Completion date: March 14, 2008 | Current use: Financial institution, existing | Permit id: Pmt2007-03802 | |||||
SCORE 95 Replace water heater and forced air furnace. Date: October 12, 2001 Contractor: Precision Plumbing And Heating Client: William Love,John Studeholme | Applicant: Precision Plumbing & Heating | Permit type: Mechanical | Permit status: N&v | Current use: Office - profes | |||||
SCORE 95 Replace water heater and forced air furnace. Client: William Love | Permit type: Mechanical | Permit status: N&v | Current use: Office - professional, existing | Permit id: Pmt2001-04522 | |||||
SCORE 98 Set crane in walnut tuesday, 9 7 from 7am - noon Date: September 3, 2004 Contractor: Sterling Crane Llc Client: Julien St | Applicant: Sterling Crane Llc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Remove temporary 500kv underground transformer. Park truck trailer on north bound lane of 9th street, between walnut and canyon. Date: August 31, 2004 Contractor: Xcel Energy Client: Julien St | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 98 Crane set in walnut from 7-3: 8 9 04-8 11 04 Date: August 6, 2004 Contractor: Sterling Crane Llc Client: Julien St | Applicant: Sterling Crane Llc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 73 R r sidewalk, curb and gutter Date: June 8, 2004 Contractor: G E Johnson Construction Inc Client: Julien St | Applicant: G E Johnson Construction, Inc. | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Run new service line for st julien hotel Date: May 26, 2004 Contractor: Qwest Comm Centurylink Client: Julien St | Applicant: Qwest Comm/centurylink | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 99 Install 2" pressure pipe in canyon, alley and 11th Date: May 21, 2004 Contractor: Northern Pipeline Construction Client: Julien St | Applicant: Northern Pipeline Construction | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 99 Electric work around st. Julien hotel Date: May 21, 2004 Contractor: Northern Pipeline Construction Client: Julien St | Applicant: Northern Pipeline Construction | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Fire sprinkler system - hotel Date: May 3, 2004 Contractor: Frontier Fire Protection Inc Client: Julien St | Applicant: Frontier Fire Protection Inc | Permit type: Fire | Permit status: Cmp | Completion date: January 25, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 98 Fire alarm system - hotel Date: April 16, 2004 Contractor: Riviera Electric Llc Client: Julien St | Applicant: Riviera Electric, Llc | Permit type: Fire | Permit status: Cmp | Completion date: January 25, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 100 Intalling new transformer for st julien electric supply. Date: March 17, 2004 Contractor: Xcel Energy Client: Julien St | Applicant: Xcel Energy | Permit type: Right-of-way, flood | Permit status: Iss | |||||
SCORE 95 Fire suppression system - st. Julien Date: March 9, 2004 Contractor: Cintas Corporation Dba Client: Julien St | Applicant: Cintas Corporation Dba | Permit type: Fire | Permit status: Cmp | Completion date: January 27, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 85 Storm line, storm manhole, sewer line and sewer tap on ne corner of building Date: March 3, 2004 Contractor: Belair Excavating Client: Julien St | Applicant: Belair Excavating | Permit type: Wastewater, right-of | Permit status: Iss | Current use: Motel/hotel/bed | |||||
SCORE 95 Fire sprinkler system - garage systems Date: February 12, 2004 Contractor: Frontier Fire Protection Inc Client: Julien St | Applicant: Frontier Fire Protection Inc | Permit type: Fire | Permit status: Cmp | Completion date: September 17, 2004 | Current use: Parking garage, | |||||
SCORE 98 Fire alarm system - parking garage Date: February 13, 2004 Contractor: Riviera Electric Llc Client: Julien St | Applicant: Riviera Electric, Llc | Permit type: Fire | Permit status: Cmp | Completion date: September 17, 2004 | Current use: Parking garage, | |||||
SCORE 95 New 3,5 puond capacity, 125 f. P. M., 3 stop hydraulic passenger elevator. Date: February 24, 2004 Contractor: Otis Elevator Company Client: Julien St | Applicant: Otis Elevator Company | Permit type: Elevator | Permit status: Cmp | Completion date: January 10, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 95 New 3,5 pound capacity, 125 f. P. M., 3 stop hydraulic passenger elevator. Date: February 24, 2004 Contractor: Otis Elevator Company Client: Julien St | Applicant: Otis Elevator Company | Permit type: Elevator | Permit status: Cmp | Completion date: January 11, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 95 New 3,5 pound capacity, 125 f. P. M., two stop hydraulic passenger elevator. Date: February 24, 2004 Contractor: Otis Elevator Company Client: Julien St | Applicant: Otis Elevator Company | Permit type: Elevator | Permit status: Cmp | Completion date: January 10, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 73 Case to track row inspector overtime hours. See case notes. Saturday, 8. 2. 03 - 2hrs. Tower cranes - 9th street closure sunday, 8. 3. 03 - 2hrs. Tower cranes - 9th street closure thursday, 10. 16. 03 - 2hrs. Initial traffic control set up on canyon (5am start) saturday, 10. 18. 03 - 2hrs. 9th street closure for concrete pumper truck deliveries saturday, 11. 8. 03 - 2hrs. Canyon ave. Traffic control set up (11. 10. 03 on time sheet due to already turned in time sheet) for concrete pumper truck deliveries tuesday, 11. 11. 03 - 2hrs. Cob holiday - veterans day. Canyon ave. Traffic control set up for concrete pumper truck deliveries. Saturday, 1 31 04 2hrs. Canyon closure for concrete pumper truck deliveries. Saturday, 2 7 04 2hrs. Canyon closure for concrete pumper truck deliveries. Monday, 2 16 04 2hrs. Canyon closure on presidents day holiday. Saturday, 2 21 04 2hrs. Canyon closure saturday, 6 25 04 2hrs. For concrete sidewalk pour Date: February 2, 2004 Contractor: G E Johnson Construction Inc Client: Julien St | Applicant: G E Johnson Construction, Inc. | Permit type: Right-of-way | Permit status: Act | |||||
SCORE 95 Install two 3,5 # capacity, 3 fpm, cable passenger elevators, and one 4,5 # capacity, 3 fpm, cable freight elevator. Date: February 24, 2004 Contractor: Otis Elevator Company Client: Julien St | Applicant: Otis Elevator Company | Permit type: Elevator | Permit status: Cmp | Completion date: January 11, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 85 2 sewer services off canyon Date: August 22, 2003 Contractor: Belair Excavating Client: Julien St | Applicant: Belair Excavating | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 85 Fire hydrant run on walnut (reference pmt2003-02175 for fees) Date: August 4, 2003 Contractor: Belair Excavating Client: Julien St | Applicant: Belair Excavating | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 86 Replace damaged cable and set vault at 9th and walnut. Date: August 20, 2003 Contractor: Utilx Corporation Client: Julien St | Applicant: Utilx Corporation | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 88 Crane Date: August 1, 2003 Contractor: Julien St Client: Julien St | Applicant: Julien St | Permit type: Right-of-way, flood | Permit status: Iss | |||||
SCORE 85 Water, sewer, irrigation & fire line installations for st. Julien hotel. Date: June 20, 2003 Contractor: Belair Excavating Client: Julien St | Applicant: Belair Excavating | Permit type: Right-of-way, flood | Permit status: Iss | |||||
SCORE 98 Temporary construction power for st. Jullien hotel construction project. Date: May 30, 2003 Contractor: Riviera Electric Llc Client: Julien St | Applicant: Riviera Electric, Llc | Permit type: Electrical | Permit status: Cmp | Completion date: February 18, 2005 | Current use: Motel/hotel/bed | |||||
SCORE 88 Shoring to allow the construction of foundation, a revocable permit has been issued for the tye backs. All fees will be paid on the building permit for the new parking structure and hotel. Date: May 8, 2003 Contractor: G E Johnson Const Company Inc Client: Julien St | Applicant: G E Johnson Const Company Inc | Permit type: Fence | Permit status: Cmp | Completion date: August 7, 2007 | Current use: Government uses | |||||
SCORE 73 Construction fence and well points for dewatering - also includes tiebacks for foundation construction (see revocable adr2002-90045) Date: December 19, 2002 Contractor: G E Johnson Construction Inc Client: Julien St | Applicant: G E Johnson Construction, Inc. | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 88 6" fireline tap to serve st. Julien hotel - fees for this permit were assessed to pmt2002-02091 Date: September 3, 2002 Contractor: Julien St Client: Julien St | Applicant: Julien St | Permit type: Water | Permit status: Act | |||||
SCORE 88 2" water tap & 4" sewer tap to serve future building (st. Julien hotel site) - fees for this permit were assessed to pmt2002-02091 Date: September 3, 2002 Contractor: Julien St Client: Julien St | Applicant: Julien St | Permit status: Act | |||||
SCORE 88 6" fire hydrant run to serve st. Julien hotel site - fees for this permit were assessed to pmt2002-02091 Date: September 3, 2002 Contractor: Julien St Client: Julien St | Applicant: Julien St | Permit type: Water | Permit status: Act | |||||
SCORE 56 Standard floodplain development permit for the garage and hotel. Date: June 25, 2002 Contractor: St Julien Partners Client: St Julien Partners | Applicant: St Julien Partners | Permit type: Flood standard permi | Permit status: Iss | Current use: Motel/hotel/bed | |||||
Intalling new transformer for st julien electric supply. Date: March 17, 2004 Client: Julien St | Permit type: Right-of-way, flood fence flood permit | Permit status: Iss | Permit id: Pmt2004-00927 | |||||
Run new service line for st julien hotel Date: May 26, 2004 Client: Julien St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2004-01986 | |||||
SCORE 71 R r sidewalk, curb and gutter Date: June 8, 2004 Contractor: G E Johnson Construction, Inc Client: Julien St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2004-02132 | |||||
Remove temporary 500kv underground transformer. Park truck trailer on north bound lane of 9th street, between walnut and canyon. Date: August 31, 2004 Client: Julien St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2004-03432 | |||||
Crane Date: August 1, 2003 Client: Julien St | Permit type: Right-of-way, flood not required | Permit status: Iss | Permit id: Pmt2003-02481 | |||||
Standard floodplain development permit for the garage and hotel. Date: June 25, 2002 Client: St Julien Partners | Permit type: Flood standard permit | Permit status: Iss | Current use: Motel/hotel/bed & breakfast, existing | Permit id: Pmt2002-02266 | |||||
2" water tap & 4" sewer tap to serve future building (st. Julien hotel site) - fees for this permit were assessed to pmt2002-02091 Client: Julien St | Permit status: Act | Permit id: Pmt2002-03877 | |||||
6" fire hydrant run to serve st. Julien hotel site - fees for this permit were assessed to pmt2002-02091 Client: Julien St | Permit type: Water | Permit status: Act | Permit id: Pmt2002-03878 | |||||
6" fireline tap to serve st. Julien hotel - fees for this permit were assessed to pmt2002-02091 Client: Julien St | Permit type: Water | Permit status: Act | Permit id: Pmt2002-03879 | |||||
SCORE 71 Construction fence and well points for dewatering - also includes tiebacks for foundation construction (see revocable adr2002-90045) Date: December 19, 2002 Contractor: G E Johnson Construction, Inc Client: Julien St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2002-05321 | |||||
2inch water tap & 4inch sewer tap to serve future building (st. Julien hotel site) - fees for this permit were assessed to pmt2002-02091 Client: Julien St | Permit type: Water | Permit status: Act | Permit id: Pmt2002-03877 | |||||
6inch fire hydrant run to serve st. Julien hotel site - fees for this permit were assessed to pmt2002-02091 Client: Julien St | Permit type: Water | Permit status: Act | Permit id: Pmt2002-03878 | |||||
6inch fireline tap to serve st. Julien hotel - fees for this permit were assessed to pmt2002-02091 Client: Julien St | Permit type: Water | Permit status: Act | Permit id: Pmt2002-03879 | |||||
SCORE 96 Temporary construction power for st. Jullien hotel construction project. Client: Julien St | Permit type: Electrical | Permit status: Cmp | Completion date: February 18, 2005 | Current use: Motel/hotel/bed & breakfast, existing | Permit id: Pmt2003-02110 | |||||
SCORE 91 Water, sewer, irrigation & fire line installations for st. Julien hotel. Date: June 20, 2003 Contractor: Belair Sitework Services Client: Julien St | Permit type: Right-of-way, flood not required | Permit status: Iss | Permit id: Pmt2003-02175 | |||||
SCORE 91 Fire hydrant run on walnut (reference pmt2003-02175 for fees) Date: August 4, 2003 Contractor: Belair Sitework Services Client: Julien St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2003-03215 | |||||
SCORE 91 2 sewer services off canyon Date: August 22, 2003 Contractor: Belair Sitework Services Client: Julien St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2003-03521 | |||||
SCORE 71 Case to track row inspector overtime hours. See case notes. Saturday, 8. 2. 03 - 2hrs. Tower cranes - 9th street closure sunday, 8. 3. 03 - 2hrs. Tower cranes - 9th street closure thursday, 10. 16. 03 - 2hrs. Initial traffic control set up on canyon (5am start) saturday, 10. 18. 03 - 2hrs. 9th street closure for concrete pumper truck deliveries saturday, 11. 8. 03 - 2hrs. Canyon ave. Traffic control set up (11. 10. 03 on time sheet due to already turned in time sheet) for concrete pumper truck deliveries tuesday, 11. 11. 03 - 2hrs. Cob holiday - veteransfoot day. Canyon ave. Traffic control set up for concrete pumper truck deliveries. Saturday, 1 31 04 2hrs. Canyon closure for concrete pumper truck deliveries. Saturday, 2 7 04 2hrs. Canyon closure for concrete pumper truck deliveries. Monday, 2 16 04 2hrs. Canyon closure on presidentfoots day holiday. Saturday, 2 21 04 2hrs. Canyon closure saturday, 6 25 04 2hrs. For concrete sidewalk pour Contractor: G E Johnson Construction, Inc Client: Julien St | Permit type: Right-of-way | Permit status: Act | Permit id: Pmt2004-00385 | |||||
SCORE 95 New 3,5 pound capacity, 125 f. P. M., two stop hydraulic passenger elevator. Client: Julien St | Permit type: Elevator | Permit status: Cmp | Completion date: January 10, 2005 | Current use: Motel/hotel/bed & breakfast, existing | Permit id: Pmt2004-00452 | |||||
SCORE 95 New 3,5 puond capacity, 125 f. P. M., 3 stop hydraulic passenger elevator. Client: Julien St | Permit type: Elevator | Permit status: Cmp | Completion date: January 10, 2005 | Current use: Motel/hotel/bed & breakfast, existing, g | Permit id: Pmt2004-00453 | |||||
SCORE 95 New 3,5 pound capacity, 125 f. P. M., 3 stop hydraulic passenger elevator. Client: Julien St | Permit type: Elevator | Permit status: Cmp | Completion date: January 11, 2005 | Current use: Motel/hotel/bed & breakfast, existing, g | Permit id: Pmt2004-00454 | |||||
SCORE 96 Fire alarm system - parking garage Client: Julien St | Permit type: Fire | Permit status: Cmp | Completion date: September 17, 2004 | Current use: Parking garage, existing | Permit id: Pmt2004-00477 | |||||
SCORE 95 Fire sprinkler system - garage systems Client: Julien St | Permit type: Fire | Permit status: Cmp | Completion date: September 17, 2004 | Current use: Parking garage, existing | Permit id: Pmt2004-00481 | |||||
SCORE 95 Install two 3,5 # capacity, 3 fpm, four stop cable passenger elevators, and one 4,5 # capacity, 3 fpm,four stop cable freight elevator. Client: Julien St | Permit type: Elevator | Permit status: Cmp | Completion date: January 11, 2005 | Current use: Motel/hotel/bed & breakfast, existing, g | Permit id: Pmt2004-00563 | |||||
SCORE 91 Storm line, storm manhole, sewer line and sewer tap on ne corner of building Date: March 3, 2004 Contractor: Belair Sitework Services Client: Julien St | Permit type: Wastewater, right-of-way | Permit status: Iss | Current use: Motel/hotel/bed & breakfast, new | Permit id: Pmt2004-00722 | |||||
SCORE 95 Fire suppression system - st. Julien Client: Julien St | Permit type: Fire | Permit status: Cmp | Completion date: January 27, 2005 | Current use: Motel/hotel/bed & breakfast, existing | Permit id: Pmt2004-00803 | |||||
SCORE 96 Fire alarm system - hotel Client: Julien St | Permit type: Fire | Permit status: Cmp | Completion date: January 25, 2005 | Current use: Motel/hotel/bed & breakfast, existing | Permit id: Pmt2004-01344 | |||||
SCORE 95 Fire sprinkler system - hotel Client: Julien St | Permit type: Fire | Permit status: Cmp | Completion date: January 25, 2005 | Current use: Motel/hotel/bed & breakfast, existing | Permit id: Pmt2004-01577 | |||||
SCORE 99 Install 2inch pressure pipe in canyon, alley and 11th Date: May 21, 2004 Contractor: Northern Pipeline Construction Client: Julien St | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2004-01764 |