Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Addition fire alarm cervices onto existing system for expansion of homeless shelter to 1st floor Date: April 13, 2015 Contractor: John Mclaughlin Client: City Of Boston | Permit type: Bfd fire alarm installations | Permit id: Bfdf460718 | Parcel: 0801027012 | |||||
SCORE 82 Install new sprinkler system for phase 2b due to architectural modifications. Rough in new system with temporary uprights which will result in a 1 day shutdown and tie-in to new service. Removal of existing piping will occur after new system is complete and online. Date: April 13, 2015 Contractor: Fp Permit J.C. Cannistraro Llc Client: City Of Boston | Permit type: Bfd sprinkler system | Permit id: Sprk457916 | Parcel: 0801027012 | |||||
SCORE 82 Install new sprinklers in select rooms for phase 2a due to architectural modifications Date: April 13, 2015 Contractor: Fp Permit J.C. Cannistraro Llc Client: City Of Boston | Permit type: Bfd sprinkler system | Permit id: Sprk457914 | Parcel: 0801027012 | |||||
Install electrical conduit; 147 x 2 rdwy; ; riley bros Date: April 7, 2015 Client: City Of Boston | Permit type: Excavation permit | Expiration date: April 19, 2015 | Permit id: Exca-459737 | Parcel: 0801027012 | |||||
To conduct the following: temporary heat for tent/structure in the rear parking lot of homeless shelter temporary heat for tent to support a dining hall Date: November 16, 2015 Client: City Of Boston | Permit type: Bfd general permit | Permit id: Gp532984 | Parcel: 0801027012 | |||||
Cutting / burning / welding for installation of new reinforcing for rooftop units and steel erection for new addition to accommodate building renovation bfd paid detail required Date: November 16, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw539032 | Parcel: 0801027012 | |||||
Erect a x membrane structure Date: November 16, 2015 Value: $80,000 Client: City Of Boston | Permit type: Short form bldg permit | Expiration date: May 16, 2016 | Current use: Other | Permit id: Sf539708 | Parcel: 0801027012 | |||||
SCORE 82 New sprinkler system for phase 3 due to arch changes. Install new system with temp uprights which results in a 1 day shutdown and tie in to new service. Existing system will then be removed. Phase 3 is isolated from the remainder of the building and shutdowns will only affect the construction area. Date: November 20, 2015 Contractor: Fp Permit J.C. Cannistraro Llc Client: City Of Boston | Permit type: Bfd sprinkler system | Permit id: Sprk536762 | Parcel: 0801027012 | |||||
Cutting/burning/welding for removal of existing hvac piping &; installing new system ;dpl 2/15/16 bfd paid detail required Date: December 9, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw543936 | Parcel: 0801027012 | |||||
SCORE 100 Phase 3 additional fire alarm devices on to existing system for expansion of fire alarm Date: January 20, 2016 Contractor: John Mclaughlin Client: City Of Boston | Permit type: Bfd fire alarm installations | Permit id: Bfdf554158 | Parcel: 0801027012 | |||||
Cutting / burning / welding for installation of gas piping to serve new hvac and plumbing equipment to accommodate building renovation (dpl) bfd paid detail required Date: April 1, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw458224 | Parcel: 0801027012 | |||||
Cutting burning &; welding for the installation of seismic clips &; unit supports (dpl) bfd paid detail required Date: April 24, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw465013 | Parcel: 0801027012 | |||||
Cutting burning &; welding of steel piping &; support (dpl) bfd paid detail required;at all times; Date: June 10, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw482461 | Parcel: 0801027012 | |||||
To conduct the following: storage of extra fuel 1 gallons of diesel fuel Date: October 14, 2015 Client: City Of Boston | Permit type: Bfd general permit | Permit id: Gp528999 | Parcel: 0801027012 | |||||
Cutting/welding/burning;for installation of structural foundation for support to new addition dpl11/13/15 bfd paid detail required Date: October 16, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw529006 | Parcel: 0801027012 | |||||
To conduct the following: temporary heat for tent structure in the rear parking lot of homeless shelter temporary heat for tent to support a dining hall Date: November 16, 2015 Client: City Of Boston | Permit type: Bfd general permit | Permit id: Gp532984 | Parcel: 0801027012 | |||||
Cutting burning welding for removal of existing hvac piping &; installing new system ;dpl 2 15 16 bfd paid detail required Date: December 9, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw543936 | Parcel: 0801027012 | |||||
Cutting burning welding for installation of gas piping to serve new hvac and plumbing equipment to accommodate building renovation (dpl) bfd paid detail required Date: April 1, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw458224 | Parcel: 0801027012 | |||||
Cutting welding burning;for installation of structural foundation for support to new addition dpl11 13 15 bfd paid detail required Date: October 16, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw529006 | Parcel: 0801027012 | |||||
Repair damaged conduit; x 2 street &; sdwk; depth 2; 7am-7pm; weekends only; boston police detail area b; 343-4287; (1) Date: May 3, 2016 Client: City Of Boston | Permit type: Excavation permit | Expiration date: June 7, 2016 | Permit id: Exca-586488 | Parcel: 0801027012 | |||||
Bfd chemist certificate proces Date: March 31, 2016 Client: City Of Boston | Permit id: Chm574478 | Parcel: 0801027012 | |||||
Cutting burning welding for installation of new reinforcing for rooftop units and steel erection for new addition to accommodate building renovation bfd paid detail required Date: November 16, 2015 Client: City Of Boston | Permit type: Bfd cutting-burning-welding | Permit id: Cbw539032 | Parcel: 0801027012 | |||||
Sewer relay; x 5 rdwy; ;umbro; 7pm-6am; boston police detail area b; 343-4287; (1); extension Date: March 25, 2016 Client: City Of Boston | Permit type: Excavation permit | Expiration date: July 20, 2016 | Permit id: Exca-574449 | Parcel: 0801027012 | |||||
SCORE 99 Installation of temporary structure/tent in the rear parking lot at the homeless shelter tents----fire extinguishers are required in each tent permitted on site.; permit is for fire apparatus access; flame certification is for the tent material only; occupant load approval is required from the inspectional services department. ; Date: November 17, 2015 Contractor: Brian Melia Client: City Of Boston | Permit type: Bfd tent with assembly | Permit id: Ta532842 | Parcel: 0801027012 | |||||
SCORE 99 Installation of temporary structure tent in the rear parking lot at the homeless shelter tents----fire extinguishers are required in each tent permitted on site.; permit is for fire apparatus access; flame certification is for the tent material only; occupant load approval is required from the inspectional services department. ; Date: July 7, 2017 Contractor: Brian Melia Client: City Of Boston | Permit type: Bfd tent with assembly | Permit id: Ta728394 | Parcel: 0801027012 |