Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 56 22 Hadley St Cambridge, Ma There are several sagging first floor joists. We propose to add 2 sections of steel beam support. One approximately 5 in length and the other approximately 7 in length. Each section to be supported by 2 3 1 2" lally columns on new 2x2x12" concrete footings. See attached engineering plan by tripi engineering services, 433 main street, suite 4, hudson ma 01749 Permit type: Addition/alteration | Completion date: April 25, 2016 | Current use: One-family | Permit id: 0 | Parcel: 18128 |