Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 59 2321 4th St Ne, Washington, Dc 20002 After hours permit for the delivery of construction materials from the adjoining suntrust property from 6 to 7 am and from 7 to 9 pm monday thru friday from june 1, thru november 30, 2015. See attached documents. Date: May 6, 2015 Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1500401 | |||||
SCORE 59 2321 4th St Ne, Washington, Dc 20002 After-hours permit for the pouring of the last concrete slab floor and podium. The delivery of the concrete will be from the adjoining sun trust property from 3: am to 5: am. The first concrete pours will occur one day from july 14th to 17th, and the second pour will be from july 30th to august 3rd. The spread in dates allows for unfavorable weather and/or unforeseen conditions. Date: June 29, 2015 Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1500542 |