Temporary wide gravel construction entrance to be installed in i-295 on-ramp from 11th street, se. Construction access for dc waters clean rivers project - division h - cso 007 shaft site. Access from ramp will be needed from january to april of 2015 during slurry wall construction. Site to be restored upon completion of work. Trail detour permitted separately under dtops #97792. Erosion control approved under dcra permit bciv1400047. Contractor to coordinate work with ddots awi team and 11th street bridge project. Date: November 25, 2014 Value: $544 Client: Carlton Ray Dc Water | Permit type: Paving; driveway beh | Permit id: Pa103139 | |||||
Shallow dewatering system to assist in near surface excavation at cso 007 site of dc waters clean rivers project div h. Thirteen (13) borings in total. Eight (8) primary dewatering wells and three (3) contingency dewatering wells of 8" diameter, and two monitoring wells of 6" diameter. Up to 7 dewatering wells and 1 monitoring well drilled to 25 bgs, with remaining 4 dewatering wells and 1 monitoring well drilled to bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa10172156. Date: May 13, 2015 Value: $100 Client: Carlton Ray Dc Water | Permit type: Excavation; monitori | |||||
Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: May 11, 2015 Value: $100 Client: Carlton Ray Dc Water | Permit type: Excavation; sheeting | Permit id: Pa109849 | |||||
Soil borings for jet grouting at cso 007 site of dc waters clean rivers project div h, which falls in ddot row. Jet grouting needed for ground improvement to facilitate excavation beneath the 54 inch sewer and for mining of the adit connecting the anacostia river tunnel to the cso 007 shaft. Thirty-eight (38) borings of 8" diameter, to max depth of 118 bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa109849. Date: August 3, 2015 Value: $100 Client: Carlton Ray Dc Water | Permit type: Excavation; monitori | Permit id: Pa113783 | |||||
Near surface structures construction for dc waters clean rivers project div h - cso 007 site. Construction of below-grade concrete approach channel, vent chamber, and odor control vault facility, to be installed adjacent to ramp c-3 near intersection with 11th street bridge. No change to existing ddoe-approved site plan or ddot-approved mot measures. Soe permitted separately via tops 109849. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Construction impact assessment report 6b submitted to ddot by dc water under separate cover. Date: August 6, 2015 Value: $2,200 Client: Carlton Ray Dc Water | Permit type: Excavation; vault(s) | Permit id: Pa113982 | |||||
Temporary wide gravel construction entrance to be installed in i-295 on-ramp from 11th street, se. Construction access for dc waters clean rivers project - division h - cso 007 shaft site. Access from ramp will be needed from january to april of 2015 during slurry wall construction. Site to be restored upon completion of work. Trail detour permitted separately under dtops #97792. Erosion control approved under dcra permit bciv1400047. Contractor to coordinate work with ddots awi team and 11th street bridge project. Date: November 25, 2014 Client: Carlton Ray Dc Water | Permit type: Paving; driveway behind sidewalk (porous/pervious only), mega projects; dc water combined sewer proj | Permit status: Permit expired | Expiration date: January 7, 2016 | Permit id: Pa103139 | |||||
Shallow dewatering system to assist in near surface excavation at cso 007 site of dc waters clean rivers project div h. Thirteen (13) borings in total. Eight (8) primary dewatering wells and three (3) contingency dewatering wells of 8" diameter, and two monitoring wells of 6" diameter. Up to 7 dewatering wells and 1 monitoring well drilled to 25 bgs, with remaining 4 dewatering wells and 1 monitoring well drilled to bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa10172156. Date: May 13, 2015 Client: Carlton Ray Dc Water | Permit type: Excavation; monitoring well (each addl), excavation; monitoring well (single), mega projects; dc water combined sewer proj | Permit status: Issued | Expiration date: September 29, 2016 | Permit id: Pa110058 | |||||
Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: May 11, 2015 Client: Carlton Ray Dc Water | Permit type: Excavation; sheeting & shoring (for buildings), mega projects; dc water combined sewer proj | Permit status: Permit expired | Expiration date: June 29, 2016 | Permit id: Pa109849 | |||||
Soil borings for jet grouting at cso 007 site of dc waters clean rivers project div h, which falls in ddot row. Jet grouting needed for ground improvement to facilitate excavation beneath the 54 inch sewer and for mining of the adit connecting the anacostia river tunnel to the cso 007 shaft. Thirty-eight (38) borings of 8" diameter, to max depth of 118 bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa109849. Date: August 3, 2015 Client: Carlton Ray Dc Water | Permit type: Excavation; monitoring well (each addl), excavation; monitoring well (single), mega projects; dc water combined sewer proj | Permit status: Issued | Expiration date: September 13, 2016 | Permit id: Pa113783 | |||||
Near surface structures construction for dc waters clean rivers project div h - cso 007 site. Construction of below-grade concrete approach channel, vent chamber, and odor control vault facility, to be installed adjacent to ramp c-3 near intersection with 11th street bridge. No change to existing ddoe-approved site plan or ddot-approved mot measures. Soe permitted separately via tops 109849. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Construction impact assessment report 6b submitted to ddot by dc water under separate cover. Date: August 6, 2015 Client: Carlton Ray Dc Water | Permit type: Excavation; vault(s) lxw, mega projects; dc water combined sewer proj | Permit status: Issued | Expiration date: November 29, 2016 | Permit id: Pa113982 | |||||
Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: June 10, 2016 Client: Carlton Ray Dc Water | Permit type: Excavation; sheeting & shoring (for buildings), mega projects; dc water combined sewer proj | Permit status: Issued | Expiration date: June 29, 2017 | Permit id: Pa109849-R1 | |||||
SCORE 89 Temporary wide gravel construction entrance to be installed in i-295 on-ramp from 11th street, se. Construction access for dc waters clean rivers project - division h - cso 007 shaft site. Access from ramp will be needed from january to april of 2015 during slurry wall construction. Site to be restored upon completion of work. Trail detour permitted separately under dtops #97792. Erosion control approved under dcra permit bciv1400047. Contractor to coordinate work with ddots awi team and 11th street bridge project. Date: November 25, 2014 Contractor: Impregilohealyparsons Jv Client: Carlton Ray Dc Water | Permit type: Paving; driveway behind sidewalk (porous/pervious only), mega projects; dc water combined sewer proj | Permit status: Permit expired | Expiration date: January 7, 2016 | Permit id: Pa103139 | |||||
SCORE 89 Shallow dewatering system to assist in near surface excavation at cso 007 site of dc waters clean rivers project div h. Thirteen (13) borings in total. Eight (8) primary dewatering wells and three (3) contingency dewatering wells of 8" diameter, and two monitoring wells of 6" diameter. Up to 7 dewatering wells and 1 monitoring well drilled to 25 bgs, with remaining 4 dewatering wells and 1 monitoring well drilled to bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa10172156. Date: May 13, 2015 Contractor: Impregilohealyparsons Jv Client: Carlton Ray Dc Water | Permit type: Excavation; monitoring well (each addl), excavation; monitoring well (single), mega projects; dc water combined sewer proj | Permit status: Permit expired | Expiration date: September 29, 2016 | Permit id: Pa110058 | |||||
SCORE 89 Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: May 11, 2015 Contractor: Impregilohealyparsons Jv Client: Carlton Ray Dc Water | Permit type: Excavation; sheeting & shoring (for buildings), mega projects; dc water combined sewer proj | Permit status: Permit expired | Expiration date: June 29, 2016 | Permit id: Pa109849 | |||||
SCORE 89 Soil borings for jet grouting at cso 007 site of dc waters clean rivers project div h, which falls in ddot row. Jet grouting needed for ground improvement to facilitate excavation beneath the 54 inch sewer and for mining of the adit connecting the anacostia river tunnel to the cso 007 shaft. Thirty-eight (38) borings of 8" diameter, to max depth of 118 bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa109849. Date: August 3, 2015 Contractor: Impregilohealyparsons Jv Client: Carlton Ray Dc Water | Permit type: Excavation; monitoring well (each addl), excavation; monitoring well (single), mega projects; dc water combined sewer proj | Permit status: Permit expired | Expiration date: September 13, 2016 | Permit id: Pa113783 | |||||
SCORE 89 Near surface structures construction for dc waters clean rivers project div h - cso 007 site. Construction of below-grade concrete approach channel, vent chamber, and odor control vault facility, to be installed adjacent to ramp c-3 near intersection with 11th street bridge. No change to existing ddoe-approved site plan or ddot-approved mot measures. Soe permitted separately via tops 109849. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Construction impact assessment report 6b submitted to ddot by dc water under separate cover. Date: August 6, 2015 Contractor: Impregilohealyparsons Jv Client: Carlton Ray Dc Water | Permit type: Excavation; vault(s) lxw, mega projects; dc water combined sewer proj | Permit status: Issued | Expiration date: November 29, 2016 | Permit id: Pa113982 | |||||
SCORE 89 Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: June 10, 2016 Contractor: Impregilohealyparsons Jv Client: Carlton Ray Dc Water | Permit type: Excavation; sheeting & shoring (for buildings), mega projects; dc water combined sewer proj | Permit status: Issued | Expiration date: June 29, 2017 | Permit id: Pa109849-R1 | |||||
SCORE 89 Excavation; sheeting & shoring (for buildings), mega projects; dc water combined sewer proj Date: June 16, 2016 Contractor: Impregilohealyparsons Jv Permit status: 9 | Expiration date: June 29, 2017 | Permit id: Pa109849-R1 | |||||
SCORE 89 Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: June 19, 2017 Contractor: Impregilohealyparsons Jv Client: Carlton Ray Dc Water | Permit type: Excavation; sheeting & shoring (for buildings), mega projects; dc water combined sewer proj | Permit status: Issued | Expiration date: December 31, 2017 | Permit id: Pa109849-R2 | |||||
SCORE 89 Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Contractor: Impregilohealyparsons Jv Permit status: Approved (pending payment | Expiration date: December 31, 2017 | Permit id: 0 | |||||
SCORE 89 Temporary wide gravel construction entrance to be installed in i-295 on-ramp from 11th street, se. Construction access for dc waters clean rivers project - division h - cso 007 shaft site. Access from ramp will be needed from january to april of 2015 during slurry wall construction. Site to be restored upon completion of work. Trail detour permitted separately under dtops #97792. Erosion control approved under dcra permit bciv1400047. Contractor to coordinate work with ddots awi team and 11th street bridge project. Date: February 4, 2015 Contractor: Impregilohealyparsons Jv Permit status: Permit expired | Expiration date: January 7, 2016 | Permit id: Pa103139 | |||||
SCORE 89 Shallow dewatering system to assist in near surface excavation at cso 007 site of dc waters clean rivers project div h. Thirteen (13) borings in total. Eight (8) primary dewatering wells and three (3) contingency dewatering wells of 8" diameter, and two monitoring wells of 6" diameter. Up to 7 dewatering wells and 1 monitoring well drilled to 25 bgs, with remaining 4 dewatering wells and 1 monitoring well drilled to bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa10172156. Date: February 17, 2016 Contractor: Impregilohealyparsons Jv Permit status: Permit expired | Expiration date: September 29, 2016 | Permit id: Pa110058 | |||||
SCORE 89 Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: July 15, 2015 Contractor: Impregilohealyparsons Jv Permit status: Permit expired | Expiration date: June 29, 2016 | Permit id: Pa109849 | |||||
SCORE 89 Soil borings for jet grouting at cso 007 site of dc waters clean rivers project div h, which falls in ddot row. Jet grouting needed for ground improvement to facilitate excavation beneath the 54 inch sewer and for mining of the adit connecting the anacostia river tunnel to the cso 007 shaft. Thirty-eight (38) borings of 8" diameter, to max depth of 118 bgs. Mud rotary drilling method. Mot measures already permitted and in place under tops pa109849. Date: August 24, 2015 Contractor: Impregilohealyparsons Jv Permit status: Permit expired | Expiration date: September 13, 2016 | Permit id: Pa113783 | |||||
SCORE 89 Near surface structures construction for dc waters clean rivers project div h - cso 007 site. Construction of below-grade concrete approach channel, vent chamber, and odor control vault facility, to be installed adjacent to ramp c-3 near intersection with 11th street bridge. No change to existing ddoe-approved site plan or ddot-approved mot measures. Soe permitted separately via tops 109849. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Construction impact assessment report 6b submitted to ddot by dc water under separate cover. Date: August 26, 2015 Contractor: Impregilohealyparsons Jv Permit status: Permit expired | Expiration date: November 29, 2016 | Permit id: Pa113982 | |||||
SCORE 89 Support of excavation for near surface work at cso 007 shaft site for dc waters clean rivers div h project. Sheeting and shoring to be installed adjacent to ramp c-3 near intersection of 11th street bridge. Soe system will consist of sheet piles, tie backs, walers, and struts. Shallow dewatering wells permitted separately through tops #110058. No change to existing ddoe-approved site plan or ddot-approved mot measures. Reference tops permits #97792, 103139, 10172156; and bciv1400047. Date: June 21, 2017 Contractor: Impregilohealyparsons Jv Permit status: Issued | Expiration date: December 31, 2017 | Permit id: Pa109849-R2 |