Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 62 Non-structural remodel converting portions of existing cafeteria seating area, office area, and storage room into a new health unit Date: July 29, 2015 Contractor: Curtis Miner Architecture Llc Permit type: Permit | Permit status: Corrections required | Completion date: September 1, 2015 | Current use: Commercial | Permit id: Bld2015-05914 | |||||
SCORE 100 Plan review approved for permit issuance. Please arrange to pay the balance due. Fire suppression Date: January 21, 2015 Contractor: Interstate Fire Sales And Service Llc Permit type: Fire | Permit status: Completed | Completion date: February 10, 2015 | Current use: Commercial | Permit id: Bld2015-00441 | |||||
SCORE 100 Remodel the 24th floor of the church office building Date: January 7, 2015 Contractor: Aj Sheet Metal Inc Permit type: Mechanical | Permit status: Accepted | Completion date: January 7, 2015 | Current use: Commercial | Permit id: Bld2015-00101 | |||||
SCORE 99 Fire sprinkler system Date: December 2, 2014 Contractor: Western Automatic Sprinkler In Permit type: Fire | Permit status: Completed | Completion date: December 22, 2014 | Current use: Commercial | Permit id: Bld2014-08834 | |||||
SCORE 100 Complete interior remodel of the 24th floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: September 11, 2014 Contractor: Bigd Construction Corp Permit type: Permit | Permit status: Completed | Completion date: November 20, 2014 | Current use: Commercial | Permit id: Bld2014-06620 | |||||
SCORE 100 Lds church intends to remodel the three main stairwells to the church office building tower: center stairwell, north east stairwell and north west stairwell. This is a voluntary seismic upgrade including an aesthetic refresh to the finish materials in the stairwells. Scope of work includes the main level up to the 28th and 29th floors. No work in the lower parking stairwells will be completed. No work in the east wing or west wing stairwells will be completed at this time. Intent is for the construction of this project to be phased. A detailed description of the construction phasing is included within the the design criteria. Date: March 1, 2013 Contractor: Layton Construction Co. Inc Permit type: Permit | Permit status: Completed | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2013-01195 | |||||
SCORE 100 Replacement of duct work and terminal units entire floor Date: December 28, 2012 Contractor: Aj Sheet Metal Inc Permit type: Mechanical | Permit status: Completed | Completion date: December 28, 2012 | Current use: Commercial | Permit id: Bld2012-09350 | |||||
SCORE 61 14th floor to receive fire sprinkler system. We will begin our work after the control valve and flow switch that is currently installed. Date: December 13, 2012 Contractor: Lds Church Office Bldg 14th Floor Remodel Permit type: Fire | Permit status: Completed | Completion date: December 27, 2012 | Current use: Commercial | Permit id: Bld2012-09111 | |||||
SCORE 95 Interior non-structural demolition, fire proofing will be included in the scope of this permit d. D. A. H. Date: October 19, 2012 Permit type: Permit | Permit status: Pass | Completion date: October 19, 2012 | Current use: Commercial | Permit id: Bld2012-07761 | |||||
SCORE 100 Interior space finished out requires pendent heads to be dropped to protect new space and ceiling layout. (existing heads are pendent style and are located in 1" outlets using bushings) Date: February 1, 2011 Contractor: Interwest Fire Protection Permit type: Fire | Permit status: Completed | Completion date: March 21, 2011 | Current use: Commercial | Permit id: Bld2011-00623 | |||||
SCORE 100 Fire sprinkler system. Food court block 75 building 4 Date: January 24, 2011 Contractor: Taylor Electric Inc Permit type: Low voltage | Permit status: Completed | Completion date: March 9, 2011 | Current use: Commercial | Permit id: Bld2011-00487 | |||||
Low voltage Date: February 3, 2015 Permit type: Fire | Permit status: Pass | Completion date: March 17, 2015 | Current use: Commercial | Permit id: Bld2015-00740 | |||||
Plan review approved for permit issuance. Please arrange to pay the balance due. Fire suppression Date: January 21, 2015 Permit type: Fire | Permit status: Completed | Completion date: February 10, 2015 | Current use: Commercial | Permit id: Bld2015-00441 | |||||
Remodel the 24th floor of the church office building Date: January 7, 2015 Permit type: Mechanical | Permit status: Accepted | Completion date: January 7, 2015 | Current use: Commercial | Permit id: Bld2015-00101 | |||||
SCORE 100 Interior remodel Date: December 31, 2014 Contractor: Okland Construction Co Permit type: Permit | Permit status: Closed | Completion date: February 23, 2015 | Current use: Commercial | Permit id: Bld2014-09469 | |||||
SCORE 64 1-lav, 1-water closet, 1-drain bathroom remodel Date: December 23, 2014 Contractor: Reliable Plumbing And Heating Inccob 24th Floor Permit type: Plumbing | Permit status: Closed | Completion date: April 16, 2015 | Current use: Commercial | Permit id: Bld2014-09371 | |||||
SCORE 64 Project is to add notification appliances in the corridors of the annex and sl temple structures. Date: December 22, 2014 Contractor: Simplexgrinnell Lpsl Temple Corridor Upgrade Permit type: Low voltage | Permit status: Closed | Completion date: February 11, 2015 | Current use: Commercial | Permit id: Bld2014-09340 | |||||
SCORE 64 This is a complete remodel of the 24th floor of the church office building. A new nac panel will be installed to control the new strobes and the existing speaker circuit will be used to run the new speakers. New duct detectors will be installed as well as all equipment that makes up the fire alarm for this floor. Date: November 17, 2014 Contractor: Simplexgrinnell Lplds Cob 24th Floor Permit type: Low voltage | Permit status: Closed | Completion date: March 31, 2015 | Current use: Commercial | Permit id: Bld2014-08454 | |||||
Hvac remodel of 23 floor Date: October 1, 2014 Permit type: Mechanical | Permit status: Pass | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2014-07147 | |||||
SCORE 64 Remodel of entire floor. Use all new equipment and tie to existing transponder in electrical room. Mount new nac panel in closet located in store room 2301 to run strobe circuits, run speaker circuits to the existing transponder. Damper shutdown relays are to be located in each of the electrical rooms. The east electrical room will close the east dampers and the west electrical room will close the west dampers. Duct detectors will be mounted within 5 of each damper. The initiating circuit will run back to the existing transponder, the circuit is m9. Won-door controller is located in the east electrical room and connect to the transponder from there. Date: September 9, 2014 Contractor: Simplexgrinnelllds Cob 23rd Floor Remodel Permit type: Low voltage | Permit status: Closed | Completion date: February 10, 2015 | Current use: Commercial | Permit id: Bld2014-06524 | |||||
Splits are charged for both heating and cooling. Install 1. 5 ton unitary split system Date: July 18, 2014 Permit type: Mechanical | Permit status: Pass | Completion date: August 25, 2014 | Current use: Commercial | Permit id: Bld2014-05135 | |||||
SCORE 64 Replace existing ups system Date: July 11, 2014 Permit type: Electrical | Permit status: Closed | Completion date: August 25, 2014 | Current use: Commercial | Permit id: Bld2014-04922 | |||||
SCORE 64 We will prepare the existing roof to receive the new system by removing the existing epdm membrane. We will be installing tapered foam crickets around the outside between drains and a 1/4" hard board will be installed. We will be installing a light grey s-327 mil pvc single-ply membrane, manufactured by sarnafil. This system will be attached using rhino bond adhered mechanically fastening system. Date: April 22, 2014 Permit type: Roofing | Permit status: Closed | Completion date: May 13, 2014 | Current use: Commercial | Permit id: Bld2014-02647 | |||||
SCORE 64 Install ahu, coils, pumps, and fan coil units Date: October 28, 2013 Permit type: Mechanical | Permit status: Closed | Completion date: March 31, 2014 | Current use: Commercial | Permit id: Bld2013-07968 | |||||
SCORE 64 Remodel of the east wing of the church office building. Floors include levels 4, 3, 2, 1, ll1, ll2, and ll3. Floors 1, ll1, ll2, and ll3 will connect to the ll1 east transponder. Floors 4, 3, and 2 will connect to the 3rd floor east transponder. Date: October 23, 2013 Contractor: Simplexgrinnelllds Cob East Wing Remodel Permit type: Low voltage | Permit status: Closed | Completion date: March 28, 2014 | Current use: Commercial | Permit id: Bld2013-07805 | |||||
SCORE 64 Hvac sheet metal Date: October 18, 2013 Contractor: Rm Chris Sheet Metalcob East Wing Permit type: Mechanical | Permit status: Closed | Completion date: May 29, 2014 | Current use: Commercial | Permit id: Bld2013-07691 | |||||
SCORE 64 Detection for rooms to be added to existing preaction system. Date: July 1, 2013 Contractor: Simplexgrinnell Lplds Nob Preaction Addition Permit type: Low voltage | Permit status: Completed | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-04502 | |||||
Lds church intends to remodel the three main stairwells to the church office building tower: center stairwell, north east stairwell and north west stairwell. This is a voluntary seismic upgrade including an aesthetic refresh to the finish materials in the stairwells. Scope of work includes the main level up to the 28th and 29th floors. No work in the lower parking stairwells will be completed. No work in the east wing or west wing stairwells will be completed at this time. Intent is for the construction of this project to be phased. A detailed description of the construction phasing is included within the the design criteria. Date: March 1, 2013 Permit type: Permit | Permit status: Completed | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2013-01195 | |||||
Renovation of the existing cafeteria & dining areas to include renovated salad bar area and soup bar; also upgrading floor & wall finishes. Date: February 21, 2013 Permit type: Permit | Permit status: Pass | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-00978 | |||||
SCORE 64 Various piping for new fixtures at church office bldg. Date: January 4, 2013 Contractor: Reliable Plumbing And Heating14th Floor Remodel Permit type: Plumbing | Permit status: Closed | Completion date: March 4, 2013 | Current use: Commercial | Permit id: Bld2013-00076 | |||||
SCORE 64 Fire alarm for 14th remodel Date: December 7, 2012 Contractor: Simplexgrinnell Lplds Office Bldg 14th Remodel Permit type: Low voltage | Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-08988 | |||||
Installing an addressable system in the temple proper and annex bldg. Devices will be replaced 1 for 1 in 95% of the building. This will not be a full upgrade at this time, but will accomodate for coverage based on the existing system. Date: August 6, 2012 Permit type: Low voltage | Permit status: Pass | Completion date: February 25, 2013 | Current use: Commercial | Permit id: Bld2012-05726 | |||||
SCORE 77 Fire sprinkler system. Module 3 Date: January 25, 2012 Contractor: Firetrol Protection Systemssalt Lake Temple Permit type: Fire | Permit status: Closed | Completion date: February 3, 2012 | Current use: Commercial | Permit id: Bld2012-00667 | |||||
SCORE 64 Electrical rough in for door modifications Date: November 14, 2011 Permit type: Electrical | Permit status: Reviews not require | Completion date: November 14, 2011 | Current use: Commercial | Permit id: Bld2011-07479 | |||||
SCORE 86 Temp structure, annual church function Date: October 6, 2011 Contractor: Diamond Rentallds Church Main Office Permit type: Temporary use | Permit status: Completed | Completion date: October 6, 2011 | Permit id: Bld2011-06453 | |||||
SCORE 64 Fire door and overhead door upgrades Date: September 27, 2011 Contractor: Crc Construction Incchurch Office Bldg Permit type: Permit | Permit status: Closed | Completion date: February 9, 2012 | Current use: Commercial | Permit id: Bld2011-06201 | |||||
SCORE 77 Fire sprinkler system. Module 3 Date: August 16, 2011 Contractor: Firetrol Protection Systemssalt Lake Temple Permit type: Fire | Permit status: Closed | Completion date: August 13, 2012 | Current use: Commercial | Permit id: Bld2011-05147 | |||||
Site modifications for the placement of bollards on private property 07/12/2011 Date: July 12, 2011 Permit type: Permit | Permit status: Pass | Completion date: March 15, 2013 | Current use: Commercial | Permit id: Bld2011-04263 | |||||
SCORE 64 Interior space finished out requires pendent heads to be dropped to protect new space and ceiling layout. (existing heads are pendent style and are located in 1" outlets using bushings) Date: February 1, 2011 Permit type: Fire | Permit status: Inspections | Completion date: March 21, 2011 | Current use: Commercial | Permit id: Bld2011-00623 | |||||
Fire sprinkler system. Food court block 75 building 4 Date: January 24, 2011 Permit type: Low voltage | Permit status: Completed | Completion date: March 9, 2011 | Current use: Commercial | Permit id: Bld2011-00487 | |||||
Replacing existing hollow / metal doors and frames and add 2 coiling doors. Door types, sizes and harware remains the same. (maintenance replacement) g. S. D-1 zone, interior to doors. A. S. Date: June 29, 2010 Permit type: Permit | Permit status: Pass | Completion date: September 17, 2010 | Current use: Commercial | Permit id: Bld2010-04368 | |||||
SCORE 61 Complete interior remodel of the 24th floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: November 20, 2014 Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-06620 | |||||
SCORE 65 Lds church intends to remodel the three main stairwells to the church office building tower: center stairwell, north east stairwell and north west stairwell. This is a voluntary seismic upgrade including an aesthetic refresh to the finish materials in the stairwells. Scope of work includes the main level up to the 28th and 29th floors. No work in the lower parking stairwells will be completed. No work in the east wing or west wing stairwells will be completed at this time. Intent is for the construction of this project to be phased. A detailed description of the construction phasing is included within the the design criteria. Date: April 19, 2016 Permit status: Inspections | Current use: Commercial | Permit id: Bld2013-01195 | |||||
SCORE 59 Elec work for 13th flr remodel Date: July 28, 2010 Permit type: Electrical | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05084 | |||||
SCORE 59 Elec work for cob fire door project Date: July 9, 2010 Permit type: Electrical | Permit status: Closed | Completion date: September 16, 2010 | Current use: Commercial | Permit id: Bld2010-04658 | |||||
SCORE 61 Non-structural remodel converting portions of existing cafeteria seating area, office area, and storage room into a new health unit Date: December 17, 2015 Contractor: Lds Cob 1ll Health Unit Remodelbrent Lundevall Permit status: Closed | Current use: Commercial | Permit id: Bld2015-05914 | |||||
Install 36 vav/fan coil units for interior remodel - 13th Date: July 21, 2010 Permit type: Mechanical | Permit status: Closed | Completion date: April 1, 2013 | Current use: Commercial | Permit id: Bld2010-04976 | |||||
SCORE 66 Fire sprinkler modifications for 13th floor interior remodel. Date: July 22, 2010 Permit type: Fire | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05000 | |||||
SCORE 66 13th floor interior remodel. Fixture grand total 2, grand total of fixture units 5 and 1 floor drains. Date: August 11, 2010 Permit type: Plumbing | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05451 | |||||
SCORE 65 Lds church intends to remodel the three main stairwells to the church office building tower: center stairwell, north east stairwell and north west stairwell. This is a voluntary seismic upgrade including an aesthetic refresh to the finish materials in the stairwells. Scope of work includes the main level up to the 28th and 29th floors. No work in the lower parking stairwells will be completed. No work in the east wing or west wing stairwells will be completed at this time. Intent is for the construction of this project to be phased. A detailed description of the construction phasing is included within the the design criteria. Date: April 19, 2016 Permit status: Inspections | Current use: Commercial | Permit id: Bld2013-01195 | |||||
SCORE 56 Replacing existing hollow / metal doors and frames and add 2 coiling doors. Door types, sizes and harware remains the same. (maintenance replacement) g. S. D-1 zone, interior to doors. A. S. Date: June 29, 2010 Permit status: Closed | Completion date: September 17, 2010 | Current use: Commercial | Permit id: Bld2010-04368 | |||||
SCORE 66 Interior only, non structural demo of office space. No new work excepet capping off elec, mech, & plmb. Drawings are for reference only, new work will be submitted in 4-6 weeks. Tmb ah 05/19/2010 Date: May 19, 2010 Permit status: Closed | Completion date: April 1, 2013 | Current use: Commercial | Permit id: Bld2010-03251 | |||||
SCORE 61 Complete interior remodel of the 23rd floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: February 12, 2015 Permit status: Closed | Current use: Commercial | Permit id: Bld2014-04780 | |||||
SCORE 61 Interior remodel Date: February 23, 2015 Contractor: Garland Brinkerhoff Permit status: Closed | Current use: Commercial | Permit id: Bld2014-09469 | |||||
SCORE 59 Fire alarm system for the 13th floor interior remodel. Date: August 24, 2010 Permit type: Fire | Permit status: Closed | Completion date: May 17, 2011 | Current use: Commercial | Permit id: Bld2010-05777 | |||||
SCORE 59 Low voltage fire alarm system. Date: August 24, 2010 Permit type: Low voltage | Permit status: Closed | Completion date: March 31, 2011 | Current use: Commercial | Permit id: Bld2010-05778 | |||||
SCORE 66 Ductwork / misc. Work for 13th floor interior remodel Date: September 7, 2010 Permit type: Mechanical | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-06108 | |||||
SCORE 61 Fire sprinkler system. Food court block 75 building 4 Date: January 24, 2011 Permit type: Low voltage | Permit status: Inspections | Completion date: March 9, 2011 | Current use: Commercial | Permit id: Bld2011-00487 | |||||
Site modifications for the placement of bollards on private property 07/12/2011 Date: July 12, 2011 Permit status: Closed | Completion date: March 15, 2013 | Current use: Commercial | Permit id: Bld2011-04263 | |||||
Installing an addressable system in the temple proper and annex bldg. Devices will be replaced 1 for 1 in 95% of the building. This will not be a full upgrade at this time, but will accomodate for coverage based on the existing system. Date: August 6, 2012 Permit type: Low voltage | Permit status: Closed | Completion date: February 25, 2013 | Current use: Commercial | Permit id: Bld2012-05726 | |||||
SCORE 66 Interior non-structural demolition, fire proofing will be included in the scope of this permit d. D. A. H. Date: October 19, 2012 Permit status: Inspections | Completion date: October 19, 2012 | Current use: Commercial | Permit id: Bld2012-07761 | |||||
SCORE 56 Interior remodel of 14th floor d. D. A. H. D. W. Date: October 19, 2012 Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-07762 | |||||
14th floor to receive fire sprinkler system. We will begin our work after the control valve and flow switch that is currently installed. Date: December 13, 2012 Permit type: Fire | Permit status: Inspections | Completion date: December 27, 2012 | Current use: Commercial | Permit id: Bld2012-09111 | |||||
SCORE 66 Interior remodel of the church office building 14th floor. Gc permit #bld2012-07762 Date: December 26, 2012 Contractor: Copper Mountain Electriccob 14th Floor Remodel Permit type: Electrical | Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-09321 | |||||
Replacement of duct work and terminal units entire floor Date: December 28, 2012 Permit type: Mechanical | Permit status: Inspections | Completion date: December 28, 2012 | Current use: Commercial | Permit id: Bld2012-09350 | |||||
Lds church office building - 14th floor vault & vault ante room fm-2 fire suppression system with controls for pre-action fire sprinkler system (pre-action sprinkler system is furnished and installed by others) Date: February 12, 2013 Permit type: Fire | Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2013-00771 | |||||
SCORE 56 Renovation of the existing cafeteria & dining areas to include renovated salad bar area and soup bar; also upgrading floor & wall finishes. Date: February 21, 2013 Permit status: Closed | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-00978 | |||||
SCORE 59 Lds church intends to remodel the three main stairwells to the church office building tower: center stairwell, north east stairwell and north west stairwell. This is a voluntary seismic upgrade including an aesthetic refresh to the finish materials in the stairwells. Scope of work includes the main level up to the 28th and 29th floors. No work in the lower parking stairwells will be completed. No work in the east wing or west wing stairwells will be completed at this time. Intent is for the construction of this project to be phased. A detailed description of the construction phasing is included within the the design criteria. Date: March 1, 2013 Permit status: Inspections | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2013-01195 | |||||
SCORE 66 Fire sprinklers nob publishing services Date: May 30, 2013 Permit type: Fire | Permit status: Closed | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-03533 | |||||
SCORE 56 Int tenant improvement, mech/elec/plmbg permits reqd k. A. Int remodel only a. H. D. W. Date: June 20, 2013 Permit status: Closed | Completion date: May 30, 2014 | Current use: Commercial | Permit id: Bld2013-04165 | |||||
SCORE 66 Church office building east wing remodel of 4 floors Date: August 22, 2013 Contractor: Wasatch Electriccob East Wing Remodel Permit type: Electrical | Permit status: Closed | Completion date: March 28, 2014 | Current use: Commercial | Permit id: Bld2013-06002 | |||||
SCORE 66 Adding sprinklers to levels 1-4 in the east wing of the church office building. Floor control valve assemblies already exist and we are attaching to them and running the sprinkler system out. Date: August 30, 2013 Contractor: Lds Cob East Wing Remodel Permit type: Fire | Permit status: Closed | Completion date: May 29, 2014 | Current use: Commercial | Permit id: Bld2013-06275 | |||||
SCORE 66 Plumbing remodel Date: September 12, 2013 Permit type: Plumbing | Permit status: Closed | Completion date: March 24, 2014 | Current use: Commercial | Permit id: Bld2013-06648 | |||||
SCORE 79 Fire sprinklers (clean agent) Date: April 23, 2014 Contractor: Fire Engineering Company Incchurch Office Bldg Permit type: Fire | Permit status: Closed | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2014-02688 | |||||
SCORE 79 Low voltage alarm (clean agent) Date: April 24, 2014 Contractor: Fire Engineering Company Incchurch Office Bldg Permit type: Low voltage | Permit status: Closed | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2014-02698 | |||||
Complete interior remodel of the 23rd floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: July 7, 2014 Permit status: Closed | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2014-04780 | |||||
SCORE 56 Splits are charged for both heating and cooling. Install 1. 5 ton unitary split system Date: July 18, 2014 Permit type: Mechanical | Permit status: Closed | Completion date: August 25, 2014 | Current use: Commercial | Permit id: Bld2014-05135 | |||||
Complete interior remodel of the 24th floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: September 11, 2014 Permit status: Inspections | Completion date: November 20, 2014 | Current use: Commercial | Permit id: Bld2014-06620 | |||||
SCORE 66 Fire sprinklers for the 23rd floor Date: September 22, 2014 Permit type: Fire | Permit status: Closed | Completion date: January 23, 2015 | Current use: Commercial | Permit id: Bld2014-06879 | |||||
SCORE 66 Tenant improvement of 23rd floor gc permit big-d bld2014-04780 Date: September 26, 2014 Permit type: Electrical | Permit status: Closed | Completion date: February 2, 2015 | Current use: Commercial | Permit id: Bld2014-07022 | |||||
Hvac remodel of 23 floor Date: October 1, 2014 Permit type: Mechanical | Permit status: Closed | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2014-07147 | |||||
SCORE 66 Remodel of the 23rd floor at the church office building Date: October 24, 2014 Permit type: Plumbing | Permit status: Closed | Completion date: February 3, 2015 | Current use: Commercial | Permit id: Bld2014-07790 | |||||
SCORE 66 Fire sprinkler system Date: December 2, 2014 Permit type: Fire | Permit status: Inspections | Completion date: December 22, 2014 | Current use: Commercial | Permit id: Bld2014-08834 | |||||
SCORE 66 Elec work for tenant improvement on 24th floor of lds church office building big-d general permit #bld2014-06620 Date: December 8, 2014 Contractor: Copper Mountain Electriclds Cob 24th Floor Permit type: Electrical | Permit status: Closed | Completion date: April 3, 2015 | Current use: Commercial | Permit id: Bld2014-08943 | |||||
Remodel the 24th floor of the church office building Date: January 7, 2015 Permit type: Mechanical | Permit status: Inspections | Completion date: January 7, 2015 | Current use: Commercial | Permit id: Bld2015-00101 | |||||
Plan review approved for permit issuance. Please arrange to pay the balance due. Fire suppression Date: January 21, 2015 Permit type: Fire | Permit status: Inspections | Completion date: February 10, 2015 | Current use: Commercial | Permit id: Bld2015-00441 | |||||
Low voltage Date: February 3, 2015 Permit type: Fire | Permit status: Closed | Completion date: March 17, 2015 | Current use: Commercial | Permit id: Bld2015-00740 | |||||
SCORE 59 Non-structural remodel converting portions of existing cafeteria seating area, office area, and storage room into a new health unit Date: July 29, 2015 Permit status: Inspections | Completion date: October 19, 2015 | Current use: Commercial | Permit id: Bld2015-05914 | |||||
SCORE 68 Ductwork over 1,0 one exhaust fan, 19 vav boxes Date: June 22, 2012 Contractor: B2 Air Systems Llc Permit type: Mechanical | Permit status: Accepted | Completion date: June 22, 2012 | Current use: Commercial | Permit id: Bld2012-04574 | |||||
Ductwork over 1,0 one exhaust fan, 19 vav boxes Date: June 22, 2012 Permit type: Mechanical | Permit status: Inspections | Completion date: June 22, 2012 | Current use: Commercial | Permit id: Bld2012-04574 | |||||
SCORE 100 Modifications to fire alarm Date: February 17, 2010 Contractor: Simplexgrinnell Permit type: Low voltage | Permit status: Corrections requested | Completion date: March 29, 2010 | Current use: Commercial | Permit id: Bld2010-00814 | |||||
SCORE 95 Demo of east wing Date: July 23, 2009 Permit type: Permit | Permit status: In progress | Completion date: July 23, 2009 | Current use: Commercial | Permit id: Bld2009-04342 | |||||
SCORE 95 7th floor remodel Date: December 19, 2008 Permit type: Permit | Permit status: Completed | Completion date: February 17, 2009 | Current use: Commercial | Permit id: Bld2008-04424 | |||||
SCORE 61 Fire alarm modifications for 2nd flr remodel. Date: February 3, 2010 Permit type: Low voltage | Permit status: Closed | Completion date: May 17, 2010 | Current use: Commercial | Permit id: Bld2010-00537 | |||||
SCORE 59 Modifications to fire alarm Date: February 17, 2010 Contractor: Simplexgrinnelllds Cob Ll3 Chiller Room Permit type: Low voltage | Permit status: Corrections requested | Completion date: March 29, 2010 | Current use: Commercial | Permit id: Bld2010-00814 | |||||
SCORE 100 Lds 1ll, 2ll mech hvac upgrade Date: March 1, 2010 Contractor: Simplexgrinnell Permit type: Low voltage | Permit status: Inspections | Completion date: March 15, 2010 | Current use: Commercial | Permit id: Bld2010-01075 | |||||
Non-structural remodel converting portions of existing cafeteria seating area, office area, and storage room into a new health unit Date: July 29, 2015 Permit type: Permit | Permit status: Completed | Completion date: October 19, 2015 | Current use: Commercial | Permit id: Bld2015-05914 | |||||
SCORE 66 Elec work for tenant improvement on 24th floor of lds church office building big-d general permit #bld2014-06620 Date: December 8, 2014 Contractor: Copper Mountain Electriclds Cob 24th Floor Permit type: Electrical | Permit status: Pass | Completion date: April 3, 2015 | Current use: Commercial | Permit id: Bld2014-08943 | |||||
SCORE 66 Fire sprinkler system Date: December 2, 2014 Permit type: Fire | Permit status: Completed | Completion date: December 22, 2014 | Current use: Commercial | Permit id: Bld2014-08834 | |||||
Complete interior remodel of the 24th floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: September 11, 2014 Permit type: Permit | Permit status: Pass | Completion date: November 20, 2014 | Current use: Commercial | Permit id: Bld2014-06620 | |||||
SCORE 66 Remodel of the 23rd floor at the church office building Date: October 24, 2014 Permit type: Plumbing | Permit status: Pass | Completion date: February 3, 2015 | Current use: Commercial | Permit id: Bld2014-07790 | |||||
SCORE 66 Fire sprinklers for the 23rd floor Date: September 22, 2014 Permit type: Fire | Permit status: Pass | Completion date: January 23, 2015 | Current use: Commercial | Permit id: Bld2014-06879 | |||||
Complete interior remodel of the 23rd floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: July 7, 2014 Permit type: Permit | Permit status: Pass | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2014-04780 | |||||
SCORE 66 Tenant improvement of 23rd floor gc permit big-d bld2014-04780 Date: September 26, 2014 Permit type: Electrical | Permit status: Pass | Completion date: February 2, 2015 | Current use: Commercial | Permit id: Bld2014-07022 | |||||
SCORE 79 Low voltage alarm (clean agent) Date: April 24, 2014 Contractor: Fire Engineering Company Incchurch Office Bldg Permit type: Low voltage | Permit status: Pass | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2014-02698 | |||||
SCORE 79 Fire sprinklers (clean agent) Date: April 23, 2014 Contractor: Fire Engineering Company Incchurch Office Bldg Permit type: Fire | Permit status: Pass | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2014-02688 | |||||
SCORE 66 Plumbing remodel Date: September 12, 2013 Permit type: Plumbing | Permit status: Pass | Completion date: March 24, 2014 | Current use: Commercial | Permit id: Bld2013-06648 | |||||
SCORE 66 Adding sprinklers to levels 1-4 in the east wing of the church office building. Floor control valve assemblies already exist and we are attaching to them and running the sprinkler system out. Date: August 30, 2013 Contractor: Lds Cob East Wing Remodel Permit type: Fire | Permit status: Pass | Completion date: May 29, 2014 | Current use: Commercial | Permit id: Bld2013-06275 | |||||
SCORE 66 Church office building east wing remodel of 4 floors Date: August 22, 2013 Contractor: Wasatch Electriccob East Wing Remodel Permit type: Electrical | Permit status: Pass | Completion date: March 28, 2014 | Current use: Commercial | Permit id: Bld2013-06002 | |||||
SCORE 64 Minimum commercial electrical. Cafeteria remodel Date: July 17, 2013 Contractor: Great Salt Lake Electric Incorporatedlds Church Permit type: Electrical | Permit status: Closed | Completion date: August 1, 2013 | Current use: Commercial | Permit id: Bld2013-04984 | |||||
Int tenant improvement, mech/elec/plmbg permits reqd k. A. Int remodel only a. H. D. W. Date: June 20, 2013 Permit type: Permit | Permit status: Pass | Completion date: May 30, 2014 | Current use: Commercial | Permit id: Bld2013-04165 | |||||
SCORE 66 Fire sprinklers nob publishing services Date: May 30, 2013 Permit type: Fire | Permit status: Pass | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-03533 | |||||
Lds church office building - 14th floor vault & vault ante room fm-2 fire suppression system with controls for pre-action fire sprinkler system (pre-action sprinkler system is furnished and installed by others) Date: February 12, 2013 Permit type: Fire | Permit status: Pass | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2013-00771 | |||||
Replacement of duct work and terminal units entire floor Date: December 28, 2012 Permit type: Mechanical | Permit status: Completed | Completion date: December 28, 2012 | Current use: Commercial | Permit id: Bld2012-09350 | |||||
SCORE 66 Interior remodel of the church office building 14th floor. Gc permit #bld2012-07762 Date: December 26, 2012 Contractor: Copper Mountain Electriccob 14th Floor Remodel Permit type: Electrical | Permit status: Pass | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-09321 | |||||
14th floor to receive fire sprinkler system. We will begin our work after the control valve and flow switch that is currently installed. Date: December 13, 2012 Permit type: Fire | Permit status: Completed | Completion date: December 27, 2012 | Current use: Commercial | Permit id: Bld2012-09111 | |||||
SCORE 66 Interior non-structural demolition, fire proofing will be included in the scope of this permit d. D. A. H. Date: October 19, 2012 Permit type: Permit | Permit status: Pass | Completion date: October 19, 2012 | Current use: Commercial | Permit id: Bld2012-07761 | |||||
Interior remodel of 14th floor d. D. A. H. D. W. Date: October 19, 2012 Permit type: Permit | Permit status: Pass | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-07762 | |||||
Ductwork over 1,0 one exhaust fan, 19 vav boxes Date: June 22, 2012 Permit type: Mechanical | Permit status: Accepted | Completion date: June 22, 2012 | Current use: Commercial | Permit id: Bld2012-04574 | |||||
SCORE 66 Ductwork / misc. Work for 13th floor interior remodel Date: September 7, 2010 Permit type: Mechanical | Permit status: Completed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-06108 | |||||
Low voltage fire alarm system. Date: August 24, 2010 Permit type: Low voltage | Permit status: Pass | Completion date: March 31, 2011 | Current use: Commercial | Permit id: Bld2010-05778 | |||||
Fire alarm system for the 13th floor interior remodel. Date: August 24, 2010 Permit type: Fire | Permit status: Completed | Completion date: May 17, 2011 | Current use: Commercial | Permit id: Bld2010-05777 | |||||
SCORE 66 13th floor interior remodel. Fixture grand total 2, grand total of fixture units 5 and 1 floor drains. Date: August 11, 2010 Permit type: Plumbing | Permit status: Completed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05451 | |||||
Elec work for 13th flr remodel Date: July 28, 2010 Permit type: Electrical | Permit status: Completed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05084 | |||||
SCORE 66 Fire sprinkler modifications for 13th floor interior remodel. Date: July 22, 2010 Permit type: Fire | Permit status: Completed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05000 | |||||
Install 36 vav/fan coil units for interior remodel - 13th Date: July 21, 2010 Permit type: Mechanical | Permit status: Pass | Completion date: April 1, 2013 | Current use: Commercial | Permit id: Bld2010-04976 | |||||
Elec work for cob fire door project Date: July 9, 2010 Permit type: Electrical | Permit status: Pass | Completion date: September 16, 2010 | Current use: Commercial | Permit id: Bld2010-04658 | |||||
SCORE 66 Interior only, non structural demo of office space. No new work excepet capping off elec, mech, & plmb. Drawings are for reference only, new work will be submitted in 4-6 weeks. Tmb ah 05/19/2010 Date: May 19, 2010 Permit type: Permit | Permit status: Pass | Completion date: April 1, 2013 | Current use: Commercial | Permit id: Bld2010-03251 | |||||
SCORE 79 Plumbing for complete floor remodel of 2nd level, fixture grand total 2, grand total of fixture units 7 and 1 floor drain. Date: February 10, 2010 Permit type: Plumbing | Permit status: Pass | Completion date: May 27, 2010 | Current use: Commercial | Permit id: Bld2010-00699 | |||||
SCORE 79 Mechanical for a complete floor remodel of 2nd level, 1 air handlers up to 10,0 cfms. Date: February 10, 2010 Permit type: Mechanical | Permit status: Pass | Completion date: March 24, 2010 | Current use: Commercial | Permit id: Bld2010-00700 | |||||
Complete floor remodel of 2nd level. D-1 zone d. D. Zone: k. B. Credit card has been declined. No further inspections until permit has been paid for in full. Date: February 8, 2010 Permit type: Mechanical | Permit status: Pass | Completion date: May 7, 2013 | Current use: Commercial | Permit id: Bld2010-00608 | |||||
Elec work for 2nd flr remodel Date: February 5, 2010 Permit type: Electrical | Permit status: Pass | Completion date: April 14, 2010 | Current use: Commercial | Permit id: Bld2010-00593 | |||||
SCORE 66 Fire sprinkler modifications for 2nd flr remodel. Date: January 27, 2010 Permit type: Fire | Permit status: Pass | Completion date: April 19, 2010 | Current use: Commercial | Permit id: Bld2010-00391 | |||||
Complete floor remodel of 2nd level. D-1 zone d. D. Zone, k. B. Date: January 5, 2010 Permit type: Permit | Permit status: Pass | Completion date: April 16, 2010 | Current use: Commercial | Permit id: Bld2010-00036 | |||||
SCORE 61 Fire alarm modifications for 2nd flr remodel. Date: February 3, 2010 Permit type: Low voltage | Permit status: Pass | Completion date: May 17, 2010 | Current use: Commercial | Permit id: Bld2010-00537 | |||||
SCORE 64 Demo of east wing Date: July 23, 2009 Permit type: Permit | Permit status: In progress | Completion date: July 23, 2009 | Current use: Commercial | Permit id: Bld2009-04342 | |||||
SCORE 66 7th floor remodel Date: December 19, 2008 Permit status: Inspections | Completion date: February 17, 2009 | Current use: Commercial | Permit id: Bld2008-04424 | |||||
SCORE 66 Fire sprinkler modifications for 2nd flr remodel. Date: January 27, 2010 Permit type: Fire | Permit status: Closed | Completion date: April 19, 2010 | Current use: Commercial | Permit id: Bld2010-00391 | |||||
SCORE 79 Plumbing for complete floor remodel of 2nd level, fixture grand total 2, grand total of fixture units 7 and 1 floor drain. Date: February 10, 2010 Permit type: Plumbing | Permit status: Closed | Completion date: May 27, 2010 | Current use: Commercial | Permit id: Bld2010-00699 | |||||
SCORE 79 Mechanical for a complete floor remodel of 2nd level, 1 air handlers up to 10,0 cfms. Date: February 10, 2010 Permit type: Mechanical | Permit status: Closed | Completion date: March 24, 2010 | Current use: Commercial | Permit id: Bld2010-00700 | |||||
SCORE 56 Elec work for 2nd flr remodel Date: February 5, 2010 Permit type: Electrical | Permit status: Closed | Completion date: April 14, 2010 | Current use: Commercial | Permit id: Bld2010-00593 | |||||
Complete floor remodel of 2nd level. D-1 zone d. D. Zone: k. B. Credit card has been declined. No further inspections until permit has been paid for in full. Date: February 8, 2010 Permit type: Mechanical | Permit status: Closed | Completion date: May 7, 2013 | Current use: Commercial | Permit id: Bld2010-00608 | |||||
SCORE 56 Complete floor remodel of 2nd level. D-1 zone d. D. Zone, k. B. Date: January 5, 2010 Permit status: Closed | Completion date: April 16, 2010 | Current use: Commercial | Permit id: Bld2010-00036 | |||||
SCORE 66 7th floor remodel Date: December 19, 2008 Permit type: Permit | Permit status: Completed | Completion date: February 17, 2009 | Current use: Commercial | Permit id: Bld2008-04424 | |||||
SCORE 99 Plumbing Date: May 20, 2008 Contractor: Building Permit status: Completed | Completion date: June 1, 2010 | Current use: Commercial | Permit id: Bld2008-8052003 | |||||
SCORE 99 Plumbing Date: May 20, 2008 Contractor: Building Permit status: Closed | Completion date: June 1, 2010 | Current use: Commercial | Permit id: Bld2008-8052003 | |||||
SCORE 66 7th floor remodel Date: December 19, 2008 Permit status: Inspections | Completion date: February 17, 2009 | Current use: Commercial | Permit id: Bld2008-04424 | |||||
SCORE 64 Demo of east wing Date: July 23, 2009 Permit status: Inspections | Completion date: July 23, 2009 | Current use: Commercial | Permit id: Bld2009-04342 | |||||
SCORE 59 Complete floor remodel of 2nd level. D-1 zone d. D. Zone, k. B. Date: January 5, 2010 Permit status: Closed | Completion date: April 16, 2010 | Current use: Commercial | Permit id: Bld2010-00036 | |||||
SCORE 66 Fire sprinkler modifications for 2nd flr remodel. Date: January 27, 2010 Permit type: Fire | Permit status: Closed | Completion date: April 19, 2010 | Current use: Commercial | Permit id: Bld2010-00391 | |||||
SCORE 59 Elec work for 2nd flr remodel Date: February 5, 2010 Permit type: Electrical | Permit status: Closed | Completion date: April 14, 2010 | Current use: Commercial | Permit id: Bld2010-00593 | |||||
SCORE 59 Complete floor remodel of 2nd level. D-1 zone d. D. Zone: k. B. Credit card has been declined. No further inspections until permit has been paid for in full. Date: February 8, 2010 Permit type: Mechanical | Permit status: Closed | Completion date: May 7, 2013 | Current use: Commercial | Permit id: Bld2010-00608 | |||||
SCORE 79 Plumbing for complete floor remodel of 2nd level, fixture grand total 2, grand total of fixture units 7 and 1 floor drain. Date: February 10, 2010 Permit type: Plumbing | Permit status: Closed | Completion date: May 27, 2010 | Current use: Commercial | Permit id: Bld2010-00699 | |||||
SCORE 79 Mechanical for a complete floor remodel of 2nd level, 1 air handlers up to 10,0 cfms. Date: February 10, 2010 Permit type: Mechanical | Permit status: Closed | Completion date: March 24, 2010 | Current use: Commercial | Permit id: Bld2010-00700 | |||||
SCORE 99 Plumbing Date: May 20, 2008 Contractor: Building Permit status: Closed | Completion date: June 1, 2010 | Current use: Commercial | Permit id: Bld2008-8052003 | |||||
SCORE 66 Interior only, non structural demo of office space. No new work excepet capping off elec, mech, & plmb. Drawings are for reference only, new work will be submitted in 4-6 weeks. Tmb ah 05 19 2010 Date: May 19, 2010 Permit status: Closed | Completion date: April 1, 2013 | Current use: Commercial | Permit id: Bld2010-03251 | |||||
SCORE 59 Replacing existing hollow metal doors and frames and add 2 coiling doors. Door types, sizes and harware remains the same. (maintenance replacement) g. S. D-1 zone, interior to doors. A. S. Date: June 29, 2010 Permit status: Closed | Completion date: September 17, 2010 | Current use: Commercial | Permit id: Bld2010-04368 | |||||
SCORE 64 Elec work for cob fire door project Date: July 9, 2010 Permit type: Electrical | Permit status: Closed | Completion date: September 16, 2010 | Current use: Commercial | Permit id: Bld2010-04658 | |||||
SCORE 59 Install 36 vav fan coil units for interior remodel - 13th Date: July 21, 2010 Contractor: Aj Sheet Metal Inclds Church Office Building Permit type: Mechanical | Permit status: Closed | Completion date: April 1, 2013 | Current use: Commercial | Permit id: Bld2010-04976 | |||||
SCORE 66 Fire sprinkler modifications for 13th floor interior remodel. Date: July 22, 2010 Permit type: Fire | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05000 | |||||
SCORE 64 Elec work for 13th flr remodel Date: July 28, 2010 Permit type: Electrical | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05084 | |||||
SCORE 66 13th floor interior remodel. Fixture grand total 2, grand total of fixture units 5 and 1 floor drains. Date: August 11, 2010 Permit type: Plumbing | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-05451 | |||||
SCORE 64 Fire alarm system for the 13th floor interior remodel. Date: August 24, 2010 Permit type: Fire | Permit status: Closed | Completion date: May 17, 2011 | Current use: Commercial | Permit id: Bld2010-05777 | |||||
SCORE 64 Low voltage fire alarm system. Date: August 24, 2010 Permit type: Low voltage | Permit status: Closed | Completion date: March 31, 2011 | Current use: Commercial | Permit id: Bld2010-05778 | |||||
SCORE 66 Ductwork misc. Work for 13th floor interior remodel Date: September 7, 2010 Permit type: Mechanical | Permit status: Closed | Completion date: January 11, 2011 | Current use: Commercial | Permit id: Bld2010-06108 | |||||
SCORE 69 Fire sprinkler system. Food court block 75 building 4 Date: January 24, 2011 Permit type: Low voltage | Permit status: Inspections | Completion date: March 9, 2011 | Current use: Commercial | Permit id: Bld2011-00487 | |||||
SCORE 64 Interior space finished out requires pendent heads to be dropped to protect new space and ceiling layout. (existing heads are pendent style and are located in 1" outlets using bushings) Date: February 1, 2011 Permit type: Fire | Permit status: Inspections | Completion date: March 21, 2011 | Current use: Commercial | Permit id: Bld2011-00623 | |||||
SCORE 69 Site modifications for the placement of bollards on private property 07 12 2011 Date: July 12, 2011 Permit status: Closed | Completion date: March 15, 2013 | Current use: Commercial | Permit id: Bld2011-04263 | |||||
SCORE 77 Fire sprinkler system. Module 3 Date: August 16, 2011 Contractor: Firetrol Protection Systemssalt Lake Temple Permit type: Fire | Permit status: Closed | Completion date: August 13, 2012 | Current use: Commercial | Permit id: Bld2011-05147 | |||||
SCORE 64 Fire door and overhead door upgrades Date: September 27, 2011 Contractor: Crc Construction Incchurch Office Bldg Permit status: Closed | Completion date: February 9, 2012 | Current use: Commercial | Permit id: Bld2011-06201 | |||||
SCORE 86 Temp structure, annual church function Date: October 6, 2011 Contractor: Diamond Rentallds Church Main Office Permit type: Temporary use | Permit status: Closed | Completion date: October 6, 2011 | Permit id: Bld2011-06453 | |||||
SCORE 64 Electrical rough in for door modifications Date: November 14, 2011 Permit type: Electrical | Permit status: Closed | Completion date: November 14, 2011 | Current use: Commercial | Permit id: Bld2011-07479 | |||||
SCORE 77 Fire sprinkler system. Module 3 Date: January 25, 2012 Contractor: Firetrol Protection Systemssalt Lake Temple Permit type: Fire | Permit status: Closed | Completion date: February 3, 2012 | Current use: Commercial | Permit id: Bld2012-00667 | |||||
SCORE 59 Installing an addressable system in the temple proper and annex bldg. Devices will be replaced 1 for 1 in 95% of the building. This will not be a full upgrade at this time, but will accomodate for coverage based on the existing system. Date: August 6, 2012 Contractor: Simplexgrinnell Slc 456slc Lds Temple Permit type: Low voltage | Permit status: Closed | Completion date: February 25, 2013 | Current use: Commercial | Permit id: Bld2012-05726 | |||||
SCORE 66 Interior non-structural demolition, fire proofing will be included in the scope of this permit d. D. A. H. Date: October 19, 2012 Permit status: Inspections | Completion date: October 19, 2012 | Current use: Commercial | Permit id: Bld2012-07761 | |||||
SCORE 59 Interior remodel of 14th floor d. D. A. H. D. W. Date: October 19, 2012 Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-07762 | |||||
SCORE 64 Fire alarm for 14th remodel Date: December 7, 2012 Contractor: Simplexgrinnell Lplds Office Bldg 14th Remodel Permit type: Low voltage | Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-08988 | |||||
SCORE 61 14th floor to receive fire sprinkler system. We will begin our work after the control valve and flow switch that is currently installed. Date: December 13, 2012 Contractor: Lds Church Office Bldg 14th Floor Remodel Permit type: Fire | Permit status: Inspections | Completion date: December 27, 2012 | Current use: Commercial | Permit id: Bld2012-09111 | |||||
SCORE 66 Interior remodel of the church office building 14th floor. Gc permit #bld2012-07762 Date: December 26, 2012 Contractor: Copper Mountain Electriccob 14th Floor Remodel Permit type: Electrical | Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2012-09321 | |||||
SCORE 61 Replacement of duct work and terminal units entire floor Date: December 28, 2012 Permit type: Mechanical | Permit status: Inspections | Completion date: December 28, 2012 | Current use: Commercial | Permit id: Bld2012-09350 | |||||
SCORE 64 Various piping for new fixtures at church office bldg. Date: January 4, 2013 Contractor: Reliable Plumbing And Heating14th Floor Remodel Permit type: Plumbing | Permit status: Closed | Completion date: March 4, 2013 | Current use: Commercial | Permit id: Bld2013-00076 | |||||
SCORE 59 Lds church office building - 14th floor vault & vault ante room fm-2 fire suppression system with controls for pre-action fire sprinkler system (pre-action sprinkler system is furnished and installed by others) Date: February 12, 2013 Permit type: Fire | Permit status: Closed | Completion date: March 8, 2013 | Current use: Commercial | Permit id: Bld2013-00771 | |||||
SCORE 59 Renovation of the existing cafeteria & dining areas to include renovated salad bar area and soup bar; also upgrading floor & wall finishes. Date: February 21, 2013 Permit status: Closed | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-00978 | |||||
SCORE 59 Lds church intends to remodel the three main stairwells to the church office building tower: center stairwell, north east stairwell and north west stairwell. This is a voluntary seismic upgrade including an aesthetic refresh to the finish materials in the stairwells. Scope of work includes the main level up to the 28th and 29th floors. No work in the lower parking stairwells will be completed. No work in the east wing or west wing stairwells will be completed at this time. Intent is for the construction of this project to be phased. A detailed description of the construction phasing is included within the the design criteria. Date: March 1, 2013 Permit status: Inspections | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2013-01195 | |||||
SCORE 66 Fire sprinklers nob publishing services Date: May 30, 2013 Permit type: Fire | Permit status: Closed | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-03533 | |||||
SCORE 59 Int tenant improvement, mech elec plmbg permits reqd k. A. Int remodel only a. H. D. W. Date: June 20, 2013 Permit status: Closed | Completion date: May 30, 2014 | Current use: Commercial | Permit id: Bld2013-04165 | |||||
SCORE 64 Detection for rooms to be added to existing preaction system. Date: July 1, 2013 Contractor: Simplexgrinnell Lplds Nob Preaction Addition Permit type: Low voltage | Permit status: Closed | Completion date: August 2, 2013 | Current use: Commercial | Permit id: Bld2013-04502 | |||||
SCORE 66 Church office building east wing remodel of 4 floors Date: August 22, 2013 Contractor: Wasatch Electriccob East Wing Remodel Permit type: Electrical | Permit status: Closed | Completion date: March 28, 2014 | Current use: Commercial | Permit id: Bld2013-06002 | |||||
SCORE 66 Adding sprinklers to levels 1-4 in the east wing of the church office building. Floor control valve assemblies already exist and we are attaching to them and running the sprinkler system out. Date: August 30, 2013 Contractor: Lds Cob East Wing Remodel Permit type: Fire | Permit status: Closed | Completion date: May 29, 2014 | Current use: Commercial | Permit id: Bld2013-06275 | |||||
SCORE 66 Plumbing remodel Date: September 12, 2013 Permit type: Plumbing | Permit status: Closed | Completion date: March 24, 2014 | Current use: Commercial | Permit id: Bld2013-06648 | |||||
SCORE 64 Hvac sheet metal Date: October 18, 2013 Contractor: Rm Chris Sheet Metalcob East Wing Permit type: Mechanical | Permit status: Closed | Completion date: May 29, 2014 | Current use: Commercial | Permit id: Bld2013-07691 | |||||
SCORE 64 Remodel of the east wing of the church office building. Floors include levels 4, 3, 2, 1, ll1, ll2, and ll3. Floors 1, ll1, ll2, and ll3 will connect to the ll1 east transponder. Floors 4, 3, and 2 will connect to the 3rd floor east transponder. Date: October 23, 2013 Contractor: Simplexgrinnelllds Cob East Wing Remodel Permit type: Low voltage | Permit status: Closed | Completion date: March 28, 2014 | Current use: Commercial | Permit id: Bld2013-07805 | |||||
SCORE 64 Install ahu, coils, pumps, and fan coil units Date: October 28, 2013 Permit type: Mechanical | Permit status: Closed | Completion date: March 31, 2014 | Current use: Commercial | Permit id: Bld2013-07968 | |||||
SCORE 64 We will prepare the existing roof to receive the new system by removing the existing epdm membrane. We will be installing tapered foam crickets around the outside between drains and a 1 4" hard board will be installed. We will be installing a light grey s-327 mil pvc single-ply membrane, manufactured by sarnafil. This system will be attached using rhino bond adhered mechanically fastening system. Date: April 22, 2014 Permit type: Roofing | Permit status: Closed | Completion date: May 13, 2014 | Current use: Commercial | Permit id: Bld2014-02647 | |||||
SCORE 79 Fire sprinklers (clean agent) Date: April 23, 2014 Contractor: Fire Engineering Company Incchurch Office Bldg Permit type: Fire | Permit status: Closed | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2014-02688 | |||||
SCORE 79 Low voltage alarm (clean agent) Date: April 24, 2014 Contractor: Fire Engineering Company Incchurch Office Bldg Permit type: Low voltage | Permit status: Closed | Completion date: August 7, 2014 | Current use: Commercial | Permit id: Bld2014-02698 | |||||
SCORE 59 Complete interior remodel of the 23rd floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: July 7, 2014 Permit status: Closed | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2014-04780 | |||||
SCORE 64 Replace existing ups system Date: July 11, 2014 Permit type: Electrical | Permit status: Closed | Completion date: August 25, 2014 | Current use: Commercial | Permit id: Bld2014-04922 | |||||
SCORE 59 Splits are charged for both heating and cooling. Install 1. 5 ton unitary split system Date: July 18, 2014 Permit type: Mechanical | Permit status: Closed | Completion date: August 25, 2014 | Current use: Commercial | Permit id: Bld2014-05135 | |||||
SCORE 64 Remodel of entire floor. Use all new equipment and tie to existing transponder in electrical room. Mount new nac panel in closet located in store room 2301 to run strobe circuits, run speaker circuits to the existing transponder. Damper shutdown relays are to be located in each of the electrical rooms. The east electrical room will close the east dampers and the west electrical room will close the west dampers. Duct detectors will be mounted within 5 of each damper. The initiating circuit will run back to the existing transponder, the circuit is m9. Won-door controller is located in the east electrical room and connect to the transponder from there. Date: September 9, 2014 Contractor: Simplexgrinnelllds Cob 23rd Floor Remodel Permit type: Low voltage | Permit status: Closed | Completion date: February 10, 2015 | Current use: Commercial | Permit id: Bld2014-06524 | |||||
SCORE 59 Complete interior remodel of the 24th floor of the lds church office building. Non-structural. Add new automatic fire sprinkler system per nfpa 13, and new fire alarm and detection system per ibc 907. 3. Add new ada compliant single-user restroom. Replace existing drinking fountains with new ada compliant electric water coolers. Date: September 11, 2014 Permit status: Inspections | Completion date: November 20, 2014 | Current use: Commercial | Permit id: Bld2014-06620 | |||||
SCORE 66 Fire sprinklers for the 23rd floor Date: September 22, 2014 Permit type: Fire | Permit status: Closed | Completion date: January 23, 2015 | Current use: Commercial | Permit id: Bld2014-06879 | |||||
SCORE 66 Tenant improvement of 23rd floor gc permit big-d bld2014-04780 Date: September 26, 2014 Permit type: Electrical | Permit status: Closed | Completion date: February 2, 2015 | Current use: Commercial | Permit id: Bld2014-07022 | |||||
SCORE 59 Hvac remodel of 23 floor Date: October 1, 2014 Permit type: Mechanical | Permit status: Closed | Completion date: February 12, 2015 | Current use: Commercial | Permit id: Bld2014-07147 | |||||
SCORE 66 Remodel of the 23rd floor at the church office building Date: October 24, 2014 Permit type: Plumbing | Permit status: Closed | Completion date: February 3, 2015 | Current use: Commercial | Permit id: Bld2014-07790 | |||||
SCORE 64 This is a complete remodel of the 24th floor of the church office building. A new nac panel will be installed to control the new strobes and the existing speaker circuit will be used to run the new speakers. New duct detectors will be installed as well as all equipment that makes up the fire alarm for this floor. Date: November 17, 2014 Contractor: Simplexgrinnell Lplds Cob 24th Floor Permit type: Low voltage | Permit status: Closed | Completion date: March 31, 2015 | Current use: Commercial | Permit id: Bld2014-08454 | |||||
SCORE 66 Fire sprinkler system Date: December 2, 2014 Permit type: Fire | Permit status: Inspections | Completion date: December 22, 2014 | Current use: Commercial | Permit id: Bld2014-08834 | |||||
SCORE 66 Elec work for tenant improvement on 24th floor of lds church office building big-d general permit #bld2014-06620 Date: December 8, 2014 Contractor: Copper Mountain Electriclds Cob 24th Floor Permit type: Electrical | Permit status: Closed | Completion date: April 3, 2015 | Current use: Commercial | Permit id: Bld2014-08943 | |||||
SCORE 64 Project is to add notification appliances in the corridors of the annex and sl temple structures. Date: December 22, 2014 Contractor: Simplexgrinnell Lpsl Temple Corridor Upgrade Permit type: Low voltage | Permit status: Closed | Completion date: February 11, 2015 | Current use: Commercial | Permit id: Bld2014-09340 | |||||
SCORE 64 1-lav, 1-water closet, 1-drain bathroom remodel Date: December 23, 2014 Contractor: Reliable Plumbing And Heating Inccob 24th Floor Permit type: Plumbing | Permit status: Closed | Completion date: April 16, 2015 | Current use: Commercial | Permit id: Bld2014-09371 | |||||
SCORE 100 Interior remodel Date: December 31, 2014 Contractor: Okland Construction Co Permit status: Closed | Completion date: February 23, 2015 | Current use: Commercial | Permit id: Bld2014-09469 | |||||
SCORE 59 Remodel the 24th floor of the church office building Date: January 7, 2015 Permit type: Mechanical | Permit status: Inspections | Completion date: January 7, 2015 | Current use: Commercial | Permit id: Bld2015-00101 | |||||
SCORE 64 Plan review approved for permit issuance. Please arrange to pay the balance due. Fire suppression Date: January 21, 2015 Permit type: Fire | Permit status: Inspections | Completion date: February 10, 2015 | Current use: Commercial | Permit id: Bld2015-00441 | |||||
SCORE 64 Low voltage Date: February 3, 2015 Permit type: Fire | Permit status: Closed | Completion date: March 17, 2015 | Current use: Commercial | Permit id: Bld2015-00740 | |||||
SCORE 59 Non-structural remodel converting portions of existing cafeteria seating area, office area, and storage room into a new health unit Date: July 29, 2015 Permit status: Inspections | Completion date: October 19, 2015 | Current use: Commercial | Permit id: Bld2015-05914 | |||||
SCORE 59 Ductwork over 1,0 one exhaust fan, 19 vav boxes Date: June 22, 2012 Permit type: Mechanical | Permit status: Inspections | Completion date: June 22, 2012 | Current use: Commercial | Permit id: Bld2012-04574 | |||||
SCORE 64 Minimum commercial electrical. Cafeteria remodel Date: July 17, 2013 Contractor: Great Salt Lake Electric Incorporatedlds Church Permit type: Electrical | Permit status: Closed | Completion date: August 1, 2013 | Current use: Commercial | Permit id: Bld2013-04984 |