Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Replacement hood system day spring Date: December 10, 2008 Contractor: Fire Stop Technologies Client: Richard Putnam,Putnam Lp | Applicant: Fire Stop Technologies | Permit type: Fire | Permit status: Cmp | Completion date: January 5, 2009 | Current use: Religious assem | |||||
SCORE 96 Wire new ansul system. Date: December 12, 2008 Contractor: Electricians Inc Of Boulder Client: Richard Putnam,Putnam Lp | Applicant: Electricians Inc Of Boulder | Permit type: Electrical | Permit status: Cmp | Completion date: December 30, 2008 | Current use: Multifamily dwe | |||||
SCORE 95 Interior non-structural demolition for further structural investigation. Date: August 6, 2009 Contractor: Deneuve Construction Services Client: Richard Putnam,Putnam Lp | Applicant: Deneuve Construction Services | Permit type: Demolition | Permit status: Cmp | Completion date: October 26, 2012 | Current use: Multifamily dwe | |||||
SCORE 100 Temporary construction power. Date: August 12, 2009 Contractor: Pullenwire Inc Client: Richard Putnam,Putnam Lp | Applicant: Pullen-Wire, Inc. | Permit type: Electrical | Permit status: Cmp | Completion date: August 27, 2009 | Current use: Multifamily dwe | |||||
SCORE 95 Structural exterior demolition of walls & floor plate 42 sf with interior nonstructural demolition of 80 and probable removal of entire roof. (see case note) Date: September 11, 2009 Contractor: Deneuve Construction Services Client: Richard Putnam,Putnam Lp | Applicant: Deneuve Construction Services | Permit type: Demolition | Permit status: Cmp | Completion date: October 26, 2012 | Current use: Multifamily dwe | |||||
SCORE 95 Partial demolition and conversion of existing fraternity house. Resulting in 11 student apartments with 37 bedrooms and 17,759 square feet. See lur2009-00029 for prior approvals. Gates and walls through separate permit. Client: Richard Putnam,Putnam Lp | Applicant: Deneuve Construction Services | Permit type: Building, electrical | Permit status: Co | Current use: Multifamily dwe | |||||
SCORE 95 Construction of a a cmu block wall, cmu trash enclosure w metal gate, and installation of a metal fencing at 985 16th. Date: October 12, 2009 Contractor: Deneuve Construction Services Client: Richard Putnam,Putnam Lp | Applicant: Deneuve Construction Services | Permit type: Fence | Permit status: Cmp | Completion date: August 15, 2014 | Current use: Multifamily dwe | |||||
SCORE 97 Reroute existing 4inch fireline within property boundary. Install 1 & 1 45 and kickers Date: October 22, 2009 Contractor: Deneuve Design Inc Client: Boulder 985.0 | Applicant: Deneuve Design, Inc | Permit type: Fire, water, right-o | Permit status: Iss | |||||
SCORE 95 Tap install new 6inch sanitary sewer service from main in euclid, abandon existing 4inch service at main in alley. Tap install new 2inch domestic water service and 3 4inch irrigation service in 16th. (see pmt2009-03676 for fees and meters) Date: November 18, 2009 Contractor: Randy Kneebone Excavatingtrucking Client: Boulder 985.0 | Applicant: Randy Kneebone Excavating-Trucking | Permit type: Water, wastewater, r | Permit status: Iss | |||||
SCORE 97 Temporary placement of (2) roll-off dumpsters in the row, north side of site along euclid Date: January 15, 2010 Contractor: Deneuve Design Inc Client: Boulder 985.0 | Applicant: Deneuve Design, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 New fire alarm system for new apartments Date: January 13, 2010 Contractor: Surelock Plus Llc Client: Boulder 985.0 | Applicant: Surelock Plus, Llc | Permit type: Fire | Permit status: Cmp | Completion date: August 17, 2010 | Current use: Multifamily dwe | |||||
SCORE 100 New sprinkler system for multi-family dwelling Date: February 9, 2010 Contractor: Safety Systems Llc Client: Boulder 985.0 | Applicant: Safety Systems, Llc | Permit type: Fire | Permit status: Cmp | Completion date: August 17, 2010 | Current use: Multifamily dwe | |||||
SCORE 100 Install new pad mount transformer. Set new pole, remove old pole & trench in new primary Date: March 4, 2010 Contractor: Xcel Energy Client: Boulder 985.0 | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Renew gas service to building Date: May 11, 2010 Contractor: Xcel Energy Client: Boulder 985.0 | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Trench 5foot between old & new pole to intercept buried cable & attach to new pole Date: May 25, 2010 Contractor: Qwest Comm Centurylink Client: Boulder 985.0 | Applicant: Qwest Comm/centurylink | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Temporary crane set-up in row to hoist const. Matfootl to upper levels - sidewalk closure reqfootd Date: June 10, 2010 Contractor: Deneuve Construction Services Client: Boulder 985.0 | Applicant: Deneuve Construction Services | Permit type: Right-of-way | Permit status: N&v | |||||
SCORE 95 New radio dialer for student housing Date: July 1, 2010 Contractor: Surelock Plus Llc Client: Boulder 985.0 | Applicant: Surelock Plus Llc | Permit type: Fire | Permit status: Iss | Current use: Multifamily dwe | |||||
SCORE 100 Temporary construction power. Date: August 12, 2009 Contractor: Pullenwire, Inc Client: Richard Putnam | Permit type: Electrical | Permit status: Cmp | Completion date: August 27, 2009 | Current use: Multifamily dwellings, existing | Permit id: Pmt2009-03176 | |||||
SCORE 95 Partial demolition and conversion of existing fraternity house. Resulting in 11 student apartments with 37 bedrooms and 17,759 square feet. See lur2009-00029 for prior approvals. Gates and walls through separate permit. Client: Richard Putnam | Permit type: Building, electrical, mechanical, plumbing, water, wastewater, sitework | Permit status: Co | Current use: Multifamily dwellings, existing, garage | Permit id: Pmt2009-03676 | |||||
SCORE 95 Construction of a a cmu block wall, cmu trash enclosure w metal gate, and installation of a metal fencing at 985 16th. Client: Richard Putnam | Permit type: Fence | Permit status: Cmp | Completion date: August 15, 2014 | Current use: Multifamily dwellings, existing | Permit id: Pmt2009-03684 | |||||
SCORE 100 Reroute existing 4inch fireline within property boundary. Install 1 & 1 45 and kickers Date: October 22, 2009 Contractor: Deneuve Design, Inc Client: Boulder | Permit type: Fire, water, right-of-way | Permit status: Iss | Permit id: Pmt2009-04244 | |||||
SCORE 100 Temporary placement of (2) roll-off dumpsters in the row, north side of site along euclid Date: January 15, 2010 Contractor: Deneuve Design, Inc Client: Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-00086 | |||||
SCORE 95 New fire alarm system for new apartments Client: Boulder | Permit type: Fire | Permit status: Cmp | Completion date: August 17, 2010 | Current use: Multifamily dwellings, existing | Permit id: Pmt2010-00113 | |||||
SCORE 99 New sprinkler system for multi-family dwelling Client: Boulder | Permit type: Fire | Permit status: Cmp | Completion date: August 17, 2010 | Current use: Multifamily dwellings, existing | Permit id: Pmt2010-00481 | |||||
Install new pad mount transformer. Set new pole, remove old pole & trench in new primary Date: March 4, 2010 Client: Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-00733 | |||||
Renew gas service to building Date: May 11, 2010 Client: Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-01740 | |||||
Trench 5foot between old & new pole to intercept buried cable & attach to new pole Date: May 25, 2010 Client: Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-01948 | |||||
SCORE 95 New radio dialer for student housing Client: Boulder | Permit type: Fire | Permit status: Iss | Current use: Multifamily dwellings, existing | Permit id: Pmt2010-02645 | |||||
SCORE 96 Wire new ansul system. Client: Richard Putnam | Permit type: Electrical | Permit status: Cmp | Completion date: December 30, 2008 | Current use: Multifamily dwellings, existing | Permit id: Pmt2008-05387 | |||||
SCORE 95 Replacement hood system day spring Client: Richard Putnam | Permit type: Fire | Permit status: Cmp | Completion date: January 5, 2009 | Current use: Religious assembly, existing | Permit id: Pmt2008-05330 | |||||
SCORE 95 Temporary crane set-up in row to hoist const. Matfootl to upper levels - sidewalk closure reqfootd Contractor: Deneuve Construction Services Client: Boulder | Permit type: Right-of-way | Permit status: N&v | Permit id: Pmt2010-02301 |