Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 62 Install 2 underground fire lines & 2 fire hydrants Date: July 30, 2008 Contractor: Sage Excavation, L.L.C Permit type: Fire | Permit status: Closed | Current use: Commercial | Permit id: Bld2008-00647 | |||||
SCORE 59 Install 25 plumbing fixtures (54 fu), 3 water heaters, 28 drains, 2 hose bibbs, 1 backflow preventors. Date: August 6, 2008 Contractor: Kelley Plumbing And Heating Services, Inc Permit type: Plumbing | Permit status: Closed | Current use: Commercial | Permit id: Bld2008-00884 | |||||
Install fire sprinkler system Date: October 3, 2008 Permit type: Fire | Permit status: Closed | Current use: Commercial | Permit id: Bld2008-02377 | |||||
SCORE 82 Install fire sprinkler system Date: October 3, 2008 Contractor: Booth Fire Protection Inc Permit type: Fire | Permit status: Closed | Current use: Commercial | Permit id: Bld2008-02377 | |||||
SCORE 100 Low voltage fire alarm, utah paper box. Date: November 20, 2008 Contractor: R. C. Hunt Electric, Inc Permit type: Low voltage | Permit status: Closed | Current use: Commercial | Permit id: Bld2008-03882 | |||||
SCORE 100 New electrical valued @ 603812. 00 Date: December 3, 2008 Contractor: R. C. Hunt Electric, Inc Permit type: Electrical | Permit status: Closed | Current use: Commercial | Permit id: Bld2008-04112 | |||||
SCORE 100 Mechanical Date: December 4, 2008 Contractor: Gunthers Inc Permit status: Closed | Current use: Commercial | Permit id: Bld2008-04140 | |||||
SCORE 100 Power to panel Date: December 18, 2008 Contractor: R. C. Hunt Electric, Inc Permit type: Electrical | Permit status: Closed | Current use: Commercial | Permit id: Bld2008-04401 | |||||
SCORE 56 Landscaping valves 2 and backflow preventors 2. Date: March 23, 2009 Contractor: Bluco Services, Inc Permit type: Plumbing | Permit status: Closed | Current use: Commercial | Permit id: Bld2009-01757 | |||||
SCORE 82 Install new photovoltaic panel system on roof. Electrical permit required ka; m-1 zoning panels will not be taller than 3 6. Building is 22 in height ae Date: August 24, 2009 Contractor: Utah Solar And Alternative Energy Inc Permit status: Closed | Current use: Commercial | Permit id: Bld2009-05087 | |||||
SCORE 82 Elec work for new photovoltaic panel system on roof. Date: September 21, 2009 Contractor: Utah Solar And Alternative Energy Inc Permit type: Electrical | Permit status: Closed | Current use: Commercial | Permit id: Bld2009-05698 | |||||
SCORE 68 New office manufacturing bldg. Public way permit reqd. M-1 zone. No cert of occ to be issued until final plat has been recorded. Date: June 14, 2010 Contractor: Justin Case, Incorporated Permit status: Closed | Current use: Commercial | Permit id: Bld2010-03961 | |||||
SCORE 100 Fire Date: April 8, 2011 Contractor: Interwest Fire Protection Permit status: Closed | Current use: Commercial | Permit id: Bld2011-00621 | |||||
SCORE 89 Install 96 panel p. V. System on rooftop of commercial building roof structure to receive additional reinforcing as as included in permit package. Electrical permit also required. T. B. M-1 zone, below zones max height 65 a. S. Date: September 10, 2010 Contractor: Utah Solar And Alternative Energy Llc Permit status: Closed | Current use: Commercial | Permit id: Bld2010-06237 | |||||
SCORE 99 New 1 amp service from existing distribution for new panel Date: September 21, 2010 Contractor: Cazier Electric Co, Inc Permit type: Electrical | Permit status: Closed | Current use: Commercial | Permit id: Bld2010-06487 | |||||
SCORE 68 Site development (grading) only. L. L. Zone: a. H. Date: December 23, 2010 Contractor: Justin Case, Incorporated Permit type: Site development | Permit status: Closed | Permit id: Bld2010-08820 | |||||
SCORE 100 Elec work for new office manufacturing bldg Date: March 18, 2011 Contractor: R. C. Hunt Electric, Inc Permit type: Electrical | Permit status: Closed | Current use: Commercial | Permit id: Bld2011-01583 | |||||
SCORE 100 Power to panel agreement on file Date: March 18, 2011 Contractor: R. C. Hunt Electric, Inc Permit type: Electrical | Permit status: Closed | Current use: Commercial | Permit id: Bld2011-01588 | |||||
SCORE 100 Install 62 plumbing fixtures, 3 water heaters, 35 drains Date: March 24, 2011 Contractor: Cci Mechanical Inc Permit type: Plumbing | Permit status: Closed | Current use: Commercial | Permit id: Bld2011-01729 | |||||
SCORE 100 Install ton rtu, 1 unit heater, 24 vav boxes, 7 radiant heaters, 3 condnsing units, exhaust fans, 1 furnace, & 2 server room, ac units. Date: July 18, 2012 Contractor: Cci Mechanical Inc Permit type: Mechanical | Permit status: Closed | Current use: Commercial | Permit id: Bld2011-01731 | |||||
SCORE 59 Install sand and grease interceptor, sampling manhole, and sewer lateral Date: October 17, 2011 Contractor: Sage Excavation Permit type: Plumbing | Permit status: Closed | Current use: Commercial | Permit id: Bld2011-06700 | |||||
SCORE 100 Solar voltaic panels on commercial bldg d. D. M-1 zone, pv system on roof of structure, bldg per bld2010-03961, less than 90% coverage of this bldg, less than max pv system height a. S. D. W. Date: May 14, 2012 Contractor: R. C. Hunt Electric, Inc Permit status: Closed | Current use: Commercial | Permit id: Bld2012-03488 | |||||
SCORE 100 Accessory building Date: April 2, 2014 Contractor: R. C. Hunt Electric, Inc Permit status: Closed | Current use: Commercial | Permit id: Bld2014-02102 | |||||
SCORE 100 Electrical Date: April 2, 2014 Contractor: R. C. Hunt Electric, Inc Permit status: Closed | Current use: Commercial | Permit id: Bld2014-02103 | |||||
SCORE 95 Solarpv Date: July 25, 2014 Contractor: Intermountain Wind And Solar Permit status: Closed | Current use: Commercial | Permit id: Bld2014-04502 | |||||
SCORE 100 Date: May 14, 2012 Contractor: Na Permit id: Bld2012-03488 | |||||
SCORE 100 Date: April 2, 2014 Contractor: Na Permit id: Bld2014-02102 | |||||
SCORE 100 Date: April 2, 2014 Contractor: Na Permit id: Bld2014-02103 | |||||
SCORE 100 Date: July 25, 2014 Contractor: Na Permit id: Bld2014-04502 |