Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Remodel to exisitng communication services Applicant Phone: (512) 327-5599 | Permit type: Building permit | Permit status: Final | Completion date: June 22, 2007 | Expiration date: June 22, 2007 | Permit id: 2007-122454 Bp | |||||
SCORE 100 Remodel to exisitng communication services Date: May 25, 2007 Contractor: Swinerton Builders Inc Permit type: Electrical permit | Permit status: Final | Completion date: June 21, 2007 | Expiration date: December 19, 2007 | Permit id: 2007-122454 Ep | |||||
SCORE 99 Elect equipment hook up for data center Date: April 19, 2007 Contractor: Robert Schmidt Permit type: Electrical permit | Permit status: Void | Expiration date: November 14, 2007 | Permit id: 2007-115285 Ep | |||||
SCORE 99 Add 30 amp secondary elec service to data centerms2 only Date: June 15, 2007 Contractor: Robert Schmidt Permit type: Electrical permit | Permit status: Final | Completion date: June 18, 2007 | Expiration date: June 18, 2007 | Permit id: 2007-129573 Ep | |||||
SCORE 100 Change of use from warehousemanufacturing to communication services and remodelpmo area phase 1c Permit type: Mechanical permit | Permit status: Final | Completion date: April 23, 2007 | Expiration date: April 23, 2007 | Permit id: 2007-004263 Mp | |||||
SCORE 100 Change of use from warehousemanufacturing to communication services and remodeldata room phase 1b Permit type: Plumbing permit | Permit status: Final | Completion date: April 19, 2007 | Expiration date: April 19, 2007 | Permit id: 2007-004262 Pp | |||||
SCORE 100 Change of use from warehousemanufacturing to communication services and remodelcommand center office phase 1a Permit type: Mechanical permit | Permit status: Final | Completion date: April 3, 2007 | Expiration date: October 15, 2007 | Permit id: 2007-002043 Mp | |||||
SCORE 99 Install secondary metering coa transformers only Permit type: Electrical permit | Permit status: Final | Completion date: June 22, 2005 | Expiration date: June 22, 2005 | Permit id: 2005-016407 Ep | |||||
SCORE 100 Interior exterior remodel to communication service officewarehouse Permit type: Building permit | Permit status: Void | Expiration date: March 15, 2008 | Permit id: 2007-003792 Bp | |||||
SCORE 99 Install secondary metering coa transformers only Permit type: Electrical permit | Permit status: Final | Completion date: June 22, 2005 | Expiration date: June 22, 2005 | Permit id: 2005-016407 Ep | |||||
SCORE 99 Elect equipment hook up for data center Date: April 19, 2007 Contractor: Robert Schmidt Permit type: Electrical permit | Permit status: Void | Expiration date: November 14, 2007 | Permit id: 2007-115285 Ep | |||||
SCORE 99 Add 30 amp secondary elec service to data centerms2 only Date: June 15, 2007 Contractor: Robert Schmidt Permit type: Electrical permit | Permit status: Final | Completion date: June 18, 2007 | Expiration date: June 18, 2007 | Permit id: 2007-129573 Ep | |||||
SCORE 74 Interior remodel and addition of exterior stair ramp Applicant Phone: (512) 476-8886 | Permit type: Building permit | Permit status: Final | Completion date: September 26, 2008 | Expiration date: September 26, 2008 | Permit id: 2008-024625 Bp | |||||
SCORE 99 Interior remodel and addition of exterior stair ramp Date: September 8, 2008 Contractor: Robert Schmidt Permit type: Electrical permit | Permit status: Final | Completion date: September 19, 2008 | Expiration date: September 19, 2008 | Permit id: 2008-024625 Ep | |||||
SCORE 74 Interior remodel and addition of exterior stair ramp Applicant Phone: (512) 476-8886 | Permit type: Building permit | Permit status: Final | Completion date: September 26, 2008 | Expiration date: September 26, 2008 | Permit id: 2008-024625 Bp | |||||
SCORE 99 Interior remodel and addition of exterior stair ramp Date: September 8, 2008 Contractor: Robert Schmidt Permit type: Electrical permit | Permit status: Final | Completion date: September 19, 2008 | Expiration date: September 19, 2008 | Permit id: 2008-024625 Ep | |||||
SCORE 100 Change out hvac to existing commercial bldg only Date: March 10, 2014 Contractor: Charles Paxton Permit type: Mechanical permit | Permit status: Final | Completion date: March 20, 2014 | Expiration date: March 20, 2014 | Permit id: 2014-023425 Mp | |||||
SCORE 99 Install secondary metering coa transformers only Permit type: Electrical permit | Permit status: Final | Completion date: June 22, 2005 | Expiration date: June 22, 2005 | Permit id: 2005-012295 Ep | |||||
SCORE 100 Interior remodel to existing warehouse manufacturing to create storage area Applicant Phone: (210) 541-0651 | Permit type: Building permit | Permit status: Final | Completion date: November 21, 2012 | Expiration date: November 21, 2012 | Permit id: 2012-094712 Bp | |||||
SCORE 100 Interior remodel to existing warehouse manufacturing to create storage area Date: September 19, 2012 Contractor: Vincent Real Permit type: Electrical permit | Permit status: Final | Completion date: September 21, 2012 | Expiration date: September 21, 2012 | Permit id: 2012-094712 Ep | |||||
SCORE 100 Change out hvac to existing commercial bldg only Date: March 10, 2014 Contractor: Chuck Paxton Permit type: Mechanical permit | Permit status: Final | Completion date: March 20, 2014 | Expiration date: March 20, 2014 | Permit id: 2014-023425 Mp | |||||
SCORE 100 Interior remodel to existing warehouse manufacturing to create storage area Applicant Phone: (210) 541-0651 | Permit type: Building permit | Permit status: Final | Completion date: November 21, 2012 | Expiration date: November 21, 2012 | Permit id: 2012-094712 Bp | |||||
SCORE 99 Install secondary metering coa transformers only Permit type: Electrical permit | Permit status: Final | Completion date: June 22, 2005 | Expiration date: June 22, 2005 | Permit id: 2005-012295 Ep | |||||
SCORE 100 Adding circuit for down draft detector Date: April 25, 2014 Contractor: Gary Fraser Permit type: Electrical permit | Permit status: Final | Completion date: June 3, 2014 | Expiration date: June 3, 2014 | Permit id: 2014-042781 Ep | |||||
SCORE 100 Test and repair existing lp gas line to existing commercial only Date: October 22, 2015 Contractor: Richard Hilderbrand Permit type: Plumbing permit | Permit status: Final | Completion date: November 4, 2015 | Expiration date: November 4, 2015 | Permit id: 2015-128351 Pp | |||||
SCORE 99 Install secondary metering coa transformers only Permit type: Electrical permit | Permit status: Final | Completion date: June 22, 2005 | Expiration date: June 22, 2005 | Permit id: 2005-012294 Ep | |||||
SCORE 100 Adding circuit for down draft detector Date: April 25, 2014 Contractor: Gary Fraser Permit type: Electrical permit | Permit status: Final | Completion date: June 3, 2014 | Expiration date: June 3, 2014 | Permit id: 2014-042781 Ep | |||||
SCORE 99 Install secondary metering coa transformers only Permit type: Electrical permit | Permit status: Final | Completion date: June 22, 2005 | Expiration date: June 22, 2005 | Permit id: 2005-012294 Ep | |||||
SCORE 100 Install generator and enclosure to existing data center Applicant Phone: (651) 643-6553 | Permit type: Building permit | Permit status: Final | Completion date: November 9, 2015 | Expiration date: November 9, 2015 | Permit id: 2014-099589 Bp | |||||
SCORE 100 Install generator and enclosure to existing data center Date: November 3, 2014 Contractor: Mike Kanetzky Permit type: Electrical permit | Permit status: Final | Completion date: February 10, 2015 | Expiration date: February 10, 2015 | Permit id: 2014-099589 Ep | |||||
New shell officewarehouse Date: October 11, 1996 Value: $3,000,000 Permit type: Mechanical permit | Permit status: Final | Completion date: August 15, 1997 | Expiration date: August 15, 1997 | Permit id: 1996-014727 Mp | |||||
Tenant finish for dell computer Date: January 10, 1997 Value: $15,000,000 Permit type: Mechanical permit | Permit status: Final | Completion date: August 15, 1997 | Expiration date: August 15, 1997 | Permit id: 1997-005302 Mp | |||||
Electric conver for hook up Date: January 23, 1997 Value: $200,000 Permit type: Mechanical permit | Permit status: Final | Completion date: March 14, 1997 | Expiration date: August 29, 2007 | Permit id: 1997-011629 Mp | |||||
Install compactor trash bailer equipment Date: March 10, 1997 Value: $2,500 Permit type: Mechanical permit | Permit status: Final | Completion date: August 19, 1997 | Expiration date: August 29, 2007 | Permit id: 1997-002898 Mp | |||||
SCORE 99 Flood lights for exst sign only Permit type: Electrical permit | Permit status: Final | Completion date: January 23, 2003 | Expiration date: January 23, 2003 | Permit id: 2002-003552 Ep | |||||
Revision to new shell officewarehouse Date: November 1, 1996 Value: $800,000 Permit type: Building permit | Permit status: Final | Completion date: August 15, 1997 | Expiration date: August 15, 1997 | Permit id: 1996-018021 Bp | |||||
SCORE 100 Install generator and enclosure to existing data center Date: November 3, 2014 Contractor: Mike E Kanetzky Permit type: Electrical permit | Permit status: Final | Completion date: February 10, 2015 | Expiration date: February 10, 2015 | Permit id: 2014-099589 Ep | |||||
SCORE 100 Install generator and enclosure to existing data center Date: November 3, 2014 Contractor: Mike E Kanetzky Permit type: Electrical permit | Permit status: Final | Completion date: February 10, 2015 | Expiration date: February 10, 2015 | Permit id: 2014-099589 Ep | |||||
SCORE 100 Change of use from manufacturing to warehouse and remodel Permit type: Mechanical permit | Permit status: Final | Completion date: April 29, 2005 | Expiration date: April 29, 2005 | Permit id: 2005-022857 Mp | |||||
SCORE 100 Interior non structural demo only Permit type: Building permit | Permit status: Void | Expiration date: July 8, 2007 | Permit id: 2007-000884 Bp |