685 sq. Ft. Garage conversion, adding stairs Date: October 20, 2014 Value: $65,951 Permit type: Building : 43 - res | Permit status: Permit issued | Permit id: Pds2014-Resalt- | |||||
2 amp electrical panel change out for (e) sfd. Date: September 18, 2014 Permit type: Electrical : 80 - ac | Permit status: Permit finaled | Completion date: October 13, 2014 | Permit id: Pds2014-Resalt- | |||||
SCORE 86 10 10 2014 plan change. Electrical only. See c of a... Ss 09-11-14 plan change: decrease msp from 400amp to 200amp... See coa tlh the scope of work is limited to upgrade of the existing main service panel. No new sub-panels or relocation permitted. Per section 46 (i) of the zoning ordinance, roof mounted photovoltaic systems shall not extend more than 5 ft. Above the highest point of the existing roof. Date: July 22, 2014 Contractor: Timothy J Molek Permit type: Electrical : 8002 - | Permit status: Permit finaled | Completion date: October 16, 2014 | Permit id: Pds2014-Resalt- | |||||
Roof mount residential solar pv for existing sfd with existing residential main electrical service upgrade - 400a - 10/10/2014 plan change. Electrical only. See c of a... Ss 09-11-14 plan change decrease msp from 400amp to 200amp... See coa tlh the scope of work is limited to upgrade of the existing main service panel. No new sub-panels or relocation permitted. Per section 46 (i) of the zoning ordinance, roof mounted photovoltaic systems shall not extend more than 5 ft. Above the highest point of the existing roof. Date: July 22, 2014 Permit type: Residential alteration-addn | Permit status: Completed | Completion date: October 16, 2014 | Permit id: Pds2014-Resalt- | |||||
685 sq. Ft. Garage conversion, adding stairs, 128 sf temp. Storage container () 10-20-15 plan change added 128 sf temp. Storage container... See coa tlh 10-15-15 renewed at 25%. Must have valid inspection within each 1 days to keep permit active... Cag Date: October 20, 2014 Value: $72,483 Permit type: Residential alteration-addn | Permit status: Completed | Completion date: February 4, 2016 | Permit id: Pds2014-Resalt- | |||||
SCORE 91 2 amp electrical panel change out for (e) sfd. Date: September 18, 2014 Contractor: Arce Builders Inc Permit type: Residential alteration-addn | Permit status: Completed | Completion date: October 13, 2014 | Permit id: Pds2014-Resalt- | |||||
SCORE 93 Roof mount residential solar pv for existing sfd with existing residential main electrical service upgrade - 400a - 10 10 2014 plan change. Electrical only. See c of a... Ss 09-11-14 plan change decrease msp from 400amp to 200amp... See coa tlh the scope of work is limited to upgrade of the existing main service panel. No new sub-panels or relocation permitted. Per section 46 (i) of the zoning ordinance, roof mounted photovoltaic systems shall not extend more than 5 ft. Above the highest point of the existing roof. Date: July 22, 2014 Contractor: T And M Solar Inc Permit type: Residential alteration-addn | Permit status: Completed | Completion date: October 16, 2014 | Permit id: Pds2014-Resalt- | |||||
Final Date: February 2, 2016 Permit status: Pass | Permit id: Pds2014-Resalt- | |||||
Permit renewal Date: October 15, 2015 Permit status: Done | Permit id: Pds2014-Resalt- | |||||
Foundation/steel/holdowns/abs/1st Date: December 19, 2014 Permit status: Pass | Permit id: Pds2014-Resalt- |