Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 93 Change of use hotel Date: April 24, 2001 Contractor: Alex Modinger Client: Of Audubon,Llc, Carbone Prop. | Permit id: B01002139 | |||||
SCORE 93 Interior demolition retail store interior exterior demolition as hdlc #c1939 & sketch. Plans to change use to follow. Work shall not began with- out deq approval or a contractor. Date: April 24, 2001 Contractor: Alex Modinger Client: Of Audubon,Llc, Carbone Prop. | Permit id: B01002140 | |||||
SCORE 56 Interior demolition vacant commercial bldg. Interior demolitin of a vac. Commercial building as per plans. No exterior work allowed under this permit. Renovation plans to be submitted at a later date. Date: June 19, 2003 Contractor: Thomas Cloke Client: Of Audubon,Llc, Carbone Prop. | Permit id: B03003356 | |||||
SCORE 56 Interior demolition vacant commercial bldg. Supplemental permit to increase the cost & scope of work begun under permit b0 02140. No use & occupancy. Plans to foll ow for renovation. Date: June 20, 2003 Contractor: Carbone Properties Of Audubon Client: Of Audubon,Llc, Carbone Prop. | Permit id: B03003358 | |||||
SCORE 56 General repairs vacant commercial bldg. Installing plywood & stud framed wall @ ground floor strfront elevation 7-9" high steel scaffold system as per hdlc c of a #c2321. Scaffold erected 3 01 04. Date: February 11, 2004 Contractor: Terry Fraelich Client: Of Audubon,Llc, Carbone Prop. | Permit id: B04000848 |