Electrical Date: May 28, 2010 Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-20000-101 | |||||
SCORE 100 Hvac Date: December 19, 2011 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 11044-90000-148 | |||||
SCORE 60 Supplemental permit for installation of pre-fabricated movable/compact Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10001-178 | |||||
SCORE 67 Relocate a private fire hydrant due to building expansion. Date: October 3, 2012 Contractor: Don Becka Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-032 | |||||
SCORE 59 Plumbing Date: September 14, 2012 Contractor: Brandon Teston Permit status: Permit expired | Current use: Commercial | Permit id: 12042-20000-169 | |||||
Fire sprinkler installation. Add 1 head. Ware house. Date: October 11, 2012 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-033 | |||||
SCORE 100 Install new foundations for relocated machine tools Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-095 | |||||
Install new air handling units, gas heaters, and ventilation fans for Date: July 13, 2012 Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-041 | |||||
SCORE 62 Replace portion of existing storefront at second floor stairway with n Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-003 | |||||
Rerouting of supply for two story office space. All heads are existing Date: November 21, 2012 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-038 | |||||
SCORE 74 Electrical Date: December 19, 2012 Contractor: Gricelda Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-305 | |||||
SCORE 59 Demolish (e) 1-story manufacturing bldg (20,3 sqft) Permit type: Bldg-demolition | Permit status: Permit expired | Current use: Commercial | Permit id: 12019-20000-019 | |||||
Electrical Date: May 5, 2011 Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-20000-091 | |||||
SCORE 87 Electrical Date: December 15, 2011 Contractor: Howard Thomas Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-20000-266 | |||||
SCORE 100 Electrical Date: November 22, 2010 Contractor: Eric Cashman Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-232 | |||||
Fire sprinkler Date: February 7, 2012 Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-003 | |||||
SCORE 89 Electrical Date: September 28, 2012 Contractor: Daniel Gonzales Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-232 | |||||
SCORE 89 Tenant improvement for added office: add non-bearing partition and new Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-063 | |||||
SCORE 100 Tenant improvement for locker room & office renovation in manufacturin Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-086 | |||||
SCORE 100 Add steel frame work support for hoist & ground level of industrial bu Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-066 | |||||
SCORE 96 Electrical Date: July 5, 2011 Contractor: Wade Arnold Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-138 | |||||
SCORE 96 Electrical Date: June 5, 2012 Contractor: Wade Arnold Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-128 | |||||
SCORE 89 Fire sprinkler Date: April 4, 2011 Contractor: Frank J. Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-90000-008 | |||||
SCORE 56 Structural steel framing support attached to concrete waffle slab for Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-230 | |||||
SCORE 100 Plumbing Date: June 23, 2012 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-90000-114 | |||||
SCORE 100 Electrical Date: December 23, 2011 Contractor: Eric Cashman Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-273 | |||||
SCORE 56 Install runway beam extensions for existing overhead bridge crane (5 t Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-20000-135 | |||||
SCORE 92 Modifications to existing central utility plant to accommodate new fu Permit type: Nonbldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 12014-10000-018 | |||||
SCORE 100 Hvac Date: December 21, 2010 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-40001-103 | |||||
Install one (1) new cabled elevator (gen 2). Date: April 16, 2012 Permit type: Elevator | Permit status: Issued | Current use: Commercial | Permit id: 11046-10000-014 | |||||
SCORE 89 Fire sprinkler Date: July 29, 2011 Contractor: Frank J. Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-90000-018 | |||||
SCORE 87 Electrical Date: June 5, 2012 Contractor: Howard Thomas Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-130 | |||||
SCORE 56 Replace existing cabled electric elevator, "pratt & whitney rocketdyne Date: March 4, 2011 Contractor: Jvaughn Aubry Permit type: Elevator | Permit status: Permit finaled | Current use: Commercial | Permit id: 11046-10000-002 | |||||
Tenant improvment. Fire sprinkler installations. Add 13 heads. Product Date: June 22, 2012 Value: $9,850 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-020 | |||||
SCORE 95 Plumbing Date: September 22, 2011 Contractor: Carlos Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 11042-90000-168 | |||||
SCORE 63 Relocate (8. 92x18. 92) entrance canopy @ gate # 53/post #4 & new ramp Permit type: Bldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 11010-20000-008 | |||||
SCORE 100 Add one story (12 x 25. 5) patio cover (for charging station for electr Permit type: Bldg-addition | Permit status: Cofo issued | Current use: Commercial | Permit id: 12014-20000-007 | |||||
SCORE 100 Install (2) steel stands for mechanical equipment support Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 10016-20000-033 | |||||
SCORE 100 Electrical Date: November 1, 2012 Contractor: Eric Cashman Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-262 | |||||
SCORE 67 Modification to previously approved set of drawings to install a new s Date: August 21, 2012 Contractor: Anthony Dagestino Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10001-048 | |||||
SCORE 59 Ti on the ground floor: to creat new training room accessory to (e) of Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-226 | |||||
Voluntary seismic upgrade from (e) steel beams to conc shear wall conn Date: October 13, 2010 Value: $110,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-20000-141 | |||||
SCORE 100 Grading: excavation/backfill for new foundations of relocated machine Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 10030-10000-031 | |||||
SCORE 100 Plan check for power only. Replacement of two 600a panels and eight 0- Date: December 11, 2012 Contractor: Vrej Ratavousian Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20000-293 | |||||
SCORE 89 Electrical Date: March 31, 2011 Contractor: Mike Mortl Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-063 | |||||
SCORE 56 Sole purpose of this project is barrier removal. Adapting the shaft a Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11014-10000-029 | |||||
SCORE 92 Construct a new equipment canopy Permit type: Bldg-new | Permit status: Permit expired | Current use: Commercial | Permit id: 12010-10000-015 | |||||
SCORE 100 Electrical Date: March 8, 2011 Contractor: Mahmoud Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10001-184 | |||||
Sole purpose of this project is barrier removal. Adapting the shaft an Date: March 14, 2011 Value: $275,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-232 | |||||
Install one cabled electric elevators. Date: December 2, 2011 Permit type: Elevator | Permit status: Issued | Current use: Commercial | Permit id: 11046-10000-007 | |||||
SCORE 95 Hvac Date: December 19, 2012 Contractor: Carlos Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-90000-150 | |||||
SCORE 89 New 3000a and 1200a switchboards, new substation and loads for an exis Date: October 30, 2012 Contractor: Daniel Gonzales Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-178 | |||||
SCORE 59 Remove and recomption for the foundation of the additiion of the mezza Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 12030-10000-039 | |||||
SCORE 89 Electrical Date: December 13, 2010 Contractor: Mike Mortl Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-247 | |||||
SCORE 67 Remove (e) asphalt, install three (n) concrete pads & anchorage for (n Permit type: Nonbldg-new | Permit status: Cofo issued | Current use: Commercial | Permit id: 12020-10000-003 | |||||
Early start permit for interior demo of non-bearing office partitions, Date: September 7, 2012 Value: $45,000 Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-20000-170 | |||||
SCORE 100 Tenant improvement for manuf equip relocation - improve 1 room and rel Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-146 | |||||
SCORE 82 Elevator Date: April 4, 2011 Contractor: Samantha Reynolds Permit status: Issued | Current use: Commercial | Permit id: 11046-10000-004 | |||||
SCORE 100 Remodel existing 2nd floor conference room: relocate double doors and Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 10016-10000-214 | |||||
SCORE 100 Use of land to install one new ( 18-0" x 9-2" x 8-0") hazardous w Permit type: Nonbldg-new | Permit status: Cofo issued | Current use: Commercial | Permit id: 12020-10000-002 | |||||
SCORE 100 Add 7 heads @ new hvac duct. Light mfg. Date: January 9, 2012 Contractor: Frank Mone Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-000 | |||||
SCORE 89 Interior alteration to create new offices, changing room, locker room Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-240 | |||||
Commercial aerospace building. Office space/lab. Plan check for potabl Date: November 28, 2012 Value: $46,575 Permit type: Plumbing | Permit status: Issued | Current use: Commercial | Permit id: 12042-10000-216 | |||||
SCORE 100 Hvac Date: February 17, 2012 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-90000-017 | |||||
SCORE 59 Remodel of existing manufacturing space, construct new plating facilit Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 12016-10000-057 | |||||
SCORE 92 Tenant improvement to existing office, built out new non-bearing parti Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-178 | |||||
Install new domestic water, industrial cold water, medium pressure gas Date: October 22, 2012 Permit type: Plumbing | Permit status: Issued | Current use: Commercial | Permit id: 12042-10000-073 | |||||
SCORE 97 Electrical Date: January 28, 2010 Contractor: Wade Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-30000-015 | |||||
Install medium pressure gas line and reduce to low pressure for 4 kw Date: June 5, 2012 Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-045 | |||||
SCORE 100 Supplemental to permit # 12020-10000-00251 : to capture fire dpt. Cl Permit type: Nonbldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10001-002 | |||||
SCORE 88 Plumbing Date: September 6, 2011 Contractor: Andrew Macmillan Permit status: Permit finaled | Current use: Commercial | Permit id: 11042-90000-156 | |||||
SCORE 100 Installation of a pre-action system and a wet fire sprinkler system in Date: November 17, 2011 Contractor: Frank Mone Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-026 | |||||
Supplemental permit to include 6 1" x 19 6" pad footing for electric Date: July 11, 2012 Value: $4,000 Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10001-003 | |||||
SCORE 100 Tenant improvement for office reorganization; partitions, doors, susp. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-144 | |||||
SCORE 100 Install new plaster over existing facade construction as per architect Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-124 | |||||
SCORE 67 Plan check for new installation of 400kw fuel cell in building #106. I Date: June 5, 2012 Contractor: Anthony Dagestino Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-048 | |||||
SCORE 98 Electrical Date: July 28, 2011 Contractor: Chris Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-20000-158 | |||||
SCORE 65 New manufacturing building for jet parts. New 4160v, 3-phase, 2000a Date: October 9, 2012 Contractor: Danile Gonzalez Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-099 | |||||
SCORE 89 Fire sprinkler Date: June 8, 2010 Contractor: Frank J. Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-90000-011 | |||||
SCORE 56 Proposed new engineering development testing labratory facility (bldg Permit type: Bldg-new | Permit status: Issued | Current use: Commercial | Permit id: 12010-10000-007 | |||||
SCORE 89 Tenant improvements to replace existing demountable partitions with dr Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-188 | |||||
SCORE 93 Hvac Date: April 5, 2011 Contractor: Phil Roemer Permit status: Permit finaled | Current use: Commercial | Permit id: 11044-90000-036 | |||||
SCORE 61 Elevator Date: December 17, 2010 Contractor: Jvaughn Permit status: Issued | Current use: Commercial | Permit id: 10046-10000-012 | |||||
SCORE 89 T. I. Of one room inside (e) manufaturing building - new ceiling panels Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-031 | |||||
SCORE 67 Install 8" underground fire line for manufacturing building. Phase 2. Date: November 1, 2012 Contractor: Don Becka Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10001-032 | |||||
SCORE 56 Barrier romoval section 1134b. 3 (3. 1) and (3. 3). Adapting the shaft a Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-188 | |||||
SCORE 65 Temporary shoring for new engineering development testing labratory fa Permit type: Nonbldg-new | Permit status: Permit expired | Current use: Commercial | Permit id: 12020-10000-016 | |||||
SCORE 65 Grading for partial site prep & proposed new building per 12010-10000- Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 12030-10000-046 | |||||
SCORE 99 Electrical Date: June 16, 2010 Contractor: Ron Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-115 | |||||
SCORE 100 Electrical Date: April 4, 2011 Contractor: Mahmoud Fazlali Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-10000-066 | |||||
SCORE 93 Install 2" domestic potable water lines and one medium pressure gas li Date: November 6, 2012 Contractor: Stefan Owechko Permit type: Plumbing | Permit status: Permit expired | Current use: Commercial | Permit id: 12042-10000-203 | |||||
SCORE 89 Install new 1/2 ton jib crane inside existing manufacturing building. Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10000-013 | |||||
SCORE 100 Tenant improvement. Installation of (1) fire sprinkler and relocating Date: February 18, 2016 Contractor: Frank Mone Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-007 | |||||
SCORE 92 Proposed revisions to the permit 12010-10k-02299. Changing the scope o Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12010-10001-022 | |||||
SCORE 99 Install (3) fire sprinkler heads in manufacturing building #115 (foam Date: July 26, 2013 Contractor: Spencer Jones Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10001-013 | |||||
SCORE 96 Electrical Date: September 5, 2013 Contractor: Wade Arnold Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-242 | |||||
Revision to previously approved plans to provide notes on plan for siz Date: December 9, 2013 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10001-038 | |||||
SCORE 100 Fire sprinkler Date: January 31, 2014 Contractor: Anna Alpizar Permit status: Issued | Current use: Commercial | Permit id: 14043-90000-003 | |||||
SCORE 98 Hvac Date: December 23, 2013 Contractor: Patrick Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-20000-138 | |||||
SCORE 100 Electrical Date: January 14, 2013 Contractor: Eric Cashman Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-008 | |||||
Electrical Date: June 26, 2015 Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-40000-201 | |||||
Phase 1 remodel of existing building, new interior partitions, doors, Date: February 19, 2013 Value: $5,788,809 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-233 | |||||
SCORE 98 New concrete pad ( x ) for the installation of equipment i Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-166 | |||||
SCORE 89 Plan check for new industrial facility. Pratt whitney rocketdyne. Buil Date: July 25, 2013 Contractor: Daniel Gonzales Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-130 | |||||
Plan check for new sprinklers being aded to existing system for rocke Date: March 6, 2013 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-003 | |||||
SCORE 86 Hvac Date: August 7, 2015 Contractor: Andrea Koch Permit status: Issued | Current use: Commercial | Permit id: 15044-90000-080 | |||||
Construct 25 x x 18 tall --- steel building addition to building 1 Date: October 28, 2013 Value: $322,200 Permit type: Bldg-addition | Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-033 | |||||
SCORE 59 Installation of sewer line serving building 101 south. Sewer line in Date: February 6, 2014 Contractor: Stefan Owenchko Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-10000-023 | |||||
SCORE 98 Electrical Date: June 20, 2013 Contractor: Kevin Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-164 | |||||
Electrical Date: March 7, 2013 Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-060 | |||||
SCORE 61 New laboratory, with medium voltage substation, loads and lighting. ( Date: May 30, 2013 Contractor: Brian De Soto Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20000-297 | |||||
SCORE 100 Hvac Date: April 15, 2014 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-90000-034 | |||||
SCORE 93 Hvac Date: August 20, 2013 Contractor: Stefan Owechko Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10001-105 | |||||
SCORE 89 Electrical Date: September 27, 2013 Contractor: Daniel Gonzales Permit status: Permit finaled | Current use: Public safety only | Permit id: 13041-90000-269 | |||||
SCORE 88 Electrical Date: July 8, 2015 Contractor: Eilia Sitnitsky Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-215 | |||||
SCORE 84 Electrical Date: July 5, 2013 Contractor: Stephanie Lopez Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-172 | |||||
SCORE 96 Electrical Date: July 17, 2014 Contractor: Blanca Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-192 | |||||
SCORE 59 Proposed mat foundation (45x40) for equipments within existing manuf Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-256 | |||||
SCORE 89 For bldg. 106, modify existing suspended ceiling system by raising Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-265 | |||||
SCORE 89 Interior non-structural remodel in office building to change copy room Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 13016-10000-121 | |||||
SCORE 100 Addition of transformer and subpanel. Per applicant request, full pc. Date: September 3, 2013 Contractor: Vrej Ratavousian Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-213 | |||||
SCORE 96 New sprinkler system for an existing light manufacturing warehouse wit Date: November 7, 2013 Contractor: David Marquez Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-035 | |||||
SCORE 97 Foundation and anchorage for equipment pad Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-033 | |||||
SCORE 100 Hvac Date: September 26, 2013 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-90000-102 | |||||
SCORE 59 Supplemental permit to 12016-10000-05738 for structural change on cran Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10002-057 | |||||
SCORE 97 New steel structure frame within (e) building to support exhaust duct Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-140 | |||||
SCORE 97 Freestanding cmu fence wall Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 15020-20000-006 | |||||
SCORE 61 Electrical Date: May 9, 2013 Contractor: Martin Decker Permit status: Permit finaled | Current use: Special equipment | Permit id: 13041-90000-121 | |||||
SCORE 72 Propose site preparation for future three (3) retail buildings and fou Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 14030-10000-004 | |||||
SCORE 100 Electrical Date: March 9, 2016 Contractor: Mahmoud Fazlali Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-082 | |||||
SCORE 100 Electrical Date: February 15, 2016 Contractor: Eric Cashman Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-90000-052 | |||||
SCORE 97 Electrical Date: January 9, 2013 Contractor: Daniel Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-005 | |||||
SCORE 73 Electrical Date: December 20, 2013 Contractor: Jason Sztapka Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-355 | |||||
Electrical Date: February 11, 2014 Permit status: Permit finaled | Current use: Public safety only | Permit id: 14041-10000-037 | |||||
SCORE 96 Electrical Date: March 14, 2014 Contractor: Wade Arnold Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-90000-068 | |||||
SCORE 59 Installation of sewage pump syatem to serve pent booth and miraclean e Date: March 24, 2014 Contractor: Budi Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20001-246 | |||||
SCORE 93 T. I. Work in existing one story commercial bldg. Adding ahu, fume hood Date: April 8, 2013 Contractor: Stefan Owechko Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-147 | |||||
SCORE 95 Electrical Date: September 17, 2013 Contractor: Eric Rowe Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-255 | |||||
SCORE 65 Electrical Date: January 9, 2014 Contractor: Danile Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20001-099 | |||||
SCORE 100 Plan check for power. New large furnace infrastructure. Emergency ligh Date: March 12, 2015 Contractor: Vrej Ratavousian Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-047 | |||||
SCORE 65 Partially remove existing roof-top platform and provide new roof-top p Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-183 | |||||
SCORE 70 New 80" high x 120" long, prefabricated wall, per engineered plans. Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 15020-20000-035 | |||||
SCORE 72 Electrical Date: December 20, 2013 Contractor: Petros Balayan Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-355 | |||||
SCORE 96 Fire sprinkler Date: October 24, 2013 Contractor: Mike Ayers Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-90000-036 | |||||
SCORE 59 Suppelemental to 12016-10000-23369, new exterior double doors. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10001-233 | |||||
SCORE 73 Install equipments on ground & at (e)roof equipment platform. No chan Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-20000-207 | |||||
SCORE 70 Pressure vessel Date: June 10, 2015 Contractor: Leon Berg Permit status: Permit finaled | Current use: Commercial | Permit id: 15045-90000-001 | |||||
SCORE 99 Changes to approved set. Changes are clouded. Delta 1 changes only. Re Date: April 1, 2014 Contractor: Doug Elliot Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10002-130 | |||||
Voluntary upgrade of existing ground foor mens and womens sanitary f Date: January 11, 2013 Value: $7,000 Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10000-218 | |||||
SCORE 93 Pressure vessel Date: January 9, 2014 Contractor: Stefan Owechko Permit status: Permit finaled | Current use: Commercial | Permit id: 14045-10000-000 | |||||
Add 176" x 278" steel supported storage platform inside (e) manufact Date: November 20, 2013 Value: $50,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-20000-206 | |||||
SCORE 72 For bldg 101 only,pc for power and energy. New equipment >600a. Transf Date: January 2, 2014 Contractor: Petros Balayan Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-355 | |||||
Removal & recompaction to prepare site for construction of addition to Date: May 10, 2013 Value: $2,850 Permit type: Grading | Permit status: Issued | Current use: Commercial | Permit id: 13030-10000-008 | |||||
SCORE 92 Proposed pre-manufactured metal building for industrial process at ro Permit type: Bldg-new | Permit status: Issued | Current use: Commercial | Permit id: 12010-10000-021 | |||||
SCORE 59 Installation and anchorage of (1-) new mechanical equipment unit and r Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-170 | |||||
Mfg ti - add partition wall & opening and door for mechanical equipmen Date: August 2, 2013 Value: $125,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-20000-117 | |||||
SCORE 100 Electrical Date: June 12, 2013 Contractor: Stephanie Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-153 | |||||
SCORE 89 For bldg 101 only, non structural interior work, to create utility tre Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-258 | |||||
SCORE 100 Electrical Date: September 2, 2015 Contractor: Eric Cashman Permit status: Issued | Current use: Commercial | Permit id: 15041-90000-290 | |||||
Install temporary earth retention bulkhead for excavation of new found Date: January 8, 2013 Value: $125,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-242 | |||||
SCORE 59 Industrial building. Plan check for heating, venting, air conditionin Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-060 | |||||
SCORE 100 Hvac Date: August 31, 2015 Contractor: Alex Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-089 | |||||
Addition of 22799 sq. Ft. To building 101 on the rocketdyne campus: s Date: June 25, 2013 Value: $9,730,664 Permit type: Bldg-addition | Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-007 | |||||
SCORE 93 Installation of duplex sump pump system for commercial building. Date: April 17, 2014 Contractor: Stefan Owechko Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-10000-071 | |||||
Supplemental permit for the installation of new mechanical equipment s Date: January 31, 2014 Value: $55,000 Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 13014-10001-007 | |||||
Grading permit to remove and recompact 1 cu. Yd. For new 25 x x Date: October 28, 2013 Value: $170 Permit type: Grading | Permit status: Issued | Current use: Commercial | Permit id: 13030-10000-059 | |||||
SCORE 99 Installation of sprinkler within a sand-blasting booth Date: March 25, 2014 Contractor: Spencer Jones Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-010 | |||||
Revision to previously approved plans: add six new heads for obstructi Date: April 14, 2014 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10002-038 | |||||
SCORE 100 Electrical Date: May 30, 2014 Contractor: Rob Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-143 | |||||
SCORE 63 Construct a foundation pad and support for a 12-0" dia. X 23-2" high Permit type: Nonbldg-new | Permit status: Cofo issued | Current use: Commercial | Permit id: 13020-20000-012 | |||||
SCORE 99 Installation of (12) sprinkler heads in grid blaster buildng, connecti Date: February 6, 2014 Contractor: Spencer Jones Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-004 | |||||
SCORE 99 Update of existing wet pipe system, existing underground & backflow. Date: June 26, 2013 Contractor: Spencer Jones Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-014 | |||||
SCORE 67 Install equipment anchorage and tenant improvement to remove and const Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-138 | |||||
SCORE 93 Installation of (2) fume ehxaust fans serving foam booth and oven fume Date: January 22, 2013 Contractor: Stefan Owechko Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-105 | |||||
Electrical Date: January 28, 2016 Permit status: Issued | Current use: Commercial | Permit id: 16041-40000-032 | |||||
SCORE 67 Fire sprinkler installation. Manufacturing facility. 257 heads. 8" dc. Date: June 25, 2013 Contractor: Don Becka Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-004 | |||||
SCORE 59 Installation of new equipment Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-063 | |||||
SCORE 92 A proposed canopy and shallow containment pit structure for steam cle Permit type: Bldg-new | Permit status: Issued | Current use: Commercial | Permit id: 12010-10000-022 | |||||
SCORE 93 New plumbing for rehabilitation of foam filtration and processing equi Date: February 12, 2013 Contractor: Stefan Owechko Permit type: Plumbing | Permit status: Permit expired | Current use: Commercial | Permit id: 12042-10000-182 | |||||
SCORE 89 Electrical Date: July 20, 2015 Contractor: Steven Greene Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-230 | |||||
SCORE 100 Electrical Date: July 21, 2015 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-200 | |||||
SCORE 61 Electrical Date: July 24, 2013 Contractor: Milton Enriquez Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-164 | |||||
SCORE 86 Electrical Date: February 20, 2015 Contractor: Linda Sosa Permit status: Issued | Current use: Commercial | Permit id: 15041-40000-050 | |||||
SCORE 98 Install (n) equipment anchorage to (e) 5" thick concrete floor slab an Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-20000-013 | |||||
SCORE 99 Install (16) fire sprinkler heads in manufacturing building #115 (foam Date: April 23, 2013 Contractor: Spencer Jones Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-013 | |||||
SCORE 77 Electrical Date: June 3, 2016 Contractor: Dale Mirtle Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-194 | |||||
SCORE 97 T. I. To the existing conference room in the exist. Office bldg. (1,37 Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-20000-139 | |||||
SCORE 96 Electrical Date: July 6, 2016 Contractor: Mike Kuzian Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-211 | |||||
SCORE 86 Install one illuminated wall sign, 11-11" x 3-9" ht. " aerojet rocke Permit type: Sign | Permit status: Issued | Current use: Onsite | Permit id: 16048-20000-016 | |||||
SCORE 70 Plumbing Date: June 30, 2016 Contractor: Picone Company Permit status: Issued | Current use: Commercial | Permit id: 16042-10000-133 | |||||
SCORE 95 Electrical Date: February 11, 2014 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Public safety only | Permit id: 14041-10000-037 | |||||
SCORE 98 Revision to previously approved plans to provide notes on plan for siz Date: December 9, 2013 Contractor: Qualco Fire Protection Inc Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10001-038 | |||||
SCORE 93 Electrical Date: June 26, 2015 Contractor: Herzog M B Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-40000-201 | |||||
SCORE 98 Plan check for new sprinklers being aded to existing system for rocke Date: March 6, 2013 Contractor: Qualco Fire Protection Inc Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-003 | |||||
SCORE 100 Electrical Date: March 7, 2013 Contractor: H C I Systems Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-060 | |||||
SCORE 59 Electrical Date: August 23, 2016 Contractor: Vrej Ratevousian Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-263 | |||||
SCORE 95 Electrical Date: September 16, 2016 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-329 | |||||
SCORE 73 Add flush & steam clean pre- fabricated metal building to (e) manufac Permit type: Bldg-addition | Permit status: Issued | Current use: Commercial | Permit id: 16014-10000-016 | |||||
SCORE 93 Electrical Date: June 17, 2016 Contractor: Herzog M B Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-40000-214 | |||||
SCORE 97 Pressure vessel Date: September 12, 2016 Contractor: Mario Garcia Permit status: Permit finaled | Current use: Commercial | Permit id: 16045-90000-001 | |||||
New poles lights foundation Date: October 20, 2016 Value: $8,000 Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 16020-30000-031 | |||||
SCORE 67 Installation of new equipment on new foundation and new covered utilit Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-185 | |||||
SCORE 95 Electrical Date: October 12, 2016 Contractor: Seyed Yasreb Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-359 | |||||
SCORE 100 Electrical Date: October 20, 2016 Contractor: Michael Mamroth Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-373 | |||||
SCORE 98 Hvac Date: October 27, 2016 Contractor: Thermalair Inc Permit status: Issued | Current use: Commercial | Permit id: 16044-90000-124 | |||||
SCORE 96 Electrical Date: November 1, 2016 Contractor: Vrej Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-380 | |||||
SCORE 100 Electrical Date: October 27, 2016 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-20000-372 | |||||
SCORE 98 Excavation for pit & trench drain inside new pre-fab. Building . Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 16030-10000-035 | |||||
SCORE 59 Pressure vessel Date: December 19, 2016 Contractor: Boiler Dynamic Inc Permit status: Issued | Current use: Commercial | Permit id: 16045-10000-002 | |||||
SCORE 98 Hvac Date: August 31, 2015 Contractor: Meadows Mechanical Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-089 | |||||
SCORE 89 Voluntary upgrade of existing ground foor mens and womens sanitary f Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10000-218 | |||||
SCORE 76 Add 176" x 278" steel supported storage platform inside (e) manufact Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-20000-206 | |||||
SCORE 99 Plumbing Date: January 28, 2015 Contractor: Xcel Mechanical Systems Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15042-10000-018 | |||||
SCORE 86 Mfg ti - add partition wall & opening and door for mechanical equipmen Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-20000-117 | |||||
SCORE 80 Install temporary earth retention bulkhead for excavation of new found Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-242 | |||||
SCORE 98 Revision to previously approved plans: add six new heads for obstructi Date: April 14, 2014 Contractor: Qualco Fire Protection Inc Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10002-038 | |||||
SCORE 95 Fire sprinkler Date: May 10, 2013 Contractor: Cosco Fire Protection Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-015 | |||||
SCORE 84 Electrical Date: January 28, 2016 Contractor: Polaris Electric Co Inc Permit status: Issued | Current use: Commercial | Permit id: 16041-40000-032 | |||||
SCORE 97 Electrical Date: October 23, 2013 Contractor: Diversified Protection Systems Inc Permit status: Permit closed | Current use: Commercial | Permit id: 13041-10000-296 | |||||
SCORE 60 Electrical Date: January 14, 2014 Contractor: Big Sky Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20002-099 | |||||
SCORE 92 Grading permit to remove and recompact 1 cu. Yd. For new 25 x x Permit type: Grading | Permit status: Issued | Current use: Commercial | Permit id: 13030-10000-059 | |||||
SCORE 89 Electrical Date: October 20, 2016 Contractor: A1 Electric Service Company Inc Permit status: Issued | Current use: Commercial | Permit id: 16041-30000-372 | |||||
SCORE 89 Electrical Date: August 12, 2015 Contractor: A1 Electric Service Company Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-30000-262 | |||||
SCORE 92 Construct 25 x x 18 tall --- steel building addition to building 1 Permit type: Bldg-addition | Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-033 | |||||
SCORE 92 Phase 1 remodel of existing building, new interior partitions, doors, Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-233 | |||||
SCORE 100 Installation of new sprinkler system inside steam pit/test cell room s Date: June 13, 2016 Contractor: Frank Mone Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-021 | |||||
SCORE 95 Electrical Date: February 11, 2014 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Public safety only | Permit id: 14041-10000-037 | |||||
SCORE 95 Electrical Date: September 16, 2016 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-329 | |||||
SCORE 92 Supplemental permit for the installation of new mechanical equipment s Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 13014-10001-007 | |||||
SCORE 92 Addition of 22799 sq. Ft. To building 101 on the rocketdyne campus: s Permit type: Bldg-addition | Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-007 | |||||
SCORE 100 Plan check for the replacement of a 4160/480-277 15 kva substation t Date: July 23, 2015 Contractor: Vrej Ratavousian Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-232 | |||||
SCORE 92 Removal & recompaction to prepare site for construction of addition to Permit type: Grading | Permit status: Issued | Current use: Commercial | Permit id: 13030-10000-008 | |||||
SCORE 86 Install (1) illuminated channel letter wall sign (540" x 44-1/2") re Permit type: Sign | Permit status: Permit finaled | Current use: Onsite | Permit id: 15048-20000-013 | |||||
SCORE 99 Installation of shelving/cabinet within (e) commercial building (6 ma Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-023 | |||||
SCORE 97 Re configuration of glazing partitions per engineer details. Permit status: Issued | Current use: Commercial | Permit id: 17016-20000-299 | |||||
SCORE 97 Alter repair to (e) manufacting bldg - 1 of 3 Permit status: Issued | Current use: Commercial | Permit id: 17016-20000-292 | |||||
SCORE 100 Replacement of (7) existing recessed panels for facilities maintenance Date: November 14, 2017 Contractor: Vrej Ratavousian Permit status: Issued | Current use: Commercial | Permit id: 17041-20000-391 | |||||
SCORE 89 Date: March 6, 2017 Contractor: Steven Greene Permit status: Permit finaled | Current use: Commercial | Permit id: 17041-90000-071 | |||||
SCORE 100 Addition of new 225amp panel and 25kva transformer for welding equipme Date: October 17, 2017 Contractor: Vrej Ratavousian Permit status: Issued | Current use: Commercial | Permit id: 17041-20000-360 | |||||
SCORE 56 Addition of 12 amp section with no loads. Plan check for power only Date: September 8, 2017 Contractor: Brian Shelton Permit status: Permit finaled | Current use: Commercial | Permit id: 17041-20000-247 | |||||
SCORE 80 Date: December 4, 2017 Contractor: Robin Moyer Permit status: Permit finaled | Current use: Commercial | Permit id: 17043-90000-061 | |||||
SCORE 99 Non structural tenant improvement to (e) office Permit status: Permit finaled | Current use: Commercial | Permit id: 17016-20000-274 | |||||
SCORE 100 Tenant improvement. Installation of (1) fire sprinkler and relocating Date: February 18, 2016 Contractor: Frank Mone Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-007 | |||||
SCORE 98 Date: October 27, 2016 Contractor: Thermalair Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16044-90000-124 | |||||
SCORE 92 Proposed revisions to the permit 12010-10k-02299. Changing the scope o Permit status: Permit expired | Current use: Commercial | Permit id: 12010-10001-022 | |||||
SCORE 99 Install (3) fire sprinkler heads in manufacturing building #115 (foam Date: July 26, 2013 Contractor: Spencer Jones Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10001-013 | |||||
SCORE 89 Voluntary upgrade of existing ground foor mens and womens sanitary f Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10000-218 | |||||
SCORE 93 Date: January 9, 2014 Contractor: Stefan Owechko Permit status: Permit finaled | Current use: Commercial | Permit id: 14045-10000-000 | |||||
SCORE 76 Add 176" x 278" steel supported storage platform inside (e) manufact Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-20000-206 | |||||
SCORE 72 For bldg 101 only,pc for power and energy. New equipment >600a. Transf Date: January 2, 2014 Contractor: Petros Balayan Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-355 | |||||
SCORE 92 Proposed pre-manufactured metal building for industrial process at ro Permit status: Issued | Current use: Commercial | Permit id: 12010-10000-021 | |||||
SCORE 59 Installation and anchorage of (1-) new mechanical equipment unit and r Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-170 | |||||
SCORE 99 Date: January 28, 2015 Contractor: Xcel Mechanical Systems Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15042-10000-018 | |||||
SCORE 100 Date: June 24, 2013 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-90000-065 | |||||
SCORE 93 Date: August 20, 2013 Contractor: Stefan Owechko Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10001-060 | |||||
SCORE 86 Mfg ti - add partition wall & opening and door for mechanical equipmen Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-20000-117 | |||||
SCORE 100 Date: June 12, 2013 Contractor: Stephanie Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-153 | |||||
SCORE 99 Installation of shelving cabinet within (e) commercial building (6 ma Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-023 | |||||
SCORE 89 For bldg 101 only, non structural interior work, to create utility tre Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-258 | |||||
SCORE 86 Date: February 20, 2015 Contractor: Linda Sosa Permit status: Issued | Current use: Commercial | Permit id: 15041-40000-050 | |||||
SCORE 67 Installation of new equipment on new foundation and new covered utilit Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-185 | |||||
SCORE 96 Date: January 30, 2017 Contractor: Wade Arnold Permit status: Permit finaled | Current use: Commercial | Permit id: 17041-90000-029 | |||||
SCORE 95 Date: August 6, 2013 Contractor: Eric Rowe Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-209 | |||||
SCORE 93 Date: June 17, 2016 Contractor: Herzog M B Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-40000-214 | |||||
SCORE 84 Date: September 26, 2013 Contractor: Stephanie Lopez Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10001-172 | |||||
SCORE 89 Date: June 28, 2013 Contractor: Daniel Gonzales Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20001-130 | |||||
SCORE 80 Install temporary earth retention bulkhead for excavation of new found Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-242 | |||||
SCORE 59 Industrial building. Plan check for heating, venting, air conditionin Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-060 | |||||
SCORE 96 Date: November 1, 2016 Contractor: Vrej Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-20000-380 | |||||
SCORE 100 Date: August 31, 2015 Contractor: Alex Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-089 | |||||
SCORE 88 Date: July 8, 2015 Contractor: Eilia Sitnitsky Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-216 | |||||
SCORE 97 Date: September 12, 2016 Contractor: Mario Garcia Permit status: Permit finaled | Current use: Commercial | Permit id: 16045-90000-001 | |||||
SCORE 100 Date: January 3, 2014 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-90000-000 | |||||
SCORE 98 Date: December 23, 2013 Contractor: Patrick Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20000-246 | |||||
SCORE 92 Addition of 22799 sq. Ft. To building 101 on the rocketdyne campus: s Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-007 | |||||
SCORE 93 Installation of duplex sump pump system for commercial building. Date: April 17, 2014 Contractor: Stefan Owechko Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-10000-071 | |||||
SCORE 98 Install (n) equipment anchorage to (e) 5" thick concrete floor slab an Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-20000-013 | |||||
SCORE 59 Date: December 19, 2016 Contractor: Boiler Dynamic Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16045-10000-002 | |||||
SCORE 96 Date: July 6, 2016 Contractor: Mike Kuzian Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-20000-211 | |||||
SCORE 92 Supplemental permit for the installation of new mechanical equipment s Permit status: Permit expired | Current use: Commercial | Permit id: 13014-10001-007 | |||||
SCORE 96 Date: February 20, 2014 Contractor: Wade Arnold Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-90000-046 | |||||
SCORE 99 Installation of sprinkler within a sand-blasting booth Date: March 25, 2014 Contractor: Spencer Jones Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-010 | |||||
SCORE 98 Revision to previously approved plans: add six new heads for obstructi Date: April 14, 2014 Contractor: Qualco Fire Protection Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10002-038 | |||||
SCORE 100 Date: May 30, 2014 Contractor: Rob Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-143 | |||||
SCORE 100 Date: May 4, 2016 Contractor: Eric Cashman Permit status: Issued | Current use: Special equipment | Permit id: 16041-90000-156 | |||||
SCORE 63 Construct a foundation pad and support for a 12-0" dia. X 23-2" high Permit status: Cofo issued | Current use: Commercial | Permit id: 13020-20000-012 | |||||
SCORE 99 Installation of (12) sprinkler heads in grid blaster buildng, connecti Date: February 6, 2014 Contractor: Spencer Jones Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-004 | |||||
SCORE 95 Date: May 10, 2013 Contractor: Cosco Fire Protection Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-015 | |||||
SCORE 99 Update of existing wet pipe system, existing underground & backflow. Date: June 26, 2013 Contractor: Spencer Jones Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-014 | |||||
SCORE 67 Install equipment anchorage and tenant improvement to remove and const Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-138 | |||||
SCORE 93 Installation of (2) fume ehxaust fans serving foam booth and oven fume Date: January 22, 2013 Contractor: Stefan Owechko Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-105 | |||||
SCORE 77 Plan check for powwer only for addition of the builidng. Note: energy Date: February 13, 2017 Contractor: Dale Mirtle Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10001-194 | |||||
SCORE 84 Date: January 28, 2016 Contractor: Polaris Electric Co Inc Permit status: Issued | Current use: Commercial | Permit id: 16041-40000-032 | |||||
SCORE 67 Fire sprinkler installation. Manufacturing facility. 257 heads. 8" dc. Date: June 25, 2013 Contractor: Don Becka Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-004 | |||||
SCORE 86 Date: August 7, 2015 Contractor: Andrea Koch Permit status: Permit expired | Current use: Commercial | Permit id: 15044-90000-080 | |||||
SCORE 86 Install one illuminated wall sign, 11-11" x 3-9" ht. " aerojet rocke Permit status: Permit finaled | Current use: Onsite | Permit id: 16048-20000-016 | |||||
SCORE 97 Date: October 23, 2013 Contractor: Diversified Protection Systems Inc Permit status: Permit closed | Current use: Commercial | Permit id: 13041-10000-296 | |||||
SCORE 95 Date: March 29, 2017 Contractor: Carlos Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 17044-90000-034 | |||||
SCORE 60 Date: January 14, 2014 Contractor: Big Sky Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20002-099 | |||||
SCORE 92 A proposed canopy and shallow containment pit structure for steam cle Permit status: Issued | Current use: Commercial | Permit id: 12010-10000-022 | |||||
SCORE 93 New plumbing for rehabilitation of foam filtration and processing equi Date: February 12, 2013 Contractor: Stefan Owechko Permit status: Permit expired | Current use: Commercial | Permit id: 12042-10000-182 | |||||
New poles lights foundation Date: October 20, 2016 Value: $8,000 Permit status: Permit finaled | Current use: Commercial | Permit id: 16020-30000-031 | |||||
SCORE 73 Install equipments on ground & at (e)roof equipment platform. No chan Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-207 | |||||
SCORE 89 Date: July 20, 2015 Contractor: Steven Greene Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-230 | |||||
SCORE 77 Date: June 3, 2016 Contractor: Dale Mirtle Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-194 | |||||
SCORE 100 Date: July 21, 2015 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-200 | |||||
SCORE 61 Date: July 24, 2013 Contractor: Milton Enriquez Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-164 | |||||
SCORE 89 Date: August 12, 2015 Contractor: A1 Electric Service Company Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-30000-262 | |||||
SCORE 99 Install (16) fire sprinkler heads in manufacturing building #115 (foam Date: April 23, 2013 Contractor: Spencer Jones Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-013 | |||||
SCORE 100 Date: October 20, 2016 Contractor: Michael Mamroth Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-373 | |||||
SCORE 100 Plan check for power only per applicant request. Project site is an ex Date: January 31, 2017 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-20000-429 | |||||
SCORE 96 Date: September 5, 2013 Contractor: Wade Arnold Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-242 | |||||
SCORE 98 Revision to previously approved plans to provide notes on plan for siz Date: December 9, 2013 Contractor: Qualco Fire Protection Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10001-038 | |||||
SCORE 70 Date: June 30, 2016 Contractor: Picone Company Permit status: Permit finaled | Current use: Commercial | Permit id: 16042-10000-133 | |||||
SCORE 100 Date: January 31, 2014 Contractor: Anna Alpizar Permit status: Issued | Current use: Commercial | Permit id: 14043-90000-003 | |||||
SCORE 100 Date: January 14, 2013 Contractor: Eric Cashman Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-008 | |||||
SCORE 93 Date: June 26, 2015 Contractor: Herzog M B Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-40000-201 | |||||
SCORE 92 Phase 1 remodel of existing building, new interior partitions, doors, Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-233 | |||||
SCORE 98 New concrete pad ( x ) for the installation of equipment i Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-166 | |||||
SCORE 89 Plan check for new industrial facility. Pratt whitney rocketdyne. Buil Date: July 25, 2013 Contractor: Daniel Gonzales Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-130 | |||||
SCORE 98 Plan check for new sprinklers being aded to existing system for rocke Date: March 6, 2013 Contractor: Qualco Fire Protection Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-003 | |||||
SCORE 92 Construct 25 x x 18 tall --- steel building addition to building 1 Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-033 | |||||
SCORE 59 Installation of sewer line serving building 101 south. Sewer line in Date: February 6, 2014 Contractor: Stefan Owenchko Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-10000-023 | |||||
SCORE 98 Date: June 20, 2013 Contractor: Kevin Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-164 | |||||
SCORE 100 Date: March 7, 2013 Contractor: H C I Systems Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-060 | |||||
SCORE 61 New laboratory, with medium voltage substation, loads and lighting. ( Date: May 30, 2013 Contractor: Brian De Soto Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20000-297 | |||||
SCORE 100 Installation of new sprinkler system inside steam pit test cell room s Date: June 13, 2016 Contractor: Frank Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-021 | |||||
SCORE 95 Date: October 12, 2016 Contractor: Seyed Yasreb Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-20000-359 | |||||
SCORE 96 Date: July 17, 2014 Contractor: Blanca Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-192 | |||||
SCORE 100 Plan check for the replacement of a 4160 480-277 15 kva substation t Date: July 23, 2015 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-232 | |||||
SCORE 59 Proposed mat foundation (45x40) for equipments within existing manuf Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-256 | |||||
SCORE 93 Date: September 13, 2017 Contractor: Linda Bush Permit status: Permit finaled | Current use: Commercial | Permit id: 17041-90000-327 | |||||
SCORE 89 For bldg. 106, modify existing suspended ceiling system by raising Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-265 | |||||
SCORE 89 Interior non-structural remodel in office building to change copy room Permit status: Issued | Current use: Commercial | Permit id: 13016-10000-121 | |||||
SCORE 100 Addition of transformer and subpanel. Per applicant request, full pc. Date: September 3, 2013 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-213 | |||||
SCORE 96 New sprinkler system for an existing light manufacturing warehouse wit Date: November 7, 2013 Contractor: David Marquez Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-035 | |||||
SCORE 97 Foundation and anchorage for equipment pad Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-033 | |||||
SCORE 56 Date: January 18, 2017 Contractor: Sebastian Brundage Permit status: Issued | Current use: Commercial | Permit id: 17041-90000-016 | |||||
SCORE 59 Supplemental permit to 12016-10000-05738 for structural change on cran Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10002-057 | |||||
SCORE 97 New steel structure frame within (e) building to support exhaust duct Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-140 | |||||
SCORE 97 Freestanding cmu fence wall Permit status: Permit finaled | Current use: Commercial | Permit id: 15020-20000-006 | |||||
SCORE 61 Date: May 9, 2013 Contractor: Martin Decker Permit status: Permit finaled | Current use: Special equipment | Permit id: 13041-90000-121 | |||||
SCORE 73 Add flush & steam clean pre- fabricated metal building to (e) manufac Permit status: Cofo issued | Current use: Commercial | Permit id: 16014-10000-016 | |||||
SCORE 98 Date: August 31, 2015 Contractor: Meadows Mechanical Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-089 | |||||
SCORE 72 Propose site preparation for future three (3) retail buildings and fou Permit status: Permit finaled | Current use: Commercial | Permit id: 14030-10000-004 | |||||
SCORE 100 Date: March 9, 2016 Contractor: Mahmoud Fazlali Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-082 | |||||
SCORE 98 Excavation for pit & trench drain inside new pre-fab. Building . Permit status: Permit finaled | Current use: Commercial | Permit id: 16030-10000-035 | |||||
SCORE 97 Date: January 9, 2013 Contractor: Daniel Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-005 | |||||
SCORE 73 Date: December 20, 2013 Contractor: Jason Sztapka Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-355 | |||||
SCORE 73 Installation of (1) 30-0" and (2) 25-0" high flag poles. All work pe Permit status: Issued | Current use: Commercial | Permit id: 17020-20000-025 | |||||
SCORE 95 Date: February 11, 2014 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Public safety only | Permit id: 14041-10000-037 | |||||
SCORE 97 T. I. To the existing conference room in the exist. Office bldg. (1,37 Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-20000-139 | |||||
SCORE 59 Installation of new equipment Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-063 | |||||
SCORE 100 Date: September 2, 2015 Contractor: Eric Cashman Permit status: Permit expired | Current use: Commercial | Permit id: 15041-90000-290 | |||||
SCORE 95 Date: September 16, 2016 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-329 | |||||
SCORE 59 Installation of sewage pump syatem to serve pent booth and miraclean e Date: March 24, 2014 Contractor: Budi Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20001-246 | |||||
SCORE 93 T. I. Work in existing one story commercial bldg. Adding ahu, fume hood Date: April 8, 2013 Contractor: Stefan Owechko Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-147 | |||||
SCORE 89 Date: October 20, 2016 Contractor: A1 Electric Service Company Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-30000-372 | |||||
SCORE 92 Grading permit to remove and recompact 1 cu. Yd. For new 25 x x Permit status: Permit finaled | Current use: Commercial | Permit id: 13030-10000-059 | |||||
SCORE 65 Date: January 9, 2014 Contractor: Danile Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20001-099 | |||||
SCORE 100 Date: October 27, 2016 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-20000-372 | |||||
SCORE 100 Plan check for power. New large furnace infrastructure. Emergency ligh Date: March 12, 2015 Contractor: Vrej Ratavousian Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-047 | |||||
SCORE 65 Partially remove existing roof-top platform and provide new roof-top p Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-183 | |||||
SCORE 84 Date: August 23, 2017 Contractor: J E Snyder Electric Inc Permit status: Issued | Current use: Commercial | Permit id: 17041-20000-300 | |||||
SCORE 70 New 80" high x 120" long, prefabricated wall, per engineered plans. Permit status: Permit finaled | Current use: Commercial | Permit id: 15020-20000-035 | |||||
SCORE 59 Date: August 23, 2016 Contractor: Vrej Ratevousian Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-20000-263 | |||||
SCORE 72 Date: December 20, 2013 Contractor: Petros Balayan Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-20000-355 | |||||
SCORE 96 Date: October 24, 2013 Contractor: Mike Ayers Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-90000-036 | |||||
SCORE 92 Removal & recompaction to prepare site for construction of addition to Permit status: Permit finaled | Current use: Commercial | Permit id: 13030-10000-008 | |||||
SCORE 59 Suppelemental to 12016-10000-23369, new exterior double doors. Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10001-233 | |||||
SCORE 86 Install (1) illuminated channel letter wall sign (540" x 44-1 2") re Permit status: Permit finaled | Current use: Onsite | Permit id: 15048-20000-013 | |||||
SCORE 70 Date: June 10, 2015 Contractor: Leon Berg Permit status: Permit finaled | Current use: Commercial | Permit id: 15045-90000-001 | |||||
SCORE 99 Changes to approved set. Changes are clouded. Delta 1 changes only. Re Date: April 1, 2014 Contractor: Doug Elliot Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10002-130 |