Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Suppression permit Date: September 27, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 365292 | |||||
Plumbing permit Date: September 13, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 712062 | |||||
Alteration permit Date: January 15, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 126497 | |||||
Electrical permit Date: March 6, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 201277 | |||||
Fast form building permit Date: July 16, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 164711 | |||||
Use permit Date: May 2, 2016 Client: Arch Partners Lp | Permit status: Completed | Permit id: 686972 | |||||
Plumbing permit Date: March 5, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 203538 | |||||
Mechanical permit Date: September 10, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 166051 | |||||
Alteration permit Date: October 4, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 362095 | |||||
Electrical permit Date: September 15, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 714108 | |||||
Alteration permit Date: May 2, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 667820 | |||||
Mechanical permit Date: June 30, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 703459 | |||||
Electrical permit Date: April 24, 2013 Client: Arch Partners Lp | Permit status: Completed | Permit id: 466983 | |||||
Electrical permit Date: April 15, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 145489 | |||||
Mechanical permit Date: May 2, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 321348 | |||||
Zoning/use permit Date: April 23, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 206987 | |||||
Alteration permit Date: April 14, 2015 Client: Arch Partners Lp | Permit status: Active | Permit id: 593690 | |||||
Electrical permit Date: December 12, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 370594 | |||||
Suppression permit Date: August 30, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 718467 | |||||
Administrative permit Date: February 12, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 198497 | |||||
Administrative permit Date: August 30, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 715749 | |||||
Plumbing permit Date: May 18, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 405865 | |||||
Alteration permit Date: February 5, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 198673 | |||||
Electrical permit Date: October 9, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 431443 | |||||
Plumbing permit Date: October 14, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 368247 | |||||
Suppression permit Date: March 10, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 134709 | |||||
Plumbing permit Date: June 25, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 287604 | |||||
Zoning/use permit Date: July 24, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 163148 | |||||
Alteration permit Date: June 8, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 279356 | |||||
Sign permit Date: August 18, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 167532 | |||||
Administrative permit Date: October 21, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 171959 | |||||
Suppression permit Date: May 18, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 405967 | |||||
Electrical permit Date: December 28, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 318328 | |||||
Mechanical permit Date: July 23, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 286311 | |||||
Plumbing permit Date: November 7, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 187229 | |||||
Sign permit Date: May 8, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 211749 | |||||
Alteration permit Date: May 10, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 398548 | |||||
Fast form building permit Date: February 24, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 202375 | |||||
Suppression permit Date: June 16, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 284637 | |||||
Mechanical permit Date: April 7, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 203898 | |||||
Mechanical permit Date: November 14, 2014 Client: Arch Partners Lp | Permit status: Expired | Permit id: 568152 | |||||
Sign permit Date: August 18, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 167532 | |||||
Plumbing permit Date: November 7, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 187229 | |||||
Alteration permit Date: April 14, 2015 Client: Arch Partners Lp | Permit status: Completed | Permit id: 593690 | |||||
Electrical permit Date: August 25, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 168795 | |||||
Electrical permit Date: May 24, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 407127 | |||||
Alteration permit Date: June 27, 2016 Client: Arch Partners Lp | Permit status: Completed | Permit id: 702724 | |||||
Alteration permit Date: January 15, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 126497 | |||||
Electrical permit Date: December 28, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 318328 | |||||
Plumbing permit Date: March 5, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 203538 | |||||
Alteration permit Date: May 10, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 398548 | |||||
Mechanical permit Date: May 2, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 321348 | |||||
Electrical permit Date: September 9, 2016 Client: Arch Partners Lp | Permit status: Completed | Permit id: 695930 | |||||
Suppression permit Date: December 19, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 744518 | |||||
Electrical permit Date: September 29, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 365710 | |||||
Electrical permit Date: March 6, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 201277 | |||||
Zoning use permit Date: April 23, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 206987 | |||||
Zoning use permit Date: October 1, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 180106 | |||||
Suppression permit Date: September 27, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 365292 | |||||
Mechanical permit Date: February 26, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 130301 | |||||
Mechanical permit Date: November 14, 2014 Client: Arch Partners Lp | Permit status: Expired | Permit id: 568152 | |||||
Plumbing permit Date: August 25, 2016 Client: Arch Partners Lp | Permit status: Completed | Permit id: 701191 | |||||
Mechanical permit Date: July 23, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 286311 | |||||
Use permit Date: May 2, 2016 Client: Arch Partners Lp | Permit status: Completed | Permit id: 686972 | |||||
Alteration permit Date: June 8, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 279356 | |||||
Alteration permit Date: February 5, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 198673 | |||||
Mechanical permit Date: April 7, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 203898 | |||||
Mechanical permit Date: June 30, 2016 Client: Arch Partners Lp | Permit status: Active | Permit id: 695489 | |||||
Plumbing permit Date: June 25, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 287604 | |||||
Fast form building permit Date: September 30, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 178517 | |||||
Electrical permit Date: April 24, 2013 Client: Arch Partners Lp | Permit status: Completed | Permit id: 466983 | |||||
Suppression permit Date: March 10, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 134709 | |||||
Fast form building permit Date: February 24, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 202375 | |||||
Alteration permit Date: January 13, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 316683 | |||||
Suppression permit Date: May 18, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 405967 | |||||
Plumbing permit Date: May 18, 2012 Client: Arch Partners Lp | Permit status: Completed | Permit id: 405865 | |||||
Administrative permit Date: September 19, 2016 Client: Arch Partners Lp | Permit status: Completed | Permit id: 722907 | |||||
Suppression permit Date: June 16, 2010 Client: Arch Partners Lp | Permit status: Completed | Permit id: 284637 | |||||
Administrative permit Date: October 21, 2008 Client: Arch Partners Lp | Permit status: Completed | Permit id: 171959 | |||||
Sign permit Date: May 8, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 211749 | |||||
Administrative permit Date: February 12, 2009 Client: Arch Partners Lp | Permit status: Completed | Permit id: 198497 | |||||
Plumbing permit Date: October 14, 2011 Client: Arch Partners Lp | Permit status: Completed | Permit id: 368247 | |||||
SCORE 100 Amend building permit #6678 to change the occupancy classification from group b to group b with accessory i-3. Date: August 30, 2016 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Administrative permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 715749 | |||||
SCORE 86 Prescriptive alterations:interior plumbing;high-rise office building. Building; tenat fit out office space, gsa us dept of immigration,customs & enforcement; third floor - the installation will compy with the philadelphia plumbing code 2004 Date: September 13, 2016 Contractor: Churchville Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 712062 | |||||
SCORE 100 Installationo of fire suppressions system in third floor of existing building to tie into existing automatic fire suppression system in accordance with nfpa 13 as per approved plans. Date: September 20, 2016 Contractor: Fire Tech Automatic Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 714477 | |||||
SCORE 100 Relocate existing sprinkler heads to accomodate new layout-ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: August 12, 2016 Contractor: Fire Tech Automatic Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 714480 | |||||
Construction of elevator shaft 1st-3rd flrs and pit, foundation slab as per architectural & structural engineers plans. Date: April 14, 2015 Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: January 13, 2017 | Permit id: 593690 | |||||
Installation of new hvac system for 3rd floor office space within an existing building as per approved plans. Date: August 17, 2016 Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 13, 2017 | Permit id: 713402 | |||||
SCORE 100 Furnish and install 34 category 5e plenum cables, average cable pull feet as per 2008 nec (cc dist) office space Date: May 24, 2012 Contractor: Belles Electrical Contractors Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: August 28, 2012 | Permit id: 407127 | |||||
Three roof top hvac units and associated supply air riser duct and return air grills in hvac shafts to include fire dampers Date: February 26, 2008 Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 17, 2008 | Permit id: 130301 | |||||
SCORE 99 Replacement windows, no change to opening size Date: January 15, 2008 Contractor: Graboyes Commercial Window Co Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: October 2, 2008 | Permit id: 126497 | |||||
SCORE 85 Erection of a sign on 8th st. Side for drivers license center. Date: May 8, 2009 Contractor: Bartush Signs Inc Client: Arch Partners Lp | Permit type: Sign permit | Permit status: Completed | Completion date: July 14, 2009 | Permit id: 211749 | |||||
SCORE 100 Interior exterior alterations, 1st floor lobby & 3rd floor tenant fit out, partitions, furnishings, finishes, new office layout, ground level storefront facade work, as per plans. Change in use with no change on occupancy classficqtion. Existing office building, co on record, one attached to update. Addl permits req: meps. Date: May 2, 2016 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 667820 | |||||
SCORE 92 Furnish and install 2 plenum cat6 cabl3es, avg cable 1 feet, as per 2005 nec (cc dist) Date: February 17, 2009 Contractor: Donald Belles Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Expired | Completion date: February 17, 2009 | Permit id: 195019 | |||||
SCORE 100 Ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: December 19, 2016 Contractor: Fire Tech Automatic Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: April 11, 2017 | Permit id: 744518 | |||||
SCORE 86 Ez standard kitchen fire suppression- for the installation of new wet chemical kitchen hood fire suppression system as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: August 30, 2016 Contractor: J And S Fire Protection Inc Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: March 20, 2017 | Permit id: 718467 | |||||
SCORE 100 For temporary certificate of occupancy for 2nd and 6th floor only. Date: September 19, 2016 Contractor: Sullivan Company The Client: Arch Partners Lp | Permit type: Administrative permit | Permit status: Completed | Completion date: October 4, 2016 | Permit id: 722907 | |||||
SCORE 100 Level ii interior renovations to an existing governors office on the 5th floor only as per plans, separate permits required for m, e. P and fss, Date: October 27, 2016 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: January 13, 2017 | Permit id: 729230 | |||||
SCORE 100 Relocating ductwork in space reloaction ( grds in tenants space Date: October 31, 2016 Contractor: Edward B Oreilly And Assoc Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: March 20, 2017 | Permit id: 733118 | |||||
SCORE 100 Renovation of existing space. New lights and receptacles connected to existing panels per 2008 nec (office space)cc district Date: December 7, 2016 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Active | Completion date: June 23, 2017 | Permit id: 733683 | |||||
SCORE 100 Tenat fit out office space, gsa us dept of immigration,customs & enforcement. Date: May 2, 2016 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Use permit | Permit status: Completed | Completion date: May 2, 2016 | Permit id: 686972 | |||||
SCORE 100 For selective interior demolition and for prescriptive alterations to create new office spaces on the first, second, and sixth floors of an existing high-rise office building. Building shall be fully sprinklered. Separate permits shall be required for mechanical, electrical, plumbing, and fire suppression systems. All asbestos to be treated & removed prior to commencement of work. Date: May 25, 2016 Contractor: Sullivan Company The Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: March 10, 2017 | Permit id: 687497 | |||||
SCORE 84 Install ductwork. Date: November 3, 2008 Contractor: Costa And Rihl Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 14, 2009 | Permit id: 182763 | |||||
SCORE 91 Install fire alarm fm2 system and devices as per nfpa-72 (cc district) Date: November 7, 2008 Contractor: Adams Electrical Construction Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Expired | Completion date: November 7, 2008 | Permit id: 182972 | |||||
SCORE 100 192 light fixtures, 13 exits, 74 occupancy sensors, 1 receptacles, 6 vav boxes, furniture whips, 29 horn strobes, 2 pull stations as per 2005 nec & nfpa-72 (cc dist) Date: December 1, 2008 Contractor: Rtm Electrical Contractors Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Expired | Completion date: December 1, 2008 | Permit id: 183709 | |||||
SCORE 100 Installation of (2) gang bathrooms on 5th and 6th floors (work space is under 10 square feet per bathroom) Date: November 7, 2008 Contractor: Lgb Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 26, 2008 | Permit id: 187229 | |||||
SCORE 100 Tenant fitout per plan - ground floor penndot drivers license center Date: February 5, 2009 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: May 29, 2009 | Permit id: 198673 | |||||
SCORE 92 Furnish and install 26 plenum cat5e cables & 62 plenum rated cat 6 cables, avg cable 1 feet, as per 2005 nec (cc dist) Date: March 6, 2009 Contractor: Donald Belles Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: December 23, 2010 | Permit id: 201277 | |||||
SCORE 100 Fast form building permit Date: February 24, 2009 Contractor: Metropolitan Fire Protection Client: Arch Partners Lp | Permit status: Completed | Completion date: October 9, 2009 | Permit id: 202375 | |||||
SCORE 100 Installation of mens and ladies room, consisting of three water closets, one urinal, four lavatories, water cooler, mop sink and breakroom sink Date: March 5, 2009 Contractor: Lgb Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 11, 2009 | Permit id: 203538 | |||||
SCORE 100 Install ductwork and mechanical units. Date: April 7, 2009 Contractor: Edward B Oreilly And Assoc Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: May 29, 2009 | Permit id: 203898 | |||||
SCORE 100 Tenant fit-out Date: June 8, 2010 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: August 24, 2010 | Permit id: 279356 | |||||
SCORE 100 Relocate sprinkler heads Date: June 16, 2010 Contractor: Oliver Sprinkler Co Inc Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: August 11, 2010 | Permit id: 284637 | |||||
SCORE 100 Tenant fit-out of existing space. New lights & receptacles with branch circuit wiring to existing panels includes additional hvac circuits. Fire alarm work is by others as per 2008 nec Date: July 16, 2010 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: December 6, 2010 | Permit id: 285205 | |||||
SCORE 100 Install 8 owner supplied vav boxes with ductwork and diffusers per plan. Date: July 23, 2010 Contractor: Edward B Oreilly And Assoc Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: August 24, 2010 | Permit id: 286311 | |||||
SCORE 96 Hvac and ductwork per submitted sealed plans. Date: September 10, 2008 Contractor: J Rihl Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 17, 2008 | Permit id: 166051 | |||||
SCORE 82 Erect a flat wall sign as per plans Date: August 18, 2008 Contractor: Monster Signs And Metal Inc Client: Arch Partners Lp | Permit type: Sign permit | Permit status: Completed | Completion date: October 17, 2008 | Permit id: 167532 | |||||
SCORE 100 Tenant fit to off spas:furn inst (705) lt fixts,(1)400a panel,(2)225a panel,(1) kva trans,(251) swits,(329) receps,(44) furn. Cont,(3) boilers,( ex. Fans,(33)hvac units,(7)hot wtr htrs, (7) fa pull stats,(48) fa horn strobes,(44) fa strobes,per 2005nec nfpa-72(cc) Date: August 25, 2008 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: February 5, 2009 | Permit id: 168795 | |||||
SCORE 92 Furnish and install 123 cat5e plenum cables, 133 cat6 plenum cables on the 4th floor, 112 cat5e plenum cables, 56 cat 6 plenum cables on 2nd fl, 16 cat 5e plenum cables, 42 cat 6 plenum cables on the 1st fl as per 2005 nec (cc district) Date: October 1, 2008 Contractor: Donald Belles Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: December 23, 2010 | Permit id: 169451 | |||||
SCORE 100 Fixture installation and water heater replacement. Exsisting 6 story bldg. 1,2,&4 floors. Date: August 14, 2008 Contractor: Lgb Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 27, 2008 | Permit id: 169956 | |||||
SCORE 72 Interior alterations as per submitted sealed plans. Date: September 9, 2008 Contractor: Re Struction Llc Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: October 21, 2008 | Permit id: 170763 | |||||
Certificate of occupancy not required for tax abatement for improvements Date: October 21, 2008 Client: Arch Partners Lp | Permit type: Administrative permit | Permit status: Completed | Completion date: November 17, 2008 | Permit id: 171959 | |||||
Fast form building permit Date: September 9, 2008 Client: Arch Partners Lp | Permit status: Completed | Completion date: August 28, 2009 | Permit id: 175964 | |||||
SCORE 100 Fast form building permit Date: September 30, 2008 Contractor: Metropolitan Fire Protection Client: Arch Partners Lp | Permit status: Completed | Completion date: August 28, 2009 | Permit id: 178517 | |||||
SCORE 100 Interior alterations in areas as indicated, partial tenant fit out of existing office space, upgrades to finishes, corridors, bathrooms, as per submitted plans. Date: October 3, 2008 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: May 29, 2009 | Permit id: 178760 | |||||
SCORE 100 Tenant fit-out to create office space Date: October 3, 2008 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: May 29, 2009 | Permit id: 178767 | |||||
SCORE 100 Install 1 set of channel letters to front wall per plans. Date: October 15, 2008 Contractor: Pro Sign Co Client: Arch Partners Lp | Permit type: Sign permit | Permit status: Completed | Completion date: December 5, 2008 | Permit id: 180191 | |||||
SCORE 100 Add 1-duplex recpt in wall connect to existing 20amp circuit as per nec 2008 (comm) Date: April 24, 2013 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: June 26, 2013 | Permit id: 466981 | |||||
SCORE 100 Add 1-floor recpt connect to existing 20amp circuit as per nec 2008 (comm) Date: April 24, 2013 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: June 26, 2013 | Permit id: 466983 | |||||
SCORE 100 Extend existing ductwork with installation of fire dampers in fire rated assemblies. Date: November 14, 2014 Contractor: Edward B Oreilly And Assoc Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Expired | Completion date: January 12, 2016 | Permit id: 568152 | |||||
SCORE 100 Furnish and install 1 receptacle with circuit connected to existing panel per 2008 nec (office space) Date: August 28, 2012 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: October 2, 2012 | Permit id: 424372 | |||||
SCORE 82 Install a new amp recept for monitor as per nec 2008 (office bldg) Date: October 9, 2012 Contractor: Dg Electrical Contractors Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: December 11, 2012 | Permit id: 431443 | |||||
SCORE 100 Install 17 diffusers Date: October 27, 2011 Contractor: Edward B Oreilly And Assoc Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 6, 2011 | Permit id: 370967 | |||||
SCORE 100 Tenant fitout to create an office suite Date: May 10, 2012 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 398548 | |||||
SCORE 96 Install (1) toilet, (1) tub (rough & finish) Date: March 27, 2008 Contractor: J Rihl Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 21, 2008 | Permit id: 139560 | |||||
SCORE 99 Replacing 14 existing fluorescent 2x4 fixtures with new ones, 1 new exit light, 1 new emerg wall pack with remote head capability, 2 new remote e-light head to cover front entrance and bathroom, new gfci in bathroom as per 2005 nec (cc district) Date: April 15, 2008 Contractor: William Enley Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: October 7, 2008 | Permit id: 145489 | |||||
SCORE 100 Installation of restroom with toilet and lavatory; install (3-5)sinks in exam rooms, soil and waste, Date: October 14, 2011 Contractor: Lgb Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 21, 2011 | Permit id: 368247 | |||||
SCORE 100 Provide and install 45 cat 6 plenum cable for voice and data applications. Install client network equipment as per 2008 nec (1st floor health care facility)(cc dist) Date: December 12, 2011 Contractor: Bluestone Communications Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: February 15, 2012 | Permit id: 370594 | |||||
Enclose walls to enclose bathroom - install 2" x 4" ceiling grid on entire 1st floor as per plans Date: March 13, 2008 Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: May 27, 2008 | Permit id: 134339 | |||||
SCORE 100 Revise existing automatic sprinkler system Date: March 10, 2008 Contractor: Metropolitan Fire Protection Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: August 11, 2008 | Permit id: 134709 | |||||
Structural modifications to existing shaft, demo, remove & replace existing elevator, shaft, upgrade new equipment, finishes, as per submitted plans. Date: February 26, 2008 Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: November 17, 2008 | Permit id: 130289 | |||||
SCORE 100 Interior alterations, upgrades to finishes for existing office space. No change in use-occupancy classification. Date: October 4, 2011 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: December 6, 2011 | Permit id: 362095 | |||||
SCORE 100 Relocate (33) sprinklers on 1st floor Date: September 27, 2011 Contractor: Oliver Sprinkler Co Inc Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: December 6, 2011 | Permit id: 365292 | |||||
SCORE 92 Furnish and install 36 light fixtures, 12 switches, receptacles, 1 hot water heater connection. All new wiring to existing panel as per 2008 nec office space Date: September 29, 2011 Contractor: Goldsmith Gary A Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: December 15, 2011 | Permit id: 365710 | |||||
SCORE 100 Installing a nac power booster in this suite to handle their strobes,their are existing pull station this suite, there are no change to the maain fire alarm panels voltage drops as per 2008 nec,nfpa-72 Date: October 21, 2011 Contractor: Kartman Fire Protection Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Expired | Completion date: October 21, 2011 | Permit id: 368008 | |||||
SCORE 100 Interior fit out of 1st 2nd and 4th fl. Offices on 2nd thru 4th floors only per submitted sealed plans. Date: July 28, 2008 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: November 17, 2008 | Permit id: 163487 | |||||
SCORE 100 Fast form building permit Date: July 16, 2008 Contractor: Oliver Sprinkler Co Inc Client: Arch Partners Lp | Permit status: Completed | Completion date: June 30, 2010 | Permit id: 164711 | |||||
SCORE 92 Tenant fit out of existing space,29 lights fixtures, 2 exit emergency fixtures, receptacless, 8 single pole switches all new wiring to existing panel as per 2008 nec Date: December 28, 2010 Contractor: Goldsmith Gary A Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: March 15, 2011 | Permit id: 318328 | |||||
SCORE 100 Install (3) vav boxes, ductwork and grilles for office @ 5th floor Date: May 2, 2011 Contractor: Edward B Oreilly And Assoc Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: May 12, 2011 | Permit id: 321348 | |||||
SCORE 100 Relocate existing heads from above coverage to new drop ceiling in 5th floor. Date: January 21, 2011 Contractor: Metropolitan Fire Protection Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: February 15, 2011 | Permit id: 321769 | |||||
SCORE 92 Furnish and install (35) category 5e plenum cables and (90) category 6 plenum cables, average cables pull 1 feet as per 2008 nec (cc dist) Date: August 3, 2010 Contractor: Donald Belles Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: December 23, 2010 | Permit id: 286803 | |||||
SCORE 100 Installation of coffee sink on 5th floor Date: June 25, 2010 Contractor: Lgb Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 24, 2010 | Permit id: 287604 | |||||
SCORE 100 For interior alterations to include new partition walls and new suspended ceiling for office as per plans. Date: January 13, 2011 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: February 15, 2011 | Permit id: 316683 | |||||
SCORE 100 F&i 441 new cat5e plenum voice and data cables,longest run 285 ft. Terminate,test and label all new cabling in existing equip racks. Support all cabling per code. F&i 441 new plenum patch cords at closet end per 2008 nec (office space)cc district Date: August 16, 2016 Contractor: Bluestone Communications Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: November 8, 2016 | Permit id: 707617 | |||||
SCORE 100 Interior plumbing alterations to create new office spaces on the first, second, and sixth floors of an existing high-rise office building - the installation will comply with the approved plans and the philadelphia plumbing code 2004 Date: August 25, 2016 Contractor: E J Raith Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 20, 2016 | Permit id: 701191 | |||||
SCORE 100 Remove existing flat roofing. Install new 3. 5" poly iso insulation to concrete deck. Adhere gaf . 0 tpo membrane with all new tpo accessories. Date: June 27, 2016 Contractor: C And G Contracting Co Inc Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: October 31, 2016 | Permit id: 702724 | |||||
SCORE 99 For the installation of one (1) type 1 commercial kitchen hood , supply exhaust ductwork, and exhaust fan as per approved plans. Exhaust fan location shall comply with section 506. 3. 12 of the 2009 imc. See ap#695489 for approved plans. Date: June 30, 2016 Contractor: Hunter Mechanical Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: March 20, 2017 | Permit id: 703459 | |||||
SCORE 100 For the erection of a new trash enclosure with protective bollards and screen fence on the exterior of an existing office building as shown in approved plans. Date: July 12, 2016 Contractor: Northwood Construction Company Client: Arch Partners Lp | Permit type: Alteration permit | Permit status: Completed | Completion date: December 21, 2016 | Permit id: 692908 | |||||
SCORE 100 Relocate (213) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. Date: May 26, 2016 Contractor: A And S Sprinkler Co Inc Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: March 20, 2017 | Permit id: 695445 | |||||
SCORE 100 Renovation to existing space install 52-horn strobe, 4-strobe, 5-smoke detector, 5-power supply as per nfpa 72 cc district Date: September 15, 2016 Contractor: New Light Electric Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: October 26, 2016 | Permit id: 714108 | |||||
Certificate of occupancy not required: office. Retail commercial 1st floor and offices 2nd to 6th floors note: "certificate of occupancy not required" document forwarded to district office. Call district office for inspection and issuance of"certificate of occupancy not required" document Date: February 12, 2009 Client: Arch Partners Lp | Permit type: Administrative permit | Permit status: Completed | Completion date: March 17, 2009 | Permit id: 198497 | |||||
SCORE 99 For the installation of an hvac system to include registers diffusers, supply exhaust ductwork, vav boxes, fpb boxes, appliances, commercial kitchenhood with exhaust duct work and exhaust fan, and all other work as per approved plans. Separate permit required for electrical and plumbing work. Date: June 30, 2016 Contractor: Hunter Mechanical Inc Client: Arch Partners Lp | Permit type: Mechanical permit | Permit status: Completed | Completion date: March 19, 2017 | Permit id: 695489 | |||||
SCORE 100 Tenant fit out including new lighting,receptacles,system furniture connection and hvac power wiring. Instal low voltage tele data and control wiring per 2008 nec (office space)cc district Date: September 9, 2016 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 695930 | |||||
SCORE 100 Renovation to existing space for new tenant,install 496 light fixtures,175 light switch,647 receptacles,15 furniture feed,11 hvac feed,(1) 208 1 volt panel,(1) 480 277 volt panel,(1) 45 kva transformer and 1 meter as per 2008 nec (cc district) Date: July 28, 2016 Contractor: New Light Electric Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: October 5, 2016 | Permit id: 697111 | |||||
SCORE 100 Tenant fitout of space including 27, 2x4 lay in fixtures, duplex receptacles, switches, all wiring to existing 200amp panel as per 2008 nec (cc dist) office Date: April 27, 2012 Contractor: Goldsmith Associates Inc Client: Arch Partners Lp | Permit type: Electrical permit | Permit status: Completed | Completion date: July 18, 2012 | Permit id: 401754 | |||||
SCORE 100 1 sink Date: May 18, 2012 Contractor: Lgb Mechanical Inc Client: Arch Partners Lp | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 28, 2015 | Permit id: 405865 | |||||
SCORE 100 Relocating (20) sprinklers on the 5th floor in hydrogeologic Date: May 18, 2012 Contractor: Oliver Sprinkler Co Inc Client: Arch Partners Lp | Permit type: Suppression permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 405967 |