Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Temp power for cedar kettner parking structure pds2013-ldgrmj-000033 pds2013-compri-0000 not issued at this time use ia# cofd7416-00007 for all pds charges in kronos Date: March 13, 2014 Contractor: Dynalectric Company Permit type: Commercial alteration-addn | Permit status: Issued expired | Permit id: Pds2014-Comalt- | |||||
SCORE 92 221,291 sqft parking structrure ( stories) to include 2773 sqft (15) utility rooms, 162 sqft office, 68 sqft bathroom for county of san diego cedar and kettner development project parking structure 7 10 15 deferred submittal -- fin system; see c of a... Vmt 6 26 15 deferred submittal -- elevators; see c of a... Vmt 6 8 15 3 deferred submittals -- rooftop canopy; stairs #1&2; handrails for stairs #1&2; see c of a... Vmt 4 24 15 plan change -- revised roof trellis framing; see c of a... Vmt 4 25 15 3 deferred submittals -- acm panels; storefront system - clark steel; storefront system - la mesa glass; see c of a... Vmt Permit type: New primary comm structure | Permit status: Completed | Completion date: November 18, 2015 | Permit id: Pds2013-Compri- | |||||
Final Date: November 13, 2015 Permit status: Pass | Permit id: Pds2013-Compri- | |||||
Foundation/steel/holdowns/abs/2nd Date: December 30, 2014 Permit status: Fail | Permit id: Pds2013-Compri- |